diff_months: 9

Professional Assignment

Download Solution Now
Added on: 2023-09-06 05:34:28
Order Code: CLT318619
Question Task Id: 0
  • Country :

    Australia

Introduction

In the construction industry, effective project management and compliance with contractual obligations are critical to the successful completion of any project and this report examines a landmark development project led by Australian mid-market Illy Construction. Located in the city’s Central Business District (CBD) in New South Wales, the project follows the traditional procurement process and uses the AS4000-1997 Standard Form Contract.

The report focuses on a critical period in the life of the project, where construction is taking place and structural defects in frames become apparent This requires a comprehensive analysis of the contractual implications, changes and subsequent changes in the scope of the project. As the contract manager appointed on behalf of the contractor, this report seeks to provide the circumstances, actions taken and steps necessary to effectively manage changes during construction (Heckathorn & Maser, 1990).

The main areas this report will examine that we will examine are the contractual structure governing the project, communication between parties, the impact of changes on project scope, and the process of preparing progress statements to reflect changes revealed.

Basic principles of contract law applicable to construction contracts:

Contract law forms the backbone of construction contracts, providing the legal framework within which the parties to the construction project operate. These principles include:

Offer and Acceptance: A contract begins with an offer by one party and acceptance by the other. In construction, a proposal is usually submitted by tender or proposal, and acceptance occurs when the principal awards the contract to the selected contractor e.g., clause 4.1 of the AS4000-1997 contract explains contract commencement date based on acceptance of the proposal.

Intent to create a legal relationship: The parties entering into a construction contract must intend it to be legally binding. This principle ensures that the parties are committed to fulfilling their contractual obligations (Lu et al., 2015).

Measurement: A valid contract requires the exchange of any value (measurement) between the parties. In construction, this may involve monetary exchange of goods and services. As paragraph 7.1 of AS4000-1997 sets out employees’ rights to payment as consideration for work.

Use of Construction Contracts:

Standard construction contracts, such as AS4000-1997, are pre-written agreements that follow established industry practices and are recognized by the regulatory framework They offer a range of benefits:

Clarity and consistency: Unwavering font application allows language and structure to remain cohesive, staying away from disputable wordings.

Legal precedents: Through successive litigations, the documents endeavour to elucidate legal precepts and the manner in which they ought to be understood via careful interpretation. Time and Cost Efficiencies: Time saved and expenses curtailed via preconditioned contract formats.

Benefits of implementing AS4000-1997:

Among the country's renowned standards, AS 4000-1997 offers guidance relevant to Australia's $38b building market, the benefits include:

Appropriate risk allocation: Offering a balanced distribution of risk among clients and principals, while promoting openness and fairness.

The industry's broadest coverage encompasses extensive modification, payment, and conflict resolution areas through this versatile collection of standards (AS4000-1997). Eliminating redundant drafts is now more convenient than ever before with up-to-date guidelines at your disposal. This streamlined process ensures easier management across all sectors by minimizing protocol repetition while ensuring compliance remains intact throughout projects completion. By adhering strictly to these relevant requirements specified herein enabling stakeholders save money time whilst maintaining sound business practice is integral part every initiative! Even experienced professionals enjoy problem solving opportunities presented here so don't miss out on valuable insights shared below any further ado make sure check out complete details available within link provided originally alongside relevant supporting documentation – then plan accordingly following template structure defined next section below

Legal Certainty: Using precise details within the agreement minimizes opportunities for arguments and guarantees legislative consistency for involved entities (Murdoch & Hughes, 2002).

Compliance: Industry compliance makes way for secure constructions.

Modification: Allowing them to customize according to each project's needs, AS4007-1997 comprises a collection of steps.

Draft progress claim:

Progress Claim for Construction Work:

  • Claim Number
  • Date of Claim
  • To: [Principal's Name]
  • Project
  • Contract Reference
  • Contractor
  • ABN
  • Address
  • Contact Person
  • Phone
  • Email

Work performed:

Elaborate on the specific accomplishments finished throughout the receiving interval. Can you supply information about how many projects there are and whether they have been expanded or reduced in magnitude since their inception? If relevant specifications or drawings are available, please include them with your submission.

Progress achieved:

Please inform on about how well the undertaking has advanced via reaching notable marks/processes compare. Progress against timeline differences in modifications.

Document any approved changes or modifications affecting the project during the receipt period. Include information describing the order of the variables and their values.

Materials and equipment:

Detail any materials, equipment or facilities provided and used in the construction work by your company during the collection period. Provide quantity and cost descriptions.

Subcontractor Fees:

Record any subcontractors involved in the project and the payments made to them during the receipt period. Include their name, ABN, occupation, and payment amount.

Retention Amount:

Determine the amount the principal is required to pay in accordance with the terms of the contract, if applicable.

Fee Claims:

Provide a summary of all work completed during the receipt period. Divide the claims into the following categories.

  • Completed work: $[amount].
  • Difference $[amount].
  • Materials/equipment: $[amount].
  • Subcontractor payment: $[cash].
  • Attention: $[amount].
  • Total Amount Required: $[total amount].
  • Payment Schedule:

Include a payment schedule for claims, which lists due dates, payment methods, and any specific payment instructions.

Miscellaneous:

Attach any supporting documents that support the transaction, such as invoices, receipts, progress reports and change orders.

Declaration:

I hereby certify that the information provided in this development statement is accurate and in accordance with the terms of the agreement. I am requesting payment as outlined in this article and understand that the principal may issue a payment plan in response.

The legitimate time extension claims that the contractor can make pursuant to the given scenario and the procedure/s to be followed:

In the given scenario, the contractor encountered structural defects in the beam shape during the construction of a four-storey building. The inspector has provided new construction drawings and instructions on how to demolish the existing irregular trees and replace them with new trees of appropriate specifications. As a result, the level of operations has increased dramatically, creating potential delays. Here we will break down and discuss the relevant time extension claims that an employee may make:

  1. Differences and adjustments in planning:
    Explanation: Dismantling and replacing incorrect frames requires a series of design changes initiated by the inspector.
    Qualification of Extension of Time: The Contractor may claim an extension of time for the additional work required to demolish, remove and replace, as it was not part of the original contract (Puddicombe, 2009).
    Procedure: The Contractor shall document the changes including the Administrator's written instructions, revised drawings and specifications. These documents serve as evidence of the design changes and their impact on the project timeline.
  2. Delay in submission of revised drawings:
    Explanation: The inspector noticed a design discrepancy and provided revised architectural drawings.
    Reasonable extension of time: Contractors can claim extension of time due to late submission of revised drawings.
    Procedure: The Contractor shall maintain a record of when the original plan discrepancy was discovered, when the Superintendent was notified, and the date of the corrected drawings. These records help identify delays and their impact on the project schedule.
  3. Impact on subcontractors:
    Explanation: Contractor submitted a variance request and made a revised order that subcontractors perform demolition and replacement work.
    Due extension of time clause: Contractor may request extension of time for any delay caused by subcontractors due to variation.
    Procedure: The Contractor should gather evidence of receipt of change orders from subcontractors, as well as any communication regarding the impact on their systems. These documents support the time dilation argument.
  4. Overtime analysis:
    Explanation: The Contractor shall estimate the additional time required to complete the demolition and replacement of the beam in accordance with the revised drawings.
    Reasonable Extension of Time: The Contractor may request an extension of time based on a reasonable evaluation of the added working hours.
    Procedure: The Contractor shall thoroughly evaluate the scope of the project, taking into consideration factors such as workload complexity, resource availability, and potential delays due to weather. This analysis forms the basis for the time dilation issue.
  5. Compliance with the terms of the Agreement:
    Explanation: The contract (e.g., AS4000-1997) may include provisions for requiring extensions of time for modifications and changes in design.
    Due extension clause: The contractor must comply with the specific provisions of the contract regarding extension clauses, including giving written notice to the principal and providing supporting documentation.
    Procedure: The contractor should review the contract and understand the requirements for time extension clauses and ensure that these procedures are followed.

The legitimate loss and expense claims that the contractor can make pursuant to the given scenario and the procedure/s to be followed:

In the given scenario, the contractors encountered architectural defects in the frame design during the construction of a four-storey building. The inspector has provided new construction drawings and instructions on how to demolish the existing irregular trees and replace them with new trees of appropriate specifications. This increased production and additional costs. Here we will break down and measure the reasonable losses and expenses that contractors can include:

  1. Demolition and replacement costs:
    Explanation: The Contractor incurred additional costs for demolition of existing damaged trees and installation of new trees in accordance with revised drawings.
    Eligible Losses and Costs: The manufacturer may claim direct costs associated with tree dismantling, removal and replacement, including labor, materials, equipment, and remediation charges around.
    Procedure: The Contractor shall maintain detailed records of all costs associated with demolition and replacement work, including invoices, receipts and time sheets. These records are proof of actual expenses.
  2. Extended labor costs:
    Explanation: The extended project required additional hours of work to complete the demolition and replacement.
    Statutory Losses and Expenses: The builder can claim extended labor costs due to delays in the work (Reve & Levitt, 1984).
    Procedure: The Contractor shall monitor overtime hours worked by its employees and subcontractors, especially those associated with demolition and replacement projects. Time records and payrolls attest to this expansion of labor costs.
  3. Cost of equipment rental:
    Explanation: The contractor may have to hire special tools or machinery for the dismantling and replacement operations.
    Statutory losses and costs: The builder can claim costs associated with renting the equipment required for the new scope.
    Procedure: Contractor should maintain rental agreements, invoices and receipts relating to equipment rentals to support this claim.
  4. Material Costs:
    Explanation: Additional materials, such as properly labelled timber, may be required for replacement purposes.
    Statutory Losses and Expenses: The contractor may claim the cost of purchasing additional supplies.
    Action: The Contractor shall maintain orders, receipts, and invoice records to show the required materials and the purchase price.
  5. Subcontractor Comments:
    Details: Small businesses affected by changes and delays may apply for additional costs. Statutory Losses and Expenses: The Contractor may claim additional costs from reasonable subcontractor requirements related to project interruption.
    Procedure: The Contractor shall document and verify subcontractor claims and maintain records of negotiations and agreements with subcontractors.
  6. Resources and Priorities:
    Explanation: Overhead expenses such as office rent, insurance, and administrative costs may increase as the duration of the project is extended.
    Statutory Losses and Expenses: The Contractor may claim additional costs for the work as well as upfront costs incurred due to the delay in the work.
    Procedure: The Contractor shall record and allocate overhead costs directly related to the delay and record these costs.
  7. Compliance with the terms of the Agreement:
    Explanation: The contract (e.g., AS4000-1997) may include provisions for claiming cost losses.
    A valid loss and expense claim requires the contractor to follow specific contractual procedures for claiming losses and expenses, including written notice to the principal and supporting documentation (You et al., 2018).
    Procedure: The contractor should review the contract and understand the requirements for loss and expense coverage and ensure that these procedures are followed.

Are you struggling to keep up with the demands of your academic journey? Don't worry, we've got your back! Exam Question Bank is your trusted partner in achieving academic excellence for all kind of technical and non-technical subjects.

Our comprehensive range of academic services is designed to cater to students at every level. Whether you're a high school student, a college undergraduate, or pursuing advanced studies, we have the expertise and resources to support you.

To connect with expert and ask your query click here Exam Question Bank

  • Uploaded By : Mohit
  • Posted on : September 06th, 2023
  • Downloads : 0
  • Views : 83

Download Solution Now

Can't find what you're looking for?

Whatsapp Tap to ChatGet instant assistance

Choose a Plan

Premium

80 USD
  • All in Gold, plus:
  • 30-minute live one-to-one session with an expert
    • Understanding Marking Rubric
    • Understanding task requirements
    • Structuring & Formatting
    • Referencing & Citing
Most
Popular

Gold

30 50 USD
  • Get the Full Used Solution
    (Solution is already submitted and 100% plagiarised.
    Can only be used for reference purposes)
Save 33%

Silver

20 USD
  • Journals
  • Peer-Reviewed Articles
  • Books
  • Various other Data Sources – ProQuest, Informit, Scopus, Academic Search Complete, EBSCO, Exerpta Medica Database, and more