diff_months: 11

Chain Scheduling Assignment

Download Solution Now
Added on: 2023-06-16 13:15:09
Order Code: SA_34507_273
Question Task Id: 0
  • Country :

    Australia

Question-1

  1. Critical Chain Scheduling places a strong emphasis on efficient project buffer management. Instead of adding buffers to each individual task, the project schedule consolidates buffers and places them at key intervals. These safety nets shield the project from unforeseen events and delays, enabling better resource management.
    Resource Levelling: Critical Chain Scheduling takes resource restrictions and availability into account while planning a project. The scheduling approach seeks to get rid of resource bottlenecks and optimize resource allocation over the course of the project by balancing resource utilization across jobs.
    Feeding Buffer: Prior to jobs that feed critical chain tasks in critical chain scheduling, a feeding buffer is introduced. The feeding buffer aids in preventing delays brought on by non-essential processes that could affect key chain tasks. The whole project schedule can be better managed by concentrating on the critical chain and controlling the feeding buffers.
  2. Paths in the Network Diagram along with their lengths or duration:
    Path 1-2-6-7: A + C + G = 2 + 6 + 3 = 11
    Path 1-3-4-6-7: B + D + F + G = 3 + 2 + 2 + 3 = 10
    Path 1-3-5-7: B + E + I = 3 + 3 + 4 = 10
    Path 1-3-4-7: B + D + H = 3 + 2 + 4 = 9
    The shortest amount of time needed to complete this project is the duration of the shortest path, which is 9 units of time (Path 1-3-4-7).

Question-2

  1. mm1-1686919378.jpg
  2. Cost Variance (CV): The CV is determined by comparing Earned Value (EV) to Actual Cost (AC). The project is above budget in this scenario because the CV is -$537. The negative value raises the unfavorable possibility that actual expenses exceed earned value.
    Schedule Variance (SV): The SV is determined by subtracting the Actual Value (EV) from the Planned Value (PV). The project is behind time in this case since the SV is $785. The project may have accomplished less work than anticipated at this time, according to the negative value. Cost Performance Index (CPI): The ratio of EV to AC is used to calculate the CPI. The CPI in this instance is 0.286, which shows that the project is operating below budget. If the CPI is less than 1, it is likely that the project's expenses will be greater than expected.
    Index of Schedule Performance (SPI): The EV to PV ratio is used to calculate the SPI. The SPI in this case is 0.215, which shows that the project is moving more slowly than anticipated. If the SPI is less than 1, the project is running behind schedule.
    These EVM indices make it clear that the project is having difficulties with its cost and schedule performance. Due to cost overruns and delays in completing the scheduled work, the project is over budget and behind schedule.
    The project's cost and schedule irregularities are indicated by the negative CV and SV values as requiring corrective action. The SPI denotes that the project is not moving along according to schedule, and the CPI suggests that the project is not effectively using its budget.
    These indicators show that the project team must take the necessary steps to bring expenses under control, increase schedule adherence, and restart the project. It may be required to conduct further research and make changes to the project's execution plan to make sure it can be finished within the specified time and financial limits.
  3. mm2-1686919379.jpg

Question-3

mm3-1686919382.jpgmm5-1686919393.jpg

Question-4

The widely used Tuckman five-stage model of team development outlines the various phases that teams experience as they develop and mature. The phases are Forming, Storming, Norming, Performing, and Adjourn. The phases are listed below, along with a team management activity for every stage:

Forming: Team members gather and become used to one another during this initial phase of formation. Facilitating team introductions and defining clear goals and objectives are two team management tasks that can be completed at this time. In order to do this, you might plan team-building exercises, hold icebreaker activities, and specify the goal and parameters of your team's work.

Storming: As team members begin to voice their thoughts and define their roles, conflicts, and differences of opinion may appear. Encourage open communication and use constructive conflict resolution as one team management task during this phase. Building a supportive and cooperative team atmosphere may entail leading team conversations, encouraging active listening, and applying dispute-resolution strategies.

Norming: During this phase, team members begin to build trust and unity. They create group dynamics, norms, and values. Encourage and support the creation of team norms and agree on expectations as one team management task during this phase. This may entail leading group talks to create ground rules, defining team ideals, and promoting respect and collaboration between team members.

Performing: The team is at its most effective and productive during the performing stage. Team members collaborate, make use of their knowledge and abilities, and accomplish their objectives. Supporting continued cooperation and performance is one team management task at this level. This can entail holding regular team meetings to track development, offering tools and encouragement to get around difficulties, and praising and recognizing the accomplishments of the team.

Adjourning: When the team disbands or the project is finished, the team enters the adjourning stage, also referred to as the mourning stage. Assisting team members in a proper closure and transition is one team management task at this point. This may entail planning a team reflection meeting to discuss the team's successes, expressing thanks for each team member's contributions, and helping team members transfer to new tasks or projects.

Question-5

  1. In project management, there are four distinct risk response methodologies that are covered:
    Avoid: By taking steps to prevent it from happening, this strategy seeks to eliminate the risk. It entails assessing the risk and altering the project's scope or plan to prevent any potential drawbacks.
    Transfer: Using this tactic, the obligation to manage the risk is transferred to a different party. It entails contracting or exporting the risk to a different entity that is more suited to managing the risk and its repercussions, such as an insurance provider or vendor.
    Mitigate: This approach aims to lessen the risk's effects or likelihood. It entails taking proactive steps to reduce the risk's possible negative impacts. This may entail putting safety measures in place, carrying out exhaustive testing, or creating backup plans.
    Accept: Sometimes avoiding, shifting, or mitigating a risk may not be practical or economical. The approach under these circumstances is to take the risk. This entails being aware of the risk's existence and ready to handle any potential repercussions should it materialize. It may entail developing a backup strategy or laying aside funds to handle unforeseen problems.
  2. The following four hazards in the project to construct the financial system, each with a different impact and probability, are listed together with the selected risk management technique:
    Risk: Software compatibility issues with existing systems
    Impact: Medium
    Probability: High
    Response Strategy: Mitigate

Justification: It is crucial to take proactive efforts to reduce the effects of this risk due to its high probability and medium impact. Software compatibility problems can be reduced by implementing extensive testing, performing system compatibility checks, and involving subject matter experts.

Risk: Loss of key project team members
Impact: High
Probability: Medium
Response Strategy: Transfer

Justification: Transferring this risk to a third party, like a recruiting agency or consulting firm, can assist assure the project's continuity in case of unexpected departures. This is because the loss of important team members can have a severe impact on the project.

Risk: Inadequate stakeholder engagement
Impact: Low
Probability: Medium
Response Strategy: Accept
Justification: Accepting this risk might be the most sensible course of action given the low impact and medium probability. It entails accepting the possibility that stakeholder participation may not be ideal and being ready to handle any problems that may arise as a result as they occur.

Risk: Security breach or data loss
Impact: High
Probability: Low
Response Strategy: Avoid

Justification: Since the likelihood of a security breach or data loss is low but its impact is great, it is imperative to take precautions. This can entail putting in place strong security measures, performing frequent audits, and adhering to best practices for data protection.

Question-6

  • The work breakdown structure (WBS) for the Work&Fun Project are:
    1. Project: Work&Fun Project
    1.1 Project Initiation
    1.2 Project Planning
    1.3 Project Execution
    1.4 Project Monitoring and Control
    1.5 Project Closure
    2. Application Development
    2.1 Requirements Gathering and Analysis
    2.2 System Design and Architecture
    2.3 User Interface Design
    2.4 Application Development and Programming
    2.5 Testing and Quality Assurance
    2.6 Deployment and Rollout
    3. 4Registration for Recreational Programs
    3.1 Program Selection and Setup
    3.2 Registration Form Design and Development
    3.3 Database Integration for Registration Data
    3.4 User Notifications and Confirmations
    4. Registration for Health-Management Programs
    4.1 Program Selection and Setup
    4.2 Registration Form Design and Development
    4.3 Database Integration for Registration Data
    4.4 User Notifications and Confirmations
    5. Reporting System
    5.1 Database Design for Program Data Storage
    5.2 Reporting Requirements Gathering
    5.3 Report Design and Development
    5.4 Integration of Reporting System with Application
    6. Rewards and Incentives
    6.1 Incentive Program Design and Planning
    6.2 Integration of Incentives with Application
    6.3 Tracking and Verification of Achievements
    6.4 Rewards Fulfillment and Distribution
    7. Data Management
    7.1 Database Design and Development
    7.2 Data Security and Privacy Measures
    7.3 Data Backup and Recovery Procedures
    7.4 Data Integration and Synchronization
    8. Documentation and Training
    8.1 User Documentation Preparation
    8.2 Training Material Development
    8.3 User Training Sessions
    9. Project Management and Coordination
    9.1 Project Schedule Development and Tracking
    9.2 Resource Allocation and Management
    9.3 Risk Identification and Management
    9.4 Stakeholder Communication and Coordination
  • Three scope control methodologies or techniques are as follows:
    Scope Baseline: To establish a scope baseline, the project's scope, including its deliverables, objectives, and requirements, must be defined. Stakeholders must also formally approve the baseline. As a point of reference for the project, the scope baseline helps to ensure that any changes or additions to the scope are correctly assessed and regulated.
    Change scope Process: Scope changes can be managed and controlled by implementing a change control process. As part of this procedure, requested changes must be evaluated, documented, and assessed in order to determine how they will affect the project's goals, timeline, and budget. Finally, they must receive formal approval before being put into action. Unneeded or unapproved scope modifications can be avoided by using a structured change control approach.
    Scope Verification and Validation: Scope verification entails checking that the project deliverables have been completed and adhere to the scope baseline as well as the agreed-upon requirements. Contrarily, scope validation entails getting formal acknowledgment and agreement from stakeholders that the project deliverables match their requirements. Any deviations or consistency issues in the project's scope can be found and fixed through the scope verification and validation processes.
    Scope creep is the unplanned and unrecorded extension of a project's scope past its initial limitations. It happens when new specifications, features, or deliverables are included in a project without adequate review, permission, or management. Scope creep frequently occurs because of Poor initial Scope Definition: Scope creep can result from inadequate planning, ambiguous requirements, or a lack of stakeholder interaction during the scope definition phase. When the scope is not clearly specified at the outset, it is simpler to add new requirements as the project is being carried out.
    Changing stakeholder expectations: As the project moves forward, stakeholders may create new requirements or change current ones in response to shifting market conditions or customer demands. If these modifications are not adequately assessed and managed, scope creep may develop.
    Ineffective change management: Changes in the scope might become out of control and cause scope creep. Scope creep is made more likely without a structured change control procedure because it becomes difficult to distinguish between necessary and valid scope changes.

Among the effects of scope creep are:

Schedule Delays: Project delays due to schedule overruns and additional scope are common and frequently originate from the need for more time to complete the work.

Budget overruns: As more resources, materials, or labor are required to meet the scope creep, project costs may increase.

Quality reduction: Project teams may need to hustle or make compromises to fulfil the enlarged requirements when they are forced to manage uncontrolled scope changes.

The following steps can be done to avoid scope creep:

To ensure a shared knowledge of the project's goals and deliverables, thoroughly define and document the project's scope at the outset.

Set up a formal evaluation and approval procedure for all proposed scope adjustments as part of a change control process.

Review and evaluate requests for changes on a regular basis, taking into account how they will affect the project's goals, timetable, and budget before approving them.

With stakeholders, manage expectations in a clear and concise manner while stressing the value of staying within the predetermined scope.

Keep thorough records of all project revisions by maintaining good project documentation and recording any scope changes.

Are you struggling to keep up with the demands of your academic journey? Don't worry, we've got your back! Exam Question Bank is your trusted partner in achieving academic excellence for all kind of technical and non-technical subjects.

Our comprehensive range of academic services is designed to cater to students at every level. Whether you're a high school student, a college undergraduate, or pursuing advanced studies, we have the expertise and resources to support you.

To connect with expert and ask your query click here Exam Question Bank

  • Uploaded By : Katthy Wills
  • Posted on : June 16th, 2023
  • Downloads : 0
  • Views : 125

Download Solution Now

Can't find what you're looking for?

Whatsapp Tap to ChatGet instant assistance

Choose a Plan

Premium

80 USD
  • All in Gold, plus:
  • 30-minute live one-to-one session with an expert
    • Understanding Marking Rubric
    • Understanding task requirements
    • Structuring & Formatting
    • Referencing & Citing
Most
Popular

Gold

30 50 USD
  • Get the Full Used Solution
    (Solution is already submitted and 100% plagiarised.
    Can only be used for reference purposes)
Save 33%

Silver

20 USD
  • Journals
  • Peer-Reviewed Articles
  • Books
  • Various other Data Sources – ProQuest, Informit, Scopus, Academic Search Complete, EBSCO, Exerpta Medica Database, and more