List and discuss four project complexity factors.
Question 1:
List and discuss four project complexity factors.
Discuss two ways project managers can manage project complexity.
Please add only five (5) references to support your discussion in the two questions.
Whenever you need to quote ideas and/or the quotes of any other author, you should acknowledge this, using the Chicago referencing method (Chicago 17th B ed.)
Be approximately 500 to 600 words in length, excluding diagrams and references.
Question 2:
Develop a WBS (work breakdown structure) for the popular band COLDPLAY in Perth, Western Australia, on November 18 and 19, 2023; be sure to identify the deliverables and organisational units (people) responsible. Develop a corresponding OBS (Organisation Breakdown Structure) which identifies who is responsible for what.
Please use only MS Word applications for this question.
For each WBS task, please list the resource(s).
There is no need to add the time and cost for each WBS task.
Question 3:
Given the network plan that follows, compute the early, late, and slack activity times; determine the planned project duration; and identify the critical path.
Id Description Predecessor Time
A External Specifications None 3
B Review Design Features A 15
C Document New Features A 5
D Write Software A 60
E Program and Test D 6
F Edit and Publish Notes B 40
G Review Manual C, E 10
H Alpha Site F 7
I Print Manual and Beta Site G 6
J Manufacture and release H, I 12