Structures for Medium Rise Construction
Structures for Medium Rise Construction
CPCCBC5018AApply structural principles to the construction of medium rise buildings
It is a requirement that participants undertaking the short course Structures for Medium Rise Construction have successfully completed the following unit.
CPCCBC5001BApply building codes and standards to the construction process for medium rise building projects
Participant Name: Course Start Date:
Participant ID: Assessment Due Date:
Trainer Name: Kim Grossman Region:
FNQ
Assessment Instructions
Assessment for this unit/unit cluster is presented in two (2) Assessment Booklets. The following instructions apply to both Assessment Booklet 1 and Assessment Booklet 2
ASSESSMENT TASKS
The assessment is provided in Assessment Booklet 1 and Assessment Booklet 2. Both Assessment Booklets should be given to the participants at the commencement of the short course so that they are aware of the assessment expectations.
There are 7 Assessment Tasks to be completed satisfactorily by the participant in order to be deemed competent in this unit of competency:
Assessment Booklet 1 contains the following summative Assessment Tasks:
AT1 Written Questions 1.1 1.18
AT2 Verbal Questions 2.1 2.7
Feedback on your completion of these tasks will assist you in identifying areas where you may need to continue to develop skills and knowledge prior to completing the Assessment Tasks in Booklet 2.
Assessment Booklet 2 contains the following summative Assessment Tasks:
AT3 Short Answer Questions 3.1 3.32
AT4 Foundations 4.1 4.3
AT5 Demolition 5.1 5.6
AT6 Observation Project 6.1 6.8
AT7 Research and Quality control 7.1 7.2
What do I have to do to be marked competent?
These assessment tasks are designed to demonstrate competency against the requirements as stated in the unit(s) of competency. The unit of competency is available from training.gov.au or upon request to HIA. The assessment requirements are also outlined in the participant guide.
Unless otherwise noted, all assessment tasks are open book.
Specific requirements for individual tasks are provided at the beginning of each assessment task
All assessment tasks must be completed satisfactorily
All questions must be answered correctly
All project tasks must be completed
All responses, unless specified, should refer to the legal requirements in your State or Territory.
HIA has a strict policy about submitting work that is not the participants own work (plagiarism). Please refer to the HIA Participant Handbook for further information about the HIA Cheating and Plagiarism Policy.
How much time will I be given to complete these assessments?
Assessment Task 1 is to be submitted at the conclusion of the final training session for this short course. It is a supervised assessment and work must be completed individually.
Assessment Task 2 will be conducted no later than 14 days from the final training session.
Assessment Tasks 3 to 6 must be submitted no later than 28 days from the final training session.
If additional time is required for submission, this may be negotiated by contacting the training co-ordinator no less than 3 days before the final submission date.
How will I know if Ive done it right?
All responses provided by the participant will be assessed by a qualified assessor with current industry expertise.
Feedback on each completed assessment task will be provided by the assessor.
What happens if I dont get it right?
In the following situations a participant will be given the opportunity to re-submit their assessment:
Incorrect, insufficient or missing answers to questions
Project tasks are incorrect or incomplete or do not address the requirements of the project
Where re-submissions have been requested, the final date for completion of the unit or cluster of units will be extended. The extra time allowed will be negotiated between the participant and trainer/assessor.
A maximum of two re-submissions will be allowed before the participant will be required to attend further training. Any further training required may incur additional costs to the participant.
How do I submit my assessment tasks?
The Participant Declaration must be read and signed prior to commencing any assessment tasks.
Assessment Task 1 Written Questions
Assessment Booklet 1 is to be submitted to the trainer/assessor at the completion of Assessment Task 1.
Assessment Task 2 Verbal Questions
The participant is not required to submit any documentation for Assessment Task 2 as this assessment task is conducted and results recorded by the trainer/assessor.
Assessment Task 3 Short Answer Questions
Assessment Task 3 is to be completed and submitted in one of the following ways:
Answers written in Assessment Booklet 2 provided
Answers written in a separate document and hard copy sent via post/fax or electronic copy sent via email.
If submitted electronically the format must be one of the following: MS Word, MS Excel or Adobe PDF
If submitted separately:
Each answer must be clearly labelled with the relevant question number.
Each page must be clearly labelled with a page number.
The cover sheet provided for Assessment Task 3 must be completed and attached.
Assessment Task 4 (and subsequent assessment tasks) Project Tasks
Assessment Task 4 (and subsequent assessment tasks) may be completed and submitted in one of the following ways:
Separate written document
Electronic submission (MS Word, MS Excel or Adobe PDF format only)
Assessment Task 4 (and subsequent assessment tasks) will contain external documents that must all be submitted at the same time in one of the following ways:
Bound
Corner-stapled
In a plastic sleeve, envelope or folder
Secured with a rubber band
Each response must be clearly labelled with the task number it is responding to.
All pages must be clearly labelled with a page number.
The cover sheet provided for Assessment Task 4 must be completed and attached to all assessment documentation.
If your work includes a CD, clearly label the disk with your name and the Structures for Medium Rise Construction. Place it in a sealed plastic pocket, attached to the cover sheet.
Prior to sending any assessment work, make and keep a copy of your work as HIA will not accept responsibility for work lost in transmission.
Where do I submit my assessment tasks?
Assessments can be posted or dropped into the regional office (please check the HIA Participant Handbook for addresses).
Assessments can be emailed to the regional email address:
Region Email Region Email
ACT ACT_Training@hia.com.auVIC VIC_Training@hia.com.auCoffs Coffs_Training@hia.com.auWA WA_Training@hia.com.auNSW NSW_Training@hia.com.auNT SA_Training@hia.com.auHunter Hunter_Training@hia.com.auQLD QLD_Training@hia.com.auSA SA_Training@hia.com.auNth QLD Nth.Qld_Training@hia.com.auTAS TAS_Training@hia.com.auWhat if I dont agree with the assessors decision?
Where the participant does not agree with an assessment decision they are able to lodge and appeal. Please refer to the HIA Participant Handbook for further information about the HIA Assessment Appeals Policy.
Assessment Resources Required
To complete this assessment, you will need:
Participant Guide
NCC Volume 1
HIA Student Accommodation Plan Packs 1 - 5
Calculator
PARTICIPANT DECLARATION FOR SUBMISSION OF WORK FOR ASSESSMENT
STRUCTURES FOR MEDIUM RISE CONSTRUCTION - SHORT COURSE
CPCCBC5018AApply structural principles to the construction of medium rise buildings
Please complete and check all shaded sections before submitting.
Make sure this cover sheet is securely attached to your submission of work.
Participant name (First Name, Family Name) Assessor Name Kim Grossman
PARTICIPANT DECLARATION:I declare that:
The purpose and procedures of this assessment have been clearly explained to me.
I have discussed with my trainer/assessor any special needs that I have in relation to this assessment and I understand the options for Reasonable Adjustment as explained in the HIA Participant Handbook.
I have been given fair notice of the date, time and venue for this assessment and that I am ready for assessment.
I understand that the work must be my own and no part of it will be copied from any other participants work or from any other source, except where I have made reference to researched material.
I have read the information on Cheating and Plagiarism Policy in the HIA Participant Handbook and agree to the conditions as stated.
I understand my right to appeal the assessment decision as explained in the HIA Participant Handbook.
I agree to keep a copy of my Assessment Booklet after submission which can be produced if the original is lost, damaged or in case of a dispute.
Participants signature Date //
Assessment Booklet 1
1.0ASSESSMENT TASK 1 WRITTEN QUESTIONS
Participant Instructions
Questions 1.1 to 1.18 are short answer questions relating to Structures for Medium Rise Construction that will be completed at the end of the last session of scheduled attendance for the course.
The answers are to be recorded in this assessment booklet.
You must not collaborate with other participants to complete this assessment.
The assessment must be submitted to the trainer immediately on completion.
As a guide this assessment task should take approximately 30 minutes.
You will be provided feedback on your answers during Assessment Task 2.
What is a UDL and what is its common unit of measure in structures?
Assessor to tick () Satisfactory Unsatisfactory
If a mass of 1.2t was spread evenly along a beam spanning 5m, what would be the UDL on the beam?
Assessor to tick () Satisfactory Unsatisfactory
What is meant by a Point Load in structures?
Assessor to tick () Satisfactory Unsatisfactory
Give one example of an applied Dead Load & Live Load on the HIA Student Accommodation Project.
Assessor to tick () Satisfactory Unsatisfactory
Using a limit of L/360, what is the maximum allowable deflection across the slab for the Gym floor on RL 23.2m?
Assessor to tick () Satisfactory Unsatisfactory
If the Ground Floor slab is 150mm thick, calculate this dead load.
Assessor to tick () Satisfactory Unsatisfactory
Why are transfer-beams specified in some structures?
Assessor to tick () Satisfactory Unsatisfactory
Identify 2 locations in the HIA Student Accommodation Project where a transfer-beam element is required.
Assessor to tick () Satisfactory Unsatisfactory
If there were insufficient floor depth allowed by the architect for a satisfactory transfer beam what alternatives might be considered?
Assessor to tick () Satisfactory Unsatisfactory
Assume the applied load onto the footing along Grid 8 (between columns) is 44kN/m (LL) and 35kN/m (DL). For this un-factored load, what is the required bearing capacity of the founding material (to the nearest 100kPa)?
Assessor to tick () Satisfactory Unsatisfactory
Is the calculated value for bearing capacity in the previous question, a minimum or maximum?
Assessor to tick () Satisfactory Unsatisfactory
What is the load path for the wind force on the north elevation of the HIA student accommodation project to get transferred into (therefore resisted by) the footings?
Assessor to tick () Satisfactory Unsatisfactory
The basement level of the HIA Student Accommodation Project needs to be free of moisture ingress from the surrounding soil. Explain why the DPC (damp proof course) in any below grade walls would be insufficient to stop moisture ingress and an alternative solution that would better prevent water ingress?
Assessor to tick () Satisfactory Unsatisfactory
How does the structural design of the basement level address the risk of termite activity? (Hint: Recall BCA Vol. 1 provisions).
Assessor to tick () Satisfactory Unsatisfactory
How does the bending effect in the Grid 1 contiguous-pile wall change after the Ground Floor slab is completed?
Assessor to tick () Satisfactory Unsatisfactory
Nominate three locations on the project structure where deliberate movement may occur to allow for thermal effects and time-dependent effects.
Assessor to tick () Satisfactory Unsatisfactory
What does it mean if a floor has an FRL of 60/60/30?
Assessor to tick () Satisfactory Unsatisfactory
What would be the consequences if the floor levels were not accurately set out?
Assessor to tick () Satisfactory Unsatisfactory
Please make sure you have answered each question before submitting your assessment.
Participant Assessment Record Assessment Task1
Participant Given Name Participant Other Names Participant Surname
AT1 Written Questions Submission 1 Tick Satisfactory or Not Satisfactory
All questions completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Kim Grossman AT1 Written Questions Submission 2 Tick Satisfactory or Not Satisfactory
All questions completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
AT1 Written Questions Submission 3 Tick Satisfactory or Not Satisfactory
All questions completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
2.0ASSESSMENT TASK 2 VERBAL QUESTIONS
Participant Instructions
Questions 2.1 to 2.7 are verbal questions relating to Structures for Medium Rise Construction that will be asked individually of each participant.
The assessment task will be either face to face or telephone.
You will be asked a series of questions and required to provide verbal answers.
When answering these questions be clear and concise and remember that communicating the information and ideas is most important. You do not need to use jargon or fancy language to get your message across effectively.
As a guide the assessment should take approximately 10 minutes.
You will be contacted no later than 14 days from the final training session.
The Assessor will record in this assessment booklet whether the verbal answers are in line with the model answers and provide feedback at the completion of the assessment.
The verbal questions can be found in the table on the following page and may be copied in preparation for the assessment.
Participant Assessment Record Assessment Task 2
Participant Given Name Participant Other Names Participant Surname
AT2 Assessment Task 2 Verbal Questions
The participants response includes the minimum points as per the model answers
Tick if Satisfactory
2.1.What two types of stress are present in all structural bending? Satisfactory
2.2.Design load multipliers for applied (un-factored) Dead and Live Loads are different. Which is larger and why? Satisfactory
2.3.What are 3 essential design functions that must be achieved by all structures and by all parts of a structure? Satisfactory
2.4.Why can a precast wall panel be supported on 2 pads and not need a strip footing under it? Satisfactory
2.5.What is an essential feature of all portal frame designs? Satisfactory
2.6.What is the difference between Class 1 and 10 buildings and the other classes of buildings? Satisfactory
2.7.Name five of the six secondary loads that buildings may be subjected to. Satisfactory
Assessor Feedback
Final Result Tick Satisfactory or Not Satisfactory
All questions completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Kim Grossman
Structures for Medium Rise Construction
CPCCBC5018AApply structural principles to the construction of medium rise buildings
It is a requirement that participants undertaking the short course Structures for Medium Rise Construction have successfully completed the following unit.
CPCCBC5001BApply building codes and standards to the construction process for medium rise building projects
Participant Name: Course Start Date:
Participant ID: Assessment Due Date:
Trainer Name: Kim Grossman Region:
FNQ
Assessment Booklet 2
Assessment Booklet 2 contains Assessment Tasks 37
Assessment Submission Cover Sheet
Assessment Task 3
Short Answer Questions
Assessment Resources Required
To complete this assessment, you will need:
oParticipant Guide
3.0ASSESSMENT TASK 3 SHORT ANSWER QUESTIONS
Participant Instructions
Questions 3.1 to 3.32 are short answer questions relating to Structures for Medium Rise Construction that are to be completed outside the learning delivery environment.
What structural options might be safely considered if the architect wants a concrete column to be reduced in cross section?
Assessor to tick () Satisfactory Unsatisfactory
Calculate the maximum deflection of a 6m simply supported single span beam 250UB37.3 due to an applied load of 15kN at mid span. Use the following inputs for the formula:
Deflection = (P x L3 ) / (48 x E x lx):
Esteel = 200,000MPalx = 55.7x106mm4
Assessor to tick () Satisfactory Unsatisfactory
The maximum bending moment due to this load is 22.5kNm. Calculate the maximum bending stress in the beam given the Section Modulus ((Zx) =435x103mm3).
Assessor to tick () Satisfactory Unsatisfactory
Is the G300 beam discussed in Q3.2 & Q3.3 overstressed? Does it satisfy a deflection limit of L/500?
Assessor to tick () Satisfactory Unsatisfactory
What is the main type of stress applied to columns under expected service loads?
Assessor to tick () Satisfactory Unsatisfactory
If a slender column is overloaded, how might it fail?
Assessor to tick () Satisfactory Unsatisfactory
What are some practical consequences from adding extra water to concrete before it is poured?
Assessor to tick () Satisfactory Unsatisfactory
What are some practical consequences from inadequate compaction of concrete once it is poured?
Assessor to tick () Satisfactory Unsatisfactory
What are some practical consequences from inadequate curing of concrete once it is finished?
Assessor to tick () Satisfactory Unsatisfactory
If an access scaffold is overloaded with materials, how might it fail?
Assessor to tick () Satisfactory Unsatisfactory
If the reinforcement cage in a beam is fixed to the correct dimensions yet the cover is less than specified, what is likely to be the cause, why is it a structural problem and how should it be rectified?
Assessor to tick () Satisfactory Unsatisfactory
What potential floor-loading problem needs to be designed for, due to the Gym being sited beside the caf?
Assessor to tick () Satisfactory Unsatisfactory
What does demolition have in common with construction? Why must it be managed?
Assessor to tick () Satisfactory Unsatisfactory
If a material reaches its elastic limit in tension and then fractures with very little stretching its behaviour is said to be what?
Assessor to tick () Satisfactory Unsatisfactory
How can materials like this be safely designed and built with?
Assessor to tick () Satisfactory Unsatisfactory
Assessor to tick () Satisfactory Unsatisfactory
In the main span of a beam, where it is preferable to locate any penetrations through the cross-section for services, and why?
Assessor to tick () Satisfactory Unsatisfactory
If a suppliers instructions are not followed for using a specified proprietary system, what benefit is lost?
Assessor to tick () Satisfactory Unsatisfactory
Why is it unacceptable to weld onto high strength (Class 8.8) bolt components?
Assessor to tick () Satisfactory Unsatisfactory
Why is aluminium not used for structural purposes in medium rise construction?
Assessor to tick () Satisfactory Unsatisfactory
What is the difference between Classes 2 and 3 buildings (up to 3 storeys) and Class 1 buildings?
Assessor to tick () Satisfactory Unsatisfactory
How does a Class 4 building relate to Class 5 to 9 buildings?
Assessor to tick () Satisfactory Unsatisfactory
Amongst all the industry professionals that a project manager will consult with, which will be consulted with when constructing the underground car park. Describe these professionals input.
Assessor to tick () Satisfactory Unsatisfactory
When communicating with the various stakeholders in a building project, explain what techniques and considerations could be used to account for cultural and language differences.
Assessor to tick () Satisfactory Unsatisfactory
Site safety will be based on what key safety document?
Assessor to tick () Satisfactory Unsatisfactory
What important detail has been omitted from Drawing A16? Will its inclusion have any structural implications?
Assessor to tick () Satisfactory Unsatisfactory
Structural principles relate to what factors?
Assessor to tick () Satisfactory Unsatisfactory
What key materials specified in a buildings plan should be identified, analysed, and applied to the planning of the construction work?
Assessor to tick () Satisfactory Unsatisfactory
What structural considerations have to be made when allowing for the installation of services into a building?
Assessor to tick () Satisfactory Unsatisfactory
What are the key safety considerations when planning the installation of temporary structural elements?
Assessor to tick () Satisfactory Unsatisfactory
What building services, designed by specialists, are likely to be installed into the structure of the HIA Student Accommodation Project?
Assessor to tick () Satisfactory Unsatisfactory
Nominate nine temporary structural element items which may be used on the site of the HIA Student Accommodation Project.
Assessor to tick () Satisfactory Unsatisfactory
Please make sure you have answered each question before submitting your assessment.
Participant Assessment Record Assessment Task 3
Participant Given Name Participant Other Names Participant Surname
AT3 Short Answer Questions Submission 1 Tick Satisfactory or Not Satisfactory
All questions completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Kim Grossman AT3 Short Answer Questions Submission 2 Tick Satisfactory or Not Satisfactory
All questions completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
AT3 Short Answer Questions Submission 3 Tick Satisfactory or Not Satisfactory
All questions completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Structures for Medium Rise Construction
CPCCBC5018AApply structural principles to the construction of medium rise buildings
It is a requirement that participants undertaking the short course Structures for Medium Rise Construction have successfully completed the following unit.
CPCCBC5001BApply building codes and standards to the construction process for medium rise building projects
Participant Name: Course Start Date:
Participant ID: Assessment Due Date:
Trainer Name: Kim Grossman Region:
FNQ
Assessment Booklet 2
Assessment Booklet 2 contains Assessment Tasks 3-7
Assessment Submission Cover Sheet
Assessment Task 4
Foundations
Assessment Resources Required
To complete this assessment, you will need:
Participant Guide
HIA Student Accommodation Plan Packs 1 - 5
4.0ASSESSMENT TASK 4 FOUNDATIONS
Participant Instructions
Tasks 4.1 to 4.3 are project tasks relating to Structures for Medium Rise Construction that is to be completed outside the learning delivery environment.
Using the information provided in Section 3.0 Structural Principles - Designing for Forces of your Participant Guide, you are required to calculate an approximate load.
Participants are required to use word-processing software to produce their responses. (No hand written responses will be accepted).
All responses must be printed out and submitted in a hard copy.
All responses must be original work no copied work will be accepted.
Word counts provided are the minimum amount required.
All pages must be numbered and labelled on the footer and bound together.
All submissions must be in a report form and include a table of contents and a bibliography.
Drawings D01- D04 provides some additional information about the structure.
Using the information in 3.0 Structural Principles - Designing for Forces of the Participant Guide, calculate the approximate load on the footing pad at A7 for the HIA Student Accommodation Project.
In carrying out your calculations, assume the load from the external tilt-panels is carried by the strip footing and is not included in the load on the pad at A7.
Once you have calculated the dead load you now need to establish the live load for the column at A7. You should apply the values contained in the Participant Guide Section 3.
The geotechnical report has provided a bearing capacity of 100kPa for the founding materials at the depth of the footings.
Is the bearing capacity of the foundation sufficient to carry the total loads applied by the building at A7?
Please make sure you have completed each of the task requirements before submitting your assessment.
Participant Assessment Record Assessment Task 4
Participant Given Name Participant Other Names Participant Surname
AT4 Foundations Submission 1 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Kim Grossman AT4 Foundations Submission 2 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
AT4 Foundations Submission 3 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Structures for Medium Rise Construction
CPCCBC5018AApply structural principles to the construction of medium rise buildings
It is a requirement that participants undertaking the short course Structures for Medium Rise Construction have successfully completed the following unit.
CPCCBC5001BApply building codes and standards to the construction process for medium rise building projects
Participant Name: Course Start Date:
Participant ID: Assessment Due Date:
Trainer Name: Kim Grossman Region:
FNQ
Assessment Booklet 2
Assessment Booklet 2 contains Assessment Tasks 3-7
Assessment Submission Cover Sheet
Assessment Task 5
Assessment Resources Required
To complete this assessment, you will need:
Participant Guide.
HIA Student Accommodation Plan Packs 1 - 5
Calculator.
5.0ASSESSMENT TASK 5 - DEMOLITION
Participant Instructions
Tasks 5.1 to 5.6 are project tasks relating to Structures for Medium Rise Construction that are to be completed outside the learning delivery environment.
Review the image below and drawings in the Student Accommodation Plan Pack 3 to produce an outline of how the demolition would be carried out.
Participants are required to use word-processing software to produce their responses. (No hand written responses will be accepted).
All responses must be printed out and submitted in a hard copy.
All responses must be original work no copied work will be accepted.
Word counts provided are the minimum amount required.
All pages must be numbered and labelled on the footer and bound together.
All submissions must be in a report form and include a table of contents and a bibliography.
Drawings D01- D04 provides some additional information about the structure.
SCENARIO
The photo below shows the North elevation of the existing building on the site for the HIA Student Accommodation Project.
Participants are to provide the following documentation:
List and detail the items required to be completed prior to the demolition, including compliance with the relevant legislative requirements for your jurisdiction. (750 words)
Identifying what technique would be used for the demolition and why. (500 words)
The sequence of the demolition including the start point and end point. (500 words)
Where the drop zones would be. (Indicated on the site plan and should comply with AS 2601). (Provide a labelled and dimensioned sketched site plan and 250 word explanation)
Where hoardings, fencing and shoring maybe used. (Provide a labelled and dimensioned sketched site plan, images of suitable materials, instructions, SWMSs, and 500 word explanation)
Other safety precautions you must take to comply with safety legislation. (500 words).
Participant Assessment Record Assessment Task 5
Participant Given Name Participant Other Names Participant Surname
AT5 Demolition Submission 1 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Kim Grossman AT5 Demolition Submission 2 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
AT5 Demolition Submission 3 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Structures for Medium Rise Construction
CPCCBC5018AApply structural principles to the construction of medium rise buildings
It is a requirement that participants undertaking the short course Structures for Medium Rise Construction have successfully completed the following unit.
CPCCBC5001BApply building codes and standards to the construction process for medium rise building projects
Participant Name: Course Start Date:
Participant ID: Assessment Due Date:
Trainer Name: Kim Grossman Region:
FNQ
Assessment Booklet 2
Assessment Booklet 2 contains Assessment Tasks 3-7
Assessment Submission Cover Sheet
Assessment Task 6
Observation Project
Assessment Resources Required
To complete this assessment, you will need:
Participant Guide.
HIA Student Accommodation Plan Packs 1 - 5
6.0ASSESSMENT TASK 6 OBSERVATION PROJECT
Participant Instructions
Tasks 6.1 to 6.8 are project tasks relating to Structures for Medium Rise Construction that are to be completed outside the learning delivery environment.
You are required to observe an actual building in your area that is similar to the one shown in the HIA Student Accommodation Project documentation and write a commentary on the structural aspects of it.
The assessment should be submitted, formatted as a formal report describing the building, location and use of the building and including a cover and table of contents.
Your submission must cover points 6.1 to 6.8 in detail. Identify the location including street address of the building in your discussion. Your submission should be a minimum of 1,600 words.
Present a range of your own photos to support the detailed commentary about the structural aspects of the building in terms of the following headings (6.1 to 6.8).
Photos supporting your discussion should be labelled and included adjacent to the information provided in your submission.
Participants are required to use word-processing software to produce their responses. (No hand written responses will be accepted).
All responses must be printed out and submitted in a hard copy.
All responses must be original work no copied work will be accepted.
Word counts provided are the minimum amount required.
All pages must be numbered and labelled on the footer and bound together.
All submissions must be in a report form and include a table of contents and a bibliography.
INSTRUCTIONS
Using an actual building in your area that is similar to the one shown in the HIA Student Accommodation Project, write a detailed discussion on the structural aspects addressing the following headings:
Primary loadings & load paths through the structure.
Structural form with respect to withstanding lateral loads
Materials used and suggestions reasons why.
Behaviour of so called non-structural elements
Any observed aspects where the building is distressed / not performing
Durability & maintenance of structural elements
Provisions made to guard against moisture ingress into the structure
Proposed demolition method and sequence to conclude the structures life cycle including protection of adjacent buildings and public areas as well other safety issues specific to the
Participant Assessment Record Assessment Task 6
Participant Given Name Participant Other Names Participant Surname
AT6 Observation Project Submission 1 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Kim Grossman AT6 Observation Project Submission 2 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
AT6 Observation Project Submission 3 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Structures for Medium Rise Construction
CPCCBC5018AApply structural principles to the construction of medium rise buildings
It is a requirement that participants undertaking the short course Structures for Medium Rise Construction have successfully completed the following unit.
CPCCBC5001BApply building codes and standards to the construction process for medium rise building projects
Participant Name: Course Start Date:
Participant ID: Assessment Due Date:
Trainer Name: Kim Grossman Region:
FNQ
Assessment Booklet 2
Assessment Booklet 2 contains Assessment Tasks 3-7
Assessment Submission Cover Sheet
Assessment Task 7
Research and Quality Control
Assessment Resources Required
To complete this assessment, you will need:
Participant Guide.
HIA Student Accommodation Plan Packs 1 5
The internet
7.0ASSESSMENT TASK 7 RESEARCH AND QUALITY CONTROL
Participant Instructions
Tasks 7.1 and 7.2 are project tasks relating to Structures for Medium Rise Construction that are to be completed outside the learning delivery environment.
You are required to observe an actual building in your area that is similar to the one shown in the HIA Student Accommodation Project documentation and write a commentary on the structural aspects of it.
The assessment should be submitted, formatted as a formal report describing the building, location and use of the building and include a cover and table of contents.
Participants are required to use word-processing software to produce their responses. (No hand written responses will be accepted).
All responses must be printed out and submitted in a hard copy.
All responses must be original work no copied work will be accepted.
Word counts provided are the minimum amount required.
All pages must be numbered and labelled on the footer and bound together.
All submissions must be in a report form and include a table of contents and a bibliography.
INSTRUCTIONS
You will need access to the internet to carry out research for these tasks. Using Drawings A14, A15, and A16:
Prepare a specification, for contractor tender purposes and to ensure quality procedures and processes will be met, for the rooftop recreation area including paving, waterproofing, planter boxes, growing media, shade sails,and soft landscaping. Data sheets must be provided. The submission should be in the format of a booklet divided into appropriate labelled sections describing the works and suggesting suitable products and methods of installation. Identify any gaps in the information provided and create an RFI for these gaps. (750 words plus data sheets)
Prepare a specification for the treatment for the prevention of moisture ingress to the basement retaining wall shown in Drawing A14. This again is to ensure quality procedures and processes and you need to address the wall structure, the finish to the wall surface, the selection of a suitable membrane, protection of the membrane, drainage to the back of the wall, water disposal, and selection of suitable back-filling material. Provide all technical data required for a compliant outcome. The submission should be in the format of a booklet divided into appropriate labelled sections describing the works and suggesting suitable products and methods of installation. (750 words plus data sheets)
Participant Assessment Record Assessment Task 7
Participant Given Name Participant Other Names Participant Surname
AT7 Research and Quality Control Submission 1 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Kim Grossman AT7 Research and Quality Control Submission 2 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
AT7 Research and Quality Control Submission 3 Tick Satisfactory or Not Satisfactory
All assessment tasks completed satisfactorily Satisfactory Not Satisfactory
Assessor Feedback
Assessor Name Assessor Signature Date
Please complete this form only when the final mark has been deemed.
Assessment of Competency Record
Participant Given Name Participant Other Names Participant Surname
Assessment Task Summary Tick Satisfactory
AT1 Assessment Task 1 Written Questions Satisfactory
AT2 Assessment Task 2 Verbal Questions Satisfactory
AT3 Assessment Task 3 Short Answer Questions Satisfactory
AT4 Assessment Task 4 Foundations Satisfactory
AT5 Assessment Task 5 Demolition Satisfactory
AT6 Assessment Task 6 Observation Project Satisfactory
AT7 Assessment Task 7 Research and quality control Satisfactory
Assessor Declaration
In completing this assessment, we confirm that the participant has demonstrated all unit outcomes through consistent and repeated application of skills with competent performance in multiple instances over a period of time.
Evidence is confirmed as: Valid Sufficient Current Authentic
Assessment Result C, NC, CT, RPL-G, WD, WDNS
CPCCBC5018A Apply structural principles to the construction of medium rise buildings
Assessor Name Assessor Signature Date
Kim Grossman Assessor Feedback
Q 7.1 specification
400 planter boxes
1GENERAL1.1SCOPE OF SECTIONGeneral
This section refers to the planter boxes. Refer to the drawings, engineers details where applicable, and project specific requirements. Supply and install Fytogreen planter box.
Beige in colour Planter F from attached brochure.
Planter-Boxes-Brochure-2018-.pdf (fytogreen.com.au)Install and fix as per manufactures specification.
planter boxtorch Applied sheet membrane
Product specification
All pertinent data sheets to be read in conjunction with this specification
AS4654.2-2012 to be read in conjunction with this specification
Substrate preperation
Substrates must be solid, clean, dry and free from (but not limited to) release agents, grease, old coatings, loose materials etc.
All substrate preparation must be carried out in accordance with the relevant data sheets.
priming
Substrate (floor to be screeded to fall)
Over the prepared substrate apply one coat of Elastocol 500 primer at a rate of approximately 4-5m2 per litre to the entire area to be waterproofed.
Detailing and reinforcement
Install cementitious fillets to all perimeter junctions both vertical and horizontal as well as internal corners.
All vertical/horizontal upstands to be detailed utilising Alsan Flashing re-enforced with RF bandage or install mechanically fastened pressure/termination strips.
The use of drain droppers is strongly recommended for all waste points. Contact Allduro for further details.
Waterproof membrane
Install a layer of Soprasun 3.0 directly over the primed area using gas propane torch fully welding the sheet to the substrate, allow for 75mm side laps and 150mm end laps. Once the first layer is complete install the Sopragum directly over the first layer (staggering joints) in the same method as the first.
Contact Allduro for further instruction or refer to Sopremas installation guide.
Flood test the area waterproofed prior to proceeding with the installation of the drainage components and soils.
Ensure the finished waterproof membrane is protected prior to the installation of the drainage components and soils.
CONTACT DETAILS
Allduro
ABN: 71 122 381 337
Telephone: 08 9455 1658
Email: info@allduro.comWebsite: www.allduro.comIMPORTANT NOTEs
Allduro recommends referral to all pertinent product data sheets listed in the above specification prior to commencing application. The information contained herein is given in good faith as being true and accurate, but no liability is accepted by Allduro, our employees, distributors, representatives or agents, for any loss or damage, direct or indirect, that may result from using the information or adopting recommendations and/or suggestions as actual conditions for use are beyond our control
9. Roof top concrete paving system
General
Provide a rooftop paving system as documented.
Refer to the drawings, engineers details, and project specific requirements
Requirements: Conform to the following:
- Light weight system designed to eliminate the use of sand when laying pavers.
- Adjustable in height to achieve design falls.
- Able to accommodate the installation of services within the cavity under the elevated platform.
- Increases heat insulation.
- Reduces sound transmission.
- Allow access to waterproofing membrane.
Product:
Location as per drawings.
Paving supports - VersiPave GP ( https://elmich.com.au/products/versipave-2/ )
Concrete paver Adbri Euro Classic ( https://www.adbrimasonry.com.au/commercials/paving/paving-ranges/euro-classic-dc )
Size 400x400x40
Colour - Athens
Warranty: The installer contractor needs to match the manufactures warranty.
Roof top waterproofing
410Waterproofing
1GENERAL1.1SCOPE OF SECTIONGeneralRoof waterproofing to be as per attached product data sheet.
Standard: Australian Standard
Q 7.1 specification
400 SHADE SAILS
1GENERAL1.1SCOPE OF SECTIONGeneral
This section refers to the shade sails. Refer to the drawings, engineers details where applicable, and project specific requirements. The Shade sail is heavy duty shade cloth is an industrial textile made from High Density Polyethylene (HDPE) yarn, which has ultraviolet stabilisers and colour pigments incorporated into the structure.
HDPE is resistant to most acids and alkalis, and fungal attack. It does not absorb water, which is a significant factor in resisting staining and inhibiting mildew growth. These characteristics make HDPE ideal as a base yarn for a lightweight, strong shade cloth.
Standard : Australian Standard As4174:2018 knitted and Woven Fabrics, Section 3.3 Resistance to degradation by light.
Warranty: The installer contractor needs to match the manufactures warranty.
Cleaning and Maintenance: Cleaning and Maintenance is to be carried out to manufacturers recommendations. (HTTps://polyfab.com.au/product/comshade Shade sail care and maintenance instructions)
Specifications:
UNDERLAYS, MEMBRANESBase preparation
Provide a working base of platform material, unless otherwise shown on the Drawings or approved by the Superintendent. Provide an even surface free of any projections likely to damage film underlays and adequate to provide a firm base for reinforcement supports, or any other items to be supported.
Base types, as follows:
Graded stone base: Blind with sufficient sand to create a smooth surface free from hard projections. Wet the sand just before laying the underlay.
Concrete working base: Remove projections above the plane surface, and loose material.
Thickness: Minimum: 50mm.
Polymeric film underlay
General: Under internal slabs on ground including integral ground beams and footings, provide a vapour barrier or, in areas prone to rising damp or salt attack, a damp-proofing membrane.
Standard: Vapour barriers and damp-proofing membranes: To AS2870.
Material: 200 micrometer thick high impact resistant polythene film, Premium Orange, IR3.
Installation: Lay over the base, lap joints at least 200mm and seal the laps and penetrations with waterproof adhesive tape. Face the laps away from the direction of concrete pour. Take the underlay up vertical faces as far as the damp proof course where applicable, and fix at the top by tape sealing. Locate vertical laps only on vertical or inclined surfaces. Patch or seal punctures or tears before pouring concrete.
CONCRETE FORMWORKSTANDARDGeneral
Formwork design: To AS3610.
Formwork construction: To AS3610.
CONCRETE REINFORCEMENTSTANDARDSGeneral
Reinforcing bars: To AS1302.
Reinforcing wire: To AS1303.
Reinforcing fabric: To AS1304.
MATERIALS AND COMPONENTSReinforcement
General:
Identification: Ensure that the grade and origin of reinforcement is readily identifiable.
Surface condition: Free of material which would reduce the bond between the reinforcement and concrete.
Dowels
Standard: To AS1302 grade 250R.
General: Provide each dowel in one piece, straight, with square cut ends free from burrs. Apply 2 coats of bitumen emulsion to half the length of the dowel at one end.
Tie wire: Galvanised in external and corrosive areas.
Bending:
General: Bend and straighten reinforcement without damaging it.
Hot bending: To AS3600.
Protective coated reinforcement
Extent: For concrete elements containing protective coated reinforcement, provide the same coating type to all that elements reinforcement and embedded ferrous metal items, including tie wires, stools, spacers, stirrups, plates and ferrules, and protect other embedded metals with a suitable coating.
Galvanising:
Coating (minimum): 700g/m2.
Preparation: Pickling to AS1627.5.
Damage: If damage occurs to the coating replace the damaged reinforcement.
EXECUTIONReinforcement supports
Support types generally: Provide purpose-made concrete, metal or plastic supports, adequate to withstand construction and traffic loads, and in the form of chairs, spacers, stools, hangers and ties.
Fixing reinforcement
Fixing requirements generally: Secure the reinforcement against displacement by tying at intersections with either annealed iron 1.25mm diameter (minimum) wire ties, or clips. Bend the ends of wire ties away from nearby faces of forms so that the ties do not project into the concrete cover.
Welding generally: Do not weld reinforcement.
within 75mm of a bend with an internal radius <6 bar diameters; or
at points which have been re-bent.
Standard: To AS1554.3.
CONCRETE MATERIALSGeneral
Cementitious materials: Dry and uncontaminated.
Aggregate: Unsegregated and uncontaminated.
Admixtures: No deterioration.
Bagged cement
Standard: To AS 3972.
Type: GP.
Age: Less than 6 months old.
Chemical admixtures
Contents: Free of chlorides, fluorides and nitrates.
CONCRETEConcrete performance
General: Mix must work readily into corners and angles, and around reinforcement, without segregation or excess free water on the surface, producing sound concrete, with minimal plastic settlement and shrinkage cracking.
Drying shrinkage (maximum including tolerances): 0.65mm for concrete up to and including strength grade 32; 0.7mm for higher strength grades.
READY MIXED SUPPLYMethod: Use the batch production process. Deliver in agitator trucks.
Addition of water: Do not add water at the site after starting discharge.
CORES, FIXINGS AND EMBEDDED ITEMSTake responsibility for co-ordinating the provision of core holes and embedment requirements of all trades whether or not shown on the Contract Drawings.
Adjoining elements
For adjoining elements to be fixed to or supported on the concrete, provide for the required fixings. Where applicable provide for temporary support of the adjoining elements during construction of the concrete.
Structural integrity
Fix cores and embedded items to prevent movement during concrete placing. In locating cores, fixings and embedded items, do not cut or displace reinforcement, or cut or core hardened concrete. Ensure that embedded pipes and conduits do not adversely affect structural integrity.
Placement
Maximum deviation from correct positions:
Cores and embedded items generally: >10mm.
Fixings including anchor bolts: <3mm.
Anchor bolt groups for structural steel: To AS4100.
Water tracking: Ensure fixings do not allow water to track to reinforcement.
Inserted fixings
Limitation: Use fixings inserted by drilling (including masonry anchors and the like), or by explosive tools, only if specified.
Protection
General: Grease threads. Cover and protect embedded items against damage.
Corrosion: Galvanise inserts, anchor bolts and embedded fixings.
PLACING AND CURINGConcrete working base
Material: N20 concrete. Lay over the base or subgrade and screed to the required level.
Finish: Membrane support: Wood float finish or equivalent.
Surface tolerance: 5mm from the correct plane, 5mm from a 2m straight edge.
Placing and compaction
Placing:
General: Use placing methods which minimise plastic settlement and shrinkage cracking. Avoid segregation. Avoid loss of materials. Between construction joints, maintain a plastic concrete edge.
Layers: Place concrete in layers 300mm thick, such that each succeeding layer is compacted before previous layer has taken initial set.
Placing slabs and pavements: Place concrete uniformly over the width of the slab so that the face is generally vertical and normal to the direction of placing.
Construction joints: Thoroughly roughen hard concrete joint surfaces. Remove loose or soft material, foreign matter and laitance. Dampen joint surface using clean water and coat with neat cement slurry.
Compaction:
General: Remove air bubbles and fully compact the mix.
Methods: Use immersion and screed vibrators accompanied by hand methods as appropriate.
Vibrators: Do not allow vibrators to come into contact with partially hardened concrete, or reinforcement embedded in it. Do not use vibrators to move concrete along the forms. Avoid over-vibration that may cause segregation.
Curing
General:
Protection: Protect fresh concrete, during the curing period, from premature drying and from excessively hot or cold temperatures. Protect fresh concrete from physical and thermal shock, from traffic likely to damage the surface, and from rain. If temperature of surrounding air is >35oC, protect from wind and sun until the concrete can be covered. Maintain at a reasonably constant temperature with minimum moisture loss, during the curing period. Prevent rapid drying out at the end of the curing period.
Curing period: Cure continuously from initial set until the total cumulative number of days or fractions of days, during which the air temperature in contact with the concrete is above 10oC, is at least the following:
Fully enclosed internal surfaces/Early high-strength cement concrete: 3 days.
Other surfaces/Ordinary Portland cement concrete: 7 days.
Curing compounds
Standard: To AS3799.
Substrates: Do not use wax-based or chlorinated rubber-based curing compounds on surfaces forming substrates to concrete toppings and cement-based render. Do not use PVA compounds.
Application: Provide a uniform continuous flexible coating without visible breaks or pinholes, which remains unbroken at least seven days after application.
Set-downs
Set down in wet areas.
Refer to structural drawings.
Unless specified otherwise on the drawings, provide:
100mm slab set down in bathrooms where finished falls to hobless showers are required.50mm (nominal) slab set down in laundries where finished falls to floor waste are required.
Threshold levels
For Platinum, Gold and Silver Levels accommodation or where wheelchair access is required:
Comply with AS 1428.1 requirements and drawings, where there is a difference in finished floor levels at external door thresholds and external sliding glass doors.
Finish
Finish floor slabs in living and bedroom areas to be suitable for the application of sheet vinyl flooring or direct stick carpet.
Do not apply surface treatments which will inhibit a positive bond of these applied finishes.
JOINTSConstruction joints
Joint preparation: Roughen and clean the hardened concrete joint surface, remove loose or soft material, free water, foreign matter and laitance. Dampen the surface just before placing the fresh concrete.
Expansion joints
Joint filling:
Preparation: Before filling, dry and clean the joint surfaces, and prime.
Joint filling: Fill with jointing materials. Finish visible jointing material neatly flush with adjoining surfaces.
Watertightness: Apply the jointing material so that joints subject to ingress of water are made watertight. Location of watertight joints as shown on the drawings.
Movement joints
Location: Construct movement joints in the locations and to the details shown on the Drawings.
Joint filling: Fill movement joints with jointing materials of the types shown and as recommended by the material manufacturers and in accordance with their instructions for the location and type of joint, compatible when used together, non-staining to concrete in visible locations, and finished neatly flush with adjoining surfaces.
Control joints
Requirement: Where shown on the Drawings. Form groove in slab either with a grooving tool, by sawing, or by inserting an approved proprietary premoulded strip
CONCRETE FINISHESDEFINITIONApplied finishes include finishes as laid, wrought finishes on formed surfaces, separate applied finishes placed monolithically on green concrete surfaces, and separate applied finishes keyed or adhered to hardened or partially hardened surfaces.
Refer to Painting worksection for proprietary textured finishes.
Cementitious toppings
Toppings comprising aggregate bound with cement.
EXECUTIONTolerances
Tolerance classes: Determine tolerance classes using a straight edge placed anywhere on the surface in any direction.
Tolerances class table
Class Measurement Maximum deviation (mm)
A 3m straight edge 3
B 3m straight edge 6
C 600mm straight edge 6
Surface modifiers
Surface hardeners:
Suitable for Cementitious toppings or as laid surfaces.
Apply to clean surfaces. Do not apply to non-slip topping.
Seal stripper: Thoroughly clean the surface before the application of finishes to masonry and cementitious floors. Remove wax (buffable, self-polishing and acrylic paste types), heavy duty polymer finishes, and clear resin sealer using a seal stripper.
Unformed surfaces
Screeding: Strike off, consolidate and level slab surfaces to finished levels, to tolerance classC unless specified otherwise.
Placing:
Process: Spread the topping mix, compact, float to the designated tolerance class and finish.
Thickness: 20 +5mm.
Monolithic placing: Spread the topping mix as soon as surface water has disappeared from the base.
Monolithic placing on hardened surfaces: If toppings are to be applied to hardened concrete surfaces, scabble the surface to remove the surface layer and expose the aggregate. Thoroughly dampen the surface and leave free of standing water. Immediately before placing, either scrub a coat of neat cement grout into the surface, or apply an adhesive.
Placing over membranes: Over waterproof membranes, place cementitious toppings at least 45mm thick. Reinforce with 50 x 50 x 1.6mm galvanised wire netting lapped 150mm at joints.
Curing: Prevent cracking or crazing resulting from drying shrinkage, without impairing the adhesion of subsequent finishes.
GRANOLITHIC TOPPINGSMix
Ratio: 1:1:1.5 cement:fine aggregate:5mm coarse aggregate.
Water:cement ratio: 0.5 maximum.
Slump: 50mm maximum.
Placing
Monolithic placing: Compact and float.
Adhesive
An approved commercial.
Integral margins
Integrally form margins in the topping material.
Coved skirtings
General: Where detailed or specified on the drawings, form coves in the topping material, and finish the top to a neatly struck line. Mitre internal and external angles.
Finishing methods
Scored or Scratch Finish (Broomed Finish): After screeding, give the surface a coarse scored texture using a stiff brush or rake drawn across the surface before final set.
Machine floated finish: After screeding consolidate the surface using a machine float. Hand float in locations inaccessible to the machine float. Cut and fill to tolerance class B and refloat immediately to a uniform, smooth, granular texture.
Steel trowelled finish: After machine floating, use power trowels to produce a smooth surface relatively free from defects. Then, when the surface has hardened sufficiently, use steel hand trowels to produce the final consolidated finish free of trowel marks and uniform in texture and appearance, to tolerance class A. Where floor coverings are to be installed, remove defects that would show through them.
Wood float finish: Produce the final finish using a wood float.
Non-Slip Broom finish: After floating draw a broom or hessian belt across the surface to produce a coarse even-textured slip-resistant transverse-scored surface.
Sponge finish: After machine floating, obtain an even textured sand finish by wiping the surface using a damp sponge.
Non-Slip Finish: Blend silicone carbide granules or aluminium oxide (size range 595 microns to 1410 microns) with portland cement in the proportions recommended by the supplier. After screeding, apply the blend at the rate of 1 kg/m in two operations.
Firstly apply approximately two-thirds of the granule cement blend to the surface by a method that ensures even coverage without segregation. Begin machine floating immediately after application of the first 'dry-shake'. When the granules have been embedded by floating, broadcast the remainder of the blend at right angles to the previous application. Machine float immediately.
Scored Non-Slip Finish: Alternatively, non-slip finish may be achieved through permanently grooving stair treads and landings.
Coloured and patterned finishes
Pattern paving: Proprietary treatment producing integral coloured and patterned surface for in situ paving and ground slabs.
Coloured concrete
Add pigment concentrates of high tinting strength inorganic oxides to the mixing as recommended by the manufacturer, to the desired colour.
Colour to be integral with the slab concrete or topping screed.
Apply and cure using experienced tradesmen to achieve uniformity in the colour and final appearance.
Provide a 1m sq sample panel on site and obtain the approval of colour and finish from the SR before proceeding with the work. LOCATIONS / FINISHESGeneral application
Steel trowelled: To all internal concrete floors other than tiled areas.
Non-slip wood floated: To all external undercover areas, patio, carports, stores and the like, including under-croft carparking areas.Broomed: To external exposed areas, paths, car tracks, slabs at doorways and the like.
WATER PROOFING
MATERIALS AND COMPONENTSMEMBRANESAsphalt tanking membranes
Waterproof 5mm thick, of bituminoid asphalt materials, reinforced with fabric, with at least one layer in each sheet of an impermeable, non-corroding material.
Single layer membranes
Fix and lap sheets with appropriate proprietary adhesive or by heat welding using a gas torch (torch on), self-finished or finished with a proprietary surfacing.
Seamless membranes
Membranes applied in liquid or gel form and air or chemically cured to form a seamless film.
Internally: use liquid acrylic, polyurethane or rubberised material suitable for use with ceramic tiling. Do not use bitumen based materials.
Externally: Bitumastic material may be used for planter lining or external works. Do not use acrylic membranes for wall tanking.
EXECUTIONSUBSTRATESSubstrates for membranes
General: Apply membranes to dry, smooth, firm, continuous surfaces, clean and free from loose or foreign matter. Provide coving or fillets on internal corners. Round or arris external corners and edges.
Dryness tests for substrates: To AS1884 Appendix A.
TANKINGAsphalt tanking installation
Standard: To ASCA55.
Tanking and under-slab membrane protection
General: Protect the membrane after installation, with a permanent cover of rigid closed cell extruded polystyrene foam boarding with shiplapped edges, adhered to the membrane with a solvent-free or low melt bitumen adhesive. Provide a maximum 6mm gap at joints between boards.
Blockwork tanking system
Refer to link for waterproofing method behind retaining wall https://cdnmedia.mapei.com/docs/librariesprovider14/default-document-library/b03---mapei-system-for-waterproofing-retaining-walls-booklet-2021.pdf?sfvrsn=d02f2871_0BRICK AND BLOCK CONSTRUCTION
GENERALSTANDARDSGeneral
Materials, construction and detailing: To AS3700.
Masonry units: To AS/NZS4455.
To SAA HB 124.
Built in components: To AS/NZS 2699.
INTERPRETATIONDefinitions
Face units: Masonry units used in facework, including purpose-made units such as squints, sills and thresholds.
Facework: Masonry in which the form, or form and colour, of the face units and joints is visible in the completed works.
QUALITYINSPECTIONWitness points
Stages: Give sufficient notice so that inspection may be made at the following stages:
Damp-proof courses, in position.
Flashings, in position.
Termite barriers in position.
Bottoms of cavities, after cleaning out.
Bottoms of core holes, before grouting.
Control joints, ready for insertion of joint filler.
SAMPLESMasonry unit samples
Submit samples of each type of face masonry illustrating the range of variation available, including colour, texture, surface irregularities, defective arrises, and shape.
Number of each type: 6.
Mark and keep the approved samples on site until the completion of the project. Do not commence laying until approval is received from the Superintendent.
Facework sample panels
General: If specified in Schedule of Requirements, or if alternative face masonry acceptable to the superintendent is proposed, provide in a suitable position a sample panel of each type of facework including face or pointing mortar.
Minimum size (face of panel): Four units long x 6 units high min. in the required pattern (such as stretcher bond).
Ordering
Order all external masonry units required for the whole of the Works at the commencement of the project. Have sufficient pallets of face masonry on site to allow even mixing and distribution of the colour range.
MATERIALS AND COMPONENTSMATERIALS AND COMPONENTSMasonry units
Refer Materials and Finishes Schedule and the drawings.
Steel components generally
Durability classification to AS3700.
Refer to Wall Ties in Cavity Walls for additional Durability Classification requirements within 3 km of salt water.
Mortar materials
Cement type to AS3972: GP.
White cement: Iron salts content 1%.
Lime: To AS1672.1.
Sand: Fine aggregate with a low clay content and free from efflorescing salts, selected for colour and grading.
Admixtures: Do not provide admixtures.
Colour
Refer to Materials and Finishes Schedule and Colour Scheme.
Mortar mix table
Mortar type to AS 3700 Mortar proportions (cement:lime:sand) Location
M3 1:0:5 + water thickener Concrete or calcium silicate masonry
M4 1:0:4 + water thickener Grouted and reinforced masonry
M4 1:0 - 0.25:3 Underpinning, high strength masonry
M3 1:1:6 Other masonry
EXECUTIONCONSTRUCTION GENERALLYCleaning
General: Clean masonry progressively as the work proceeds. Clean facework to remove mortar smears, stains and discolouration. Do not use acid.
REINFORCED MASONRYGeneral
Designation: Masonry strengthened with embedded steel reinforcement, other than bed joint reinforcement.
Cleaning core holes
Blockwork: Provide purpose-made cleanout blocks or machine cut a cleaning hole at the base of each reinforced core. Locate on the side of the wall which is to be rendered or otherwise concealed. Cover the hole with formwork and grout the core.
330 PLUMBING AND DRAINAGEGENERALCROSS REFERENCESQUALITYINSPECTIONWitness points
Give sufficient notice so that inspection may be made at the following stages:
Excavated surfaces.
Work ready for specified testing.
Concealed or underground services before covering.
STANDARDSStormwater drainage
General: To AS/NZS3500.3.2.
Sanitary plumbing and sanitary drainage
General: To AS/NZS 3500.2.2.
Local authority requirements
Plumbing and Drainage Act 2002.
Standard Plumbing and Drainage Regulation 2003.
Plumbing Code of Australia.
Queensland Plumbing and Wastewater Code.
INTERPRETATIONDefinition
Pipe surround: Includes pipe overlay, pipe side support, side zone and haunch zone.
NOTICE OF COMMENCEMENTGive seven days notice of intention to commence drainage.
LAYOUTInstall pipework in position as shown on drawings. Before commencing work, verify the exact positions of connection points to Utility Service Providers service, fixtures, plant, appliance and the like to which the pipework is to be connected.
Systems installation to allow for easy maintenance and servicing of all components.
APPROVED DRAWINGSRefer to the Schedules of Requirements to this worksection for supply of approved drawings.
AS-BUILT DRAWINGSRequirement
Refer to Preliminaries section As-Built Drawings and Project Specific Schedules.
PIPEWORK TESTINGArrange for testing as required by the Plumbing and Drainage Act 2002.
Concealed Work: Do not cover or conceal underground or enclosed work until it has been tested and approved.
UPVC Pipework: Cure solvent cement joints for at least 24 hours before testing.
SAMPLESGeneral
Submit samples of the following if requested.
Each type of imported pipe-bedding material.
Each type of filter material.
PIPEWORKGeneral
Supply and install all pipework and fittings where shown and specified on the Drawings.
Pipe materials
Vitrified Clay Pipe and Fittings: To AS 1741, Grade A, Class Y.
Concrete pipe
To AS 4058.
Class:
100mm and 150mm dia.: Class LDU (light duty unreinforced).
Over 150mm dia: Class 2 (reinforced).
Jointing methods
Flexible joints: Using rubber rings.
Rigid joints: Spigot and socket joints or rebated joints to AS 4058, Appendix A, caulked with mortar jointing material.
Joint materials: to AS 1646.
Marking: To AS 4058, Clause 1.5.
UPVC pipe and fittings
Drainage and Stormwater pipe and fittings: Within site, to be sewer class to AS 1260, not less than 100mm diameter. Identifying colour to be cream.
Footpath crossings
Cluster Housing: 100mm minimum dia. pressure pipe Class 6 UPVC.
Apartments or Attached Housing: Hot dipped galvanised RHS pipes.
Unless otherwise required by the relevant Local Government.
Pipe underlay
General: Bed piping on a continuous underlay of bedding material, at least 75mm thick after compaction. Grade the underlay evenly to the gradient of the pipeline.
Chases: If necessary, form chases to prevent projections such as sockets and flanges from bearing on the trench bottom or underlay.
Pipe surrounds
General: Place the material in the pipe surround in layers 200mm loose thickness, and compact without damaging or displacing the piping.
Anchor blocks
If necessary, provide anchor blocks which restrain lateral and axial movement of the pipelines at junctions and changes of grade or direction.
Underground Installations
Minimum Cover Over Pipe: Provide the following cover to underground pipeline external to the building:
Generally: 300mm.
Pipes subject to vehicular loading (under sealed roadways, Parking areas and the like) 600mm.
Encasing: Where the required minimum cover cannot be provided encase the pipeline with 20 MPa reinforced concrete not less than 150mm thick all round or 100mm concrete pad over pipe extending 100mm into the side walls of the trench.
Procedure: Drains through footings to be laid before footings are poured.
Drainage line and/or waste pipes passing through foundations or slabs to be lagged with 6mm thick (minimum) approved material.
Junctions to be at 45o unless otherwise approved.
Tolerances
Comply with the Pipeline tolerances table. These tolerances are conditional on falls to outlets being maintained and no part of a pipeline being at less than the designated gradient.
Pipeline tolerances table
Permissible angular deviation from alignment Permissible displacement from alignment
Horizontal 1 in 300 15mm
Vertical 1 in 500 5mm
Gradients
Lay drains to gradients complying with the relevant authoritys requirements, and in any case not less than the following:
Pipeline type Pipe Diameter (mm) Pipeline gradient
Sewer 100
150 1 in 60
1 in 80
Stormwater 100
150-300 1 in 100
1 in 150
Subsoil 100-150 1 in 300
PITSGeneral
This Clause includes manholes, field gullies and channels.
In situ concrete: 20 MPa concrete, 100mm thick.
Precast concrete: Proprietary precast concrete units or spun precast wall sections, minimum 20 MPa concrete designed for the appropriate application. Provide cored holes as required.
Reinforcement: If depth of pit exceeds 1500mm: F718 mesh or as otherwise shown on Drawings.
Proprietary Pits: Where proprietary polypropylene pits are installed, the following conditions apply:
Trafficable areas:
600 x 600mm and 450 x 450mm pits to be cast in 100mm (minimum) concrete with 150 x 150mm concrete collar surround.
300 x 300mm pits to be cast in 100mm (minimum) concrete with 100 x 100mm concrete collar surround.
Non-Trafficable areas:
300 x 300mm pits to have a 100 x 100mm concrete collar surround.
Pedestrian areas:
Heel Safe grates shall be provided to all pits in paved areas shared or solely used by pedestrians.
Grate spacing and direction to allow unencumbered traverse of narrow wheeled equipment, wheelchairs, bicycles, prams and narrow heeled footwear.
Grate aperture: 8mm max. perpendicular to direction of travel.
Conform to:
AS 4685 to resist narrow heeled footwear penetration.
AS 3996 to resist bicycle/wheeled equipment tyre penetration, and AS 3996 Clause 3.3.5: Surface Openings in Pedestrian Areas.
AS 1428.2 for wheelchair and walking cane safety requirements.
AS 4586 Slip resistance required: rated to P4 / R11 min. where grades are equal or under 1:14; and rated to P5 / R12 min. where grades are greater than 1:14.
Collar to finish flush with top of grate.
All grates to be hot dipped galvanised (including grates in garden areas).
Inspection Chambers: Construct in concrete and fit with concrete infill type cover appropriate to the finish of contiguous surfaces and trafficable loads.
Invert and benching to be rendered with at least 10mm thickness of cement mortar. Ladders to be set in one wall of the chamber where the depth of same exceeds 1200mm. The top rung is not to be more than 700mm below the finished top.
Finish to exposed surfaces
General: Provide a smooth, seamless finish, using steel trowelled render or concrete cast in steel forms.
Corners: Cove or splay internal corners.
Metal access covers and grates
Standard: To AS3996.
Covers and grates are to meet the appropriate load requirements areas. Load class: A, B, C or D, to suit application.
Cover levels: Top of cover or grate, including frame:
In paved areas: Flush with the paving surface.
In landscaped areas: 25mm above finished surface.
Gratings taking surface water runoff: Locate to receive runoff without ponding.
Slip resistance:
AS 4586 Slip resistance required to access covers and grates in pedestrian areas, including car parks: rated to P4 / R11 min. where grades are equal or under 1:14; and rated to P5 / R12 min. where grades are greater than 1:14.
STORMWATEREXECUTIONGeneral
General: Provide stormwater drains to connect downpipes, surface drains, subsoil drains, seepage drains and drainage pits to the outlet point or point of connection.
Provide means for stormwater drains to discharge as detailed on Drawings:
underground drain;street channel;soakage pits.
Downpipe connections
Turn up the drain branch pipeline with a suitable bend to meet the downpipe, to finish 50mm above finished ground or flush with pavement.
Provide UPVC adaptor to connect roof water downpipe to drainage without reduction in pipe size. Except where impractical due to limited fall to site adaptor to be encased by pavers or, if none, in concrete to 50mm above ground.
Where connection is between Colorbond or equal downpipe and collar of drainage line (without adaptor) concrete surround to be separated from downpipe by 10mm gap to permit back flow discharge.
LINED SURFACE DRAINSWhere specified:
Half round pipe drains: Provide surface drains lined with half round pipe, including bedding and jointing.
Grated trenches: Provide precast or cast in situ concrete lined trenches with galvanized steel gratings. Refer to CL 1.12 Pits.
PRECAST BOX CULVERTSStandards
Culverts <1200mm span x 900mm high: To AS1597.1.
Culverts 1500 - 4200mm span x 4200mm (maximum) high: To AS1597.2.
Lifting gear
Provide suitable attachments for lifting gear to culverts 600 x 450mm.
Installation
Screed and compact the bedding to provide uniform support. Install culvert sections to provide a continuous waterway without abrupt changes in alignment or grade.
SUBSOIL DRAINSGeneral
Provide subsoil drains to intercept groundwater seepage and prevent water build-up behind walls and under floors and pavements. Wrap pipes in geotechnic cloth. Connect subsoil drains to surface drains or to the stormwater drainage system as applicable.
Pipe depth
Refer to minimum pipe cover table CL 1.11 as per AS/NZS 3500.3, 7-2.6.
Jointing
At junctions of subsoil pipes provide tees, couplings or adaptors to AS2439.1.
Trench width
Minimum 450mm.
Pipe underlay
General: To requirements of AS/NZS 2032.
Pipe surrounds
General: Place the material in the pipe surround in layers 200mm loose thickness, and compact without damaging or displacing the piping.
Depth of overlay: Backfill with clean rubble over the filter:
To the underside of the bases of overlying structures such as pavements, slabs and channels.
To within 150mm of the finished surface of unpaved or landscaped areas.
Filter fabric
General: Provide polymeric fabric formed from plastic yarn composed of at least 85% by weight propylene, ethylene, amide or vinyledenechloride, and containing stabilisers or inhibitors which provide resistance to deterioration due to ultraviolet light.
Marking: To AS3705.
Protection: Provide heavy duty protective covering. Store clear of the ground and out of direct sunlight. During installation do not expose the filter fabric to sunlight for more than 14 days.
TOPSOILImported soil mix
Definitions:
Imported Soil Mix to AS 4419, clause 4.2 Low Density Soil:
Imported Soil Mix to AS 4419, clause 4.6 Soil Blend:
Soil mix types: The required soil mix types are nominated on the drawings.
Soil mix depths: The required depths of soil mix are nominated on the drawings or otherwise, as specified herein.
Source: Import specified soil mix on to the site from an approved source.
Nitrogen draw down index (NDI): The Contractor shall be responsible for any additions of soluble nitrogen to the proposed topsoil mixes which may be necessary to achieve the required NDI requirements of AS 4419 clause 5.12 and or as indicated as necessary by delivery documentation as per AS 4419 clause 8(d) refer SPECIFIED SOILS DELIVERY LANDSCAPE.
IMPORTED SOIL MIX ALTERNATIVESite strip topsoil raised to the standard of the appropriate imported soil mix type by the use of additives such as organic matter, lime, sand etc, may be approved for use at the Superintendent's discretion, subject to compliance with the relevant test criteria outlined in TESTING-LANDSCAPE, and provided that there shall be no contract variation involving additional cost.
Upgrading proposal to be based on Agronomists recommendations based on the analyses of the results of soil tests carried out in accordance with Table 1: Scheme of soils testing of AS 4419 for Natural Soils and Soil Blends and a particle size distribution analysis, all in accordance with specification section TESTING-LANDSCAPE.
Sample for Testing: Take 15 samples over the whole area to be stripped to the depth of elevation. Blended sample size to be 250 grams.
Upgrading proposal: Forward original test certificates from a NATA testing authority together with the Agronomists upgrading proposal to the Superintendent for approval prior to upgrading the site soil.
Test upgraded material in accordance with in accordance with Table 1: Scheme of soils testing of AS4419 for Natural Soils and Soil Blends and carry out a particle size distribution analysis , all in accordance with specification section TESTING-LANDSCAPE to demonstrate compliance with the specification of the relevant imported soil mix.
Deficiencies in the required quantities of upgraded site strip soil to be made up with imported soil mix to AS4419, Clause 4.6 Soil Blend at the Contractors expense.
TOP DRESSINGDefinitions
Top Dressing: To AS 4419 clause 4.7 suitable for application to turf or grass areas and complying with the requirements of AS 4419 sections 6, 7 and 8.
Top dressing depths
Maximum depth of topdressing is to be 10mm unless noted otherwise.
TESTINGTiming
Do not bring imported soil mix or top dressing onto the site until the approval of the test information has been received from the S.R.
Requirement
For each of the soils proposed for use in the works, provide certification that it meets the relevant specification and supply the test data outlined in AS4419 Table 1 scheme of soils testing used to verify specification compliance. Testing to be carried out in accordance with the requirements of AS 4419 appendices A to I. Carry out particle size distribution analyses where specified.
Particle size distribution analyses to be carried out by both the hydrometer method as in AS1289.C6.3-1977 and by sieving.
Particle size distribution to be provided as a percentage passing by mass the following AS sieve apertures: 2.36mm, 1.18mm, 0.60mm, 0.30mm, 0.15mm, 0.075mm, 0.002mm.
Materials to be representative of product proposed for supply to site. Include batch identities on certificates.
Carry out the tests specified in TESTING LANDSCAPE' to the relevant Australian Standards by an approved NATA testing authority.
Certificates
Forward original test certificates from a NATA testing authority to the Superintendent.
SPECIFIED SOILS DELIVERYDeliveries of soil to site must from an approved supplier and be accompanied by the documentation referred to in section 8 of AS 4419. Submit documentation to the S.R.
PLACING SPECIFIED SOILContamination
Where diesel oil, cement or other phytotoxic material has been spilt on the subsoil or specified soil, excavate the contaminated soil, dispose of it off the site, and replace it at no extra cost with imported topsoil, as directed, to restore design levels.
Placing
General: Spread the topsoil on the prepared subsoil and grade evenly, making the necessary allowances to permit the following:
Required finished levels and contours may be achieved after light compaction.
Place the appropriate specified soil on the prepared subsoil to the areas and depths shown on the Drawings. Spread and grade evenly, making the necessary allowances so that the required finished levels and contours may be achieved after light compaction.
Grassed areas are required to be finished flush with adjacent hard surfaces such as kerbs, paths and mowing strips.
Compaction
Prevent excess compaction by constructional plant. Compact lightly and uniformly in 150mm layers. Progressively tamp backfilling topsoil to avoid later subsidence, and thoroughly water to prevent voids. Rake over lightly to attain finished profiles. Avoid differential subsidence and produce a finished topsoil surface, which is:
at design levels as shown on Drawings;smooth and free from stones or lumps of soil;graded to drain freely, without ponding, to catchment points;graded evenly into adjoining ground surfaces; and
ready for planting.
Topsoil depths generally
Spread topsoil to the depths shown on the drawings.
FERTILISERSupply
Provide proprietary fertilisers, delivered to the site in sealed bags marked to show manufacturer or vendor, weight, fertiliser type, N:P:K ratio, recommended uses and application rates. Use in accordance with the recommendations.
Fertilizer Types & Rates: As shown on Drawings.
Application
Turfing: Mix the fertilizer thoroughly into the specified soil:
prior to spreading topsoil;immediately prior to the end of Establishment Period.
Plantings: Place fertilizer as shown on Standard Landscape Detail LD 126 at the time of planting.
TURFTurf
Obtain turf from an approved specialist grower of cultivated turf. Provide turf of even thickness, free from weeds and other foreign matter.
Supply
Deliver the turf from the supplier within 24 hours of being cut, and lay within 36 hours of cutting. Prevent it from drying out between cutting and laying.
Warranty
Furnish a warranty from the supplier that the turf is free from weeds and other foreign matters.
Turf species
Refer to the drawings for turf species.
Grade B turf with a minimum of 25mm attached topsoil unless otherwise specified.
Grade B: Shall have minimum 80% of the specified species.
WORKMANSHIPMULCH SPREADINGRequirement
Spread so that after settling it is:
smooth and evenly graded between design surface levels;
of the required depth and areas shown on the Drawings; and
sloped towards the base of plant stems in planting beds, but not closer than 50mm with the stem.
TURFINGFertilizing
Mix the fertilizer thoroughly into the topsoil before placing turf.
Laying
Lay the turf.
in "stretcher" pattern with the joints staggered and close butted;parallel with the long sides of level areas, and with contours on slopes;to design levels shown on Drawings;to finish flush, after tamping, with adjacent finished surfaces of ground, paving edging, or grass seeded areas;close butt all joints; and
species and grade shown on the Drawings.
Tamping
Lightly tamp to an even surface immediately after laying. Roll the turf with a roller weighing not more than 90 kg per metre of width for sandy or light soils.
Watering
Immediately after laying. Moisten the topsoil to its full depth. Continue watering as necessary to maintain moisture to this depth. Keep the turf in a healthy condition.
Maintain the grass at the required height by mowing. Carry out the last mowing within 7 days before the end of the planting establishment period.
Making good
Lift failed turf and relay with new turf.
Maintenance
Maintain the turfed areas until the attainment of a dense continuous sward of healthy and evenly green grass over the whole area. Lift failed turf and relay with new turf. Where levels have deviated from the design levels after placing and watering, lift turf and regrade topsoil to achieve design levels.
Top dressing
When the turfed area is established. Mow, remove cuttings and lightly top dress to all turfed areas to a depth of 10mm with top dressing as specified in 'TOP DRESSING LANDSCAPE'. Rub the dressing well into the joints and correct any unevenness in the turf surface.
Weeding
Remove weeds that emerge in the grassed areas, or where necessary spray with a selected herbicide for broad leafed weeds, to manufacturer's recommendations.
ENVIRONMENTAL REQUIREMENTSGENERALOUTLINE DESCRIPTIONApplication
This worksection applies to all activities that are required to be undertaken in compliance with the Environmental Protection Act 1994 and subordinate legislation, and with due regard to work, health and safety requirements associated with such work.
CROSS REFERENCESGeneral
Refer to the Preliminaries and General Requirements worksections.
EXECUTIONSTATUTORY REQUIREMENTSGeneral
Comply with the following as applicable:
Environmental Protection Act 1994.
Environmental Protection (Air) Policy 2008.
Environmental Protection (Noise) Policy 2008.
Environmental Protection (Water) Policy 2009.
Environmental Protection Regulation 2008.
Waste Reduction and Recycling Act 2011.
Land Protection (Pest and Stock Route Management) Act 2002.
Aboriginal Cultural Heritage Act 2003.
Vegetation Management Act 1999.
Nature Conservation Act 1992.
Water Act 2000.
Planning Act 2016
Planning Regulation 2017
Coastal Protection and Management Act 1995.
Fisheries Act 1994.
Environment Protection and Biodiversity Conservation Act 1999.
Reference guidelines
Where applicable, comply with requirements of the following guideline documents:
Best Practice Erosion and Sediment Control (Books 1 -4), International Erosion Control Association (IECA) Australasia, November 2008.
Monitoring and Sampling Manual 2009, Environmental Protection (Water) Policy 2009 Version 2 (Department of Environment and Resource Management, 2010).
AS 4970 Protection of Trees on Development Sites.
Queensland Acid Sulphate Soil Technical Manual: Soil Management Guidelines v4.0 (Department of Science, Information Technology, Innovation and the Arts, 2014).
CONSTRUCTION MANAGEMENT PLAN (ENVIRONMENTAL)Submission
Prepare a Construction Management Plan for the site:
detailing the planned sequence, methodology and program proposed for undertaking and environmental management of all work under the Contract; and
conforming to the requirements of the Contract.
Submit the Construction Management Plan to the Superintendent within 7 days of the date of the Letter of Acceptance, or at such later time as might be agreed, and prior to proceeding with any work under the Contract.
Liability of Principal limited
Receipt of the Construction Management Plan shall in no way relieve the Contractor of responsibility under the Contract to ensure compliance with environmental legislation and any approvals issued by the Environmental Protection Agency or other statutory authority as may be required in respect to work under the Contract.
Details
Address, as a minimum requirement, the following topics in the Construction Management Plan:
order of work under the Contract;Stormwater Management Plan
Soil Erosion and Sediment Control Plan;earthworks controls;Stock Piling Area Plan;dust control;noise control;weed control;temporary fencing, barricading and/or other access controls;temporary sanitary and waste services;storage of plant and materials, including any chemicals, fuels or other hazardous substances;engagement of a competent Environmental Officer;environmental training of employees and subcontractors where appropriate;any other items necessary to protect the surrounding environment.
Audits
The Superintendent may undertake, or direct, audits of the work under the Contract against the accepted Construction Management Plan (Environmental), the Specification, and legislation, at any time. The Contractor shall bring the work under the Contract into compliance with all Contractual requirements, if necessary, within the time notified after the audit.
ENVIRONMENTAL HARM OR BREACHESResponsibility
If an incident or non-compliance occurs, which may constitute an environmental harm or breach under the provisions of the Environmental Protection Act, immediately attend to the incident or non-compliance. Contain or prevent the likelihood of an environmental harm or breach, and protect public health and safety.
Notify the Superintendent immediately that such an incident or non-compliance occurs. Register each such incident with the Environmental Protection Agency and any other relevant statutory authority as necessary.
Restoration
If an incident or non-compliance occurs, comply with directions given by all relevant statutory authorities and the Superintendent, whether or not an environmental harm or breach is deemed to have occurred.
All costs and delays, including those related to restoration, that result from the incident or non-compliance shall be wholly borne by the Contractor, if the Principal determines that the incident or non-compliance resulted from an act or omission of the Contractor.
GENERAL ENVIRONMENTAL CONTROLSDust control
Restrict dust caused by the Works to a minimum.
Noise control
Take all practical precautions to minimise noise resulting from work under the Contract. Fit all construction equipment with noise suppressors and manage use so noise is minimised.
Runoff
Control runoff to minimise sediment loss from the site and pollution of natural waterways and municipal drainage systems. Additionally, comply with specific Local Authority requirements in addition to governing statutory requirements.
Fire protection
Burning of refuse or other materials or lighting of any fires is not permitted.
Storage on site
Store materials and equipment on site to prevent damage to the site and minimise hazards to persons, materials and equipment. Keep storage areas neat and tidy.
Site activities
Do not form new tracks, alter existing tracks, erect camps, remove trees or shrubs, cut fences, water, sewerage, power or telecommunication lines, or perform other activities not specified or indicated on the drawings or otherwise required under the Contract without prior approval by the Superintendent.
Disposal of wastes
Dispose of all construction wastes, site refuse and any solid or liquid contaminants resulting from work under the Contract in accordance with statutory and local authority requirements.
Acid sulphate soil
Treat and manage any disturbed or oxidised acid sulphate soil in accordance with the current Queensland Acid Sulphate Soil Technical Manual: Soil Management Guidelines document. This will ensure any disturbance to acid sulphate soils is managed to prevent impacts to the coastal environment and public safety.
EXISTING FLORAProtection
Protect from damage all trees and other plants which are shown or specified to be retained, or need not be removed or damaged for construction operations.
Tree protection
Tree protection zone: To AS4970 Section 3.
Tree protective measures: To AS4970 Section 4.
Work near trees
Harmful materials: Keep the area within the dripline free of sheds and paths, construction material and debris.
Work under trees: Do not remove topsoil from, or add topsoil to, the area within the dripline of the trees.
Hand methods: Use hand methods to locate, expose and cleanly remove the roots on the line of excavation.
VEGETATION CLEARINGExtent
Contain the extent of vegetation clearing to the limits specified or indicated on the drawings or otherwise approved by the Superintendent.
Disposal
Unless otherwise approved, no off-site disposal or burning of cleared vegetation is permitted. Put all cleared vegetation through a chipper and stockpile for re-use as mulch where directed. Materials may be reused in conjunction with environmental control measures if suitable. Dispose of excess or unwanted material in accordance with Local Authority requirements and guidelines.
SOIL EROSION AND SEDIMENT CONTROLGeneral
Undertake all work under the Contract to prevent erosion, contamination and sedimentation of the site, surrounding areas and drainage systems. Do not commence work on site prior to submitting a Soil Erosion and Sediment Control Plan to the Superintendent.
Control measures
Adopt such control measures as may be necessary, including the following where applicable:
staging of operations and sequence of work under the Contract (e.g. clearing, stripping, rehabilitation);
restoration of disturbed areas in progress with the work under the Contract;use of mulch materials to protect disturbed or exposed areas where suitable;provision of temporary drains and catch drains;application of diversion, dispersal and/or retention measures to concentrated flows to control and dissipate stormwater through the site without damage;spreader banks or other structures to disperse concentrated runoff;silt traps to prevent discharge sediment material to downstream areas;temporary grassing or other treatments (e.g. contour ploughing/bunding) to disturbed areas and long-term stockpiles; and
silt fencing.
Maintenance
Continually inspect and maintain control measures throughout the course of the work under the Contract and during the Defects Liability Period, and following each incidence of rain. Rearrange and reposition control measures as required to maintain their efficacy. Handle and dispose of sediment collected by control measures in an approved manner.
Removal
Remove all temporary control measures following rehabilitation or when otherwise no longer required.
IMPORTED SOIL MATERIALSTesting
Imported soil materials shall be sampled and tested or otherwise obtained from a certified source as being free from contaminants. Testing from non-certified sources shall be at a minimum rate of 1 sample per 50 m3 or as otherwise approved by the Environmental Protection Agency or Superintendent. Supply all test results and/or certificates to the Superintendent for verification prior to any site delivery of materials.
HEALTH PROTECTIONPrecautions
Take the precautions necessary to protect the health of persons on or within the vicinity of the site from conditions which are or may be dangerous to health, including the noxious effects of dust, fumes, liquids, infection, fire explosion or other hazards.
Hazardous materials
Notify the Superintendent immediately hazardous materials or conditions are found refer Preliminaries.
CONSTRUCTION WASTE MANAGEMENTGENERALAIMSResponsibilities
Undertake the reduction, reuse, recycling and disposal of waste building and civil infrastructure materials in accordance with this worksection and to demonstrate best practice for ecologically-sustainable development.
CROSS REFERENCESGeneral
Conform to the Preliminaries, General Requirements and Environmental Requirements worksections.
Associated worksectionsConform also to the Demolition and Asbestos Removal worksections (as applicable).
COMPLIANCE WITH STATUTORY AND OTHER REQUIREMENTSStatutory requirements
Comply with the following legislation as applicable:
Environmental Protection Act 1994.
Environmental Protection (Waste Management) Policy 2000.
Environmental Protection (Waste Management) Regulation 2000.
Environmental Protection Regulation 2008.
Reference guides
Waste Management Association of Australia.
SUBMISSIONSRecycling Management Plan
Prepare a Recycling Management Plan to achieve the nominated reuse / recycling targets as well as to maintain sufficient waste tracking records for the Works. Incorporate this Plan into the Construction Management Plan (Environmental) as a discrete sub-element for record-keeping and audit purposes. Submit within 7 days of acceptance, or at such later time as may be agreed with the Superintendent, but prior to commencement of any work under the Contract.
Details
Incorporate at least the following information in the Recycling Management Plan:
Commitment to the nominated reuse / recycling target and overall strategy for how this will be achieved.
Nomination of an appropriately-experienced individual to act as Waste Management Officer (WMO), who may or may not be the Environmental Management Officer (EMO), and oversee all waste management practices and processes, including training, supervision, reporting and auditing during the Contract period.
Nomination of Waste Subcontractor(s) for recycling and timing of waste collection services.
Identification of waste streams and confirmation that materials identified for recycling can be recycled in a cost-efficient manner and that local recyclers are available and prepared to take such materials.
Strategies and methodology for minimising resource use and waste generation and maximising reuse / recycling of building and civil infrastructure waste (see indicative trade-based template at the end of this worksection).
Strategies and practices for segregation, containment, storage, collection and disposal mechanisms for each category of waste.
Strategies and practices for segregation, containment, storage, safe handling and disposal mechanisms for hazardous and liquid wastes (which do not form part of target amounts).
Measurement techniques for the weight (or volume where appropriate) of each material to be reused / recycled or disposed of.
Recording and reporting procedures for waste management. Records must be kept by the Contractor to demonstrate the actual percentage of waste recycled by weight and these must be reported to the Superintendent monthly and at Practical Completion (see indicative templates with required reporting information at the end of this worksection).
Training and induction of employees and Subcontractors in waste management as appropriate.
Waste management monitoring and auditing procedures for all persons engaged in the Works, including Subcontractors.
Site plan indicating location of waste storage / separation area(s).
Any other items considered warranted to adhere to the waste management hierarchy.
EXECUTIONWASTE REUSE / RECYCLINGRequirement
Maximise the reuse or recycling of demolition and construction waste by all persons engaged in the Works, including Subcontractors and materials suppliers. The target for this project is to reuse or recycle minimum 40% by weight of each waste material stream and of the total demolition and construction waste materials that would otherwise be disposed of to landfill. Develop and implement a Recycling Management Plan to ensure this reuse / recycling target is achieved and that sufficient waste tracking records are maintained for the Works. Submit the Recycling Management Plan to the Superintendent and gain the Superintendents acceptance of proposed waste management implementation and reporting strategies before proceeding with the Works.
Where practical, sort waste materials prior to their removal from site. Follow the waste management hierarchy as outlined in the Environmental Protection (Waste Management) Policy 2000. Liaise with local authorities, commercial recycling organisations and community groups where the potential for recycling is evident.
Ensure that suppliers of building materials, components and systems also participate in recycling programs and otherwise assist in minimising generation of waste associated with the Works.
Maintain sufficient records in approved format to demonstrate total percentages of waste reused or recycled by weight. Make these results available to the Superintendent each month in accordance with the accepted reporting process.
Disposal of wastes
Dispose of demolition and construction wastes that cannot be reused or recycled, as well as site refuse and any solid or liquid contaminants resulting from work under the Contract, in accordance with statutory and local authority requirements.
Maintain records of all waste transport and disposal. Provide these records to the Superintendent progressively so that the Superintendent holds the full project waste disposal history on or before Practical Completion.
Materials separation
Where practical, establish areas for sorting and segregating demolition and construction wastes on site, using colour-coded and clearly marked containers for identified waste stream materials. Record these areas and the sorting / segregation process in the Recycling Management Plan.
Where on-site sorting is impractical or the management of demolition and construction waste recycling is otherwise outsourced, include equivalent details of off-site recycling procedures within the Recycling Management Plan.
Identified waste stream materials may include some or all of:
Cardboard.
Timber.
Ferrous metals.
Non-ferrous metals.
Soft plastic.
Polystyrene.
Insulation.
Concrete.
Glass.
Bricks.
Ceiling tiles.
Carpet.
Plaster.
Fabric.
Other waste materials applicable to individual projects.
Training
Conduct sufficient training for all persons engaged in the Works, including Subcontractors and materials suppliers as appropriate, to ensure satisfactory understanding of waste management protocols outlined in the Recycling Management Plan and required to be implemented under the Contract.
Record keeping and reporting
Maintain records to demonstrate the actual percentage (by weight) of each material reused / recycled / disposed of and corresponding evidence of where these materials were used / sold / disposed of. Make these results available to the Superintendent each month in the form of a Waste Management Performance Report (see sample template at the end of this worksection). Compile this information into an overall Waste Management Performance Summary on or before Practical Completion (see sample template at the end of this worksection).
Records for each separable portion of the Works which are to be made available to the Superintendent include:
the weight (or volume where applicable) of all outgoing loads for each waste / resource stream generated;the actual percentage (by weight) of each waste / resource stream reused, recycled or dumped;the destination of each waste stream (i.e. reuse application, licensed resource recovery / recycling facility, or landfill) and the name of the relevant recycler / Waste Subcontractor;
supporting evidence, including receipts from resource recovery / recycling facilities and landfill sites;monthly Waste Management Performance Reports, to include:
updates on the waste management performance (percentage of waste reused / recycled) to date in comparison with nominated targets;
evidence of total waste generated and total waste disposed to landfill to date;
measures to improve performance if requirements are not being achieved (with corresponding amendments to the Recycling Management Plan as required);
an overall Waste Management Performance Summary upon completion, clearly indicating the percentage of project waste materials (by weight) which were reused or recycled; and
certification (signed and dated) of all results and reports by the nominated Waste Management Officer confirming that nominated waste management requirements have been met.
Project waste auditing
Environmental audits of the Works may be organized by the Superintendent to confirm compliance with the accepted
TERMITE CONTROL
GENERALTERMITE MANAGEMENTRequirement
Provide a termite management system based on physical / non-chemical termite barriers to all new construction work. Approved termite management systems shall be consistent with Contract requirements and capable of protecting all primary building elements from subterranean termite attack for their design life, provided the manufacturers recommended inspection and maintenance practices are followed.
Definition
As well as structural timber members, primary building elements are defined in NCC 2016 Volume 2 as including all door jambs, window frames and reveals, architraves and skirtings.
CROSS REFERENCESGeneral
Refer to the General Requirements worksection.
STANDARDGeneral
Termite barriers: To AS3660.1.
Product appraisal
Mandatory requirement: Termite management systems used shall hold a current Code Mark or Certificate of Conformity including the expected life of the installation of at least 50 years required under the Queensland variation to the NCC.
QUALITYINSPECTIONWitness points
Give sufficient notice so that inspection may be made of the completed termite barriers by the supplier.
MATERIALS AND COMPONENTSPHYSICAL BARRIERSConcrete slab as part barrier
Standard: To AS3660.1 Section 4.
Termite protection at slab edges: Expose sound off-form slab edges minimum 75mm above finished ground level and without rendering, tiling, cladding or concealment by flashing. Protect slab edges at ramped entrances and abutments with carport slabs and pathways as for slab joints i.e. with embedment of a tested and approved barrier system component.
Slab services penetrations
Barrier type: Same as perimeter treatment or a tested and approved total system component.
Cap and strip shields
Projection: Install so that no edge is less than 55mm from the vertical face of the wall or pier.
Material: Galvanized steel.
PROPRIETARY SLAB ON GROUND SYSTEMSWoven stainless steel mesh barriers
Standard: To AS3660.1 Section 6.
Protection shall consist of approved continuous lapped stainless steel mesh termite barrier material used in conjunction with reinforced slab and masonry wall elements as part of an integrated physical barrier system. Proprietary systems shall use ultra marine grade stainless steel wire interwoven for strength into a fine mesh with maximum apertures sufficient to prevent passage by termite species endemic to South-East Queensland (or other region as directed).
Graded stone particles barriers
Standard: To AS3660.1 Section 7.
Capping for graded particle systems
Reinforced Concrete Strip 450mm x 100mm deep, Broom finish with tooled edge.
Physical barriers with a chemical impregnation (composite products)
Mandatory requirement: Contractor to provide a Material Safety Data Sheet declaring the product is not classified as hazardous according to the criteria of National Occupational Health and Safety Commission Australia and not a dangerous good according to the Australian Dangerous Goods code.
SUB-FLOOR VENTILATIONRequirement
For all forms of raised floor construction, provide sufficient clearance (i.e. at least 400mm) beneath structural members in accordance with NCC Volume 2, Figure 3.4.1 Diagram b. Sufficient clearance for access is a Principals requirement to permit regular structural integrity inspections, irrespective of the requirement for physical inspection of any proposed termite management system.
INSTALLATIONPHYSICAL BARRIERSProvide the physical barrier to the manufacturers recommendations to protect:
Service Penetrations.
Cavity brick walls including internal leaf gaps.
200 concrete blockworks/retaining walls.
Brick veneer walls.
Joins in the concrete slab.
Junctions with external paving where paving is less than 75mm below floor slab or weep holes.
Any location required to complete the installation.
Extent
Use a proprietary system installed as a Physical Barrier for a Partial Installation - Perimeter and penetrations to the requirements of AS 3660. Proprietary systems shall be installed in strict accordance with the manufacturers written recommendations, including ancillary parging and other installation measures as required.
Approved Subcontractors
The work must be performed by an approved specialist subcontractor, approved and licensed by the manufacturer.
Certification
Furnish a Certificate and a warranty satisfactory to the Principal from the subcontractor to the Principal.
APPLIED CHEMICAL SOIL BARRIERSNot to be used in new construction.
COMPLETIONCOMPLETIONTermite barrier notice
Provide two durable notices. Permanently fix one in a prominent location in accordance with NCC B1.4(i)(ii) or NCC 3.1.3.2(b) and AS3660.1 Appendix A. Include the other in the project Maintenance Manual along with the warranty.
Warranty
Terms: Provide a warranty in accordance with AS3660.1 valid for a period of 10 years and covering:
Reinstallation necessitated by termite attack.
Replacement of timber attacked by termites.
Removal and reinstatement of building contents, whether built-in or not, as necessary to replace affected timber.
Completion inspection
At the end of the defects liability period, inspect the termite control systems and submit a report on their efficacy and status.
400 planter boxes
1GENERAL1.1SCOPE OF SECTIONGeneral
This section refers to the planter boxes. Refer to the drawings, engineers details where applicable, and project specific requirements. Supply and install Fytogreen planter box.
Beige in colour Planter F from attached brochure.
Planter-Boxes-Brochure-2018-.pdf (fytogreen.com.au)Install and fix as per manufactures specification.
9. Roof top concrete paving system
General
Provide a rooftop paving system as documented.
Refer to the drawings, engineers details, and project specific requirements
Requirements: Conform to the following:
- Light weight system designed to eliminate the use of sand when laying pavers.
- Adjustable in height to achieve design falls.
- Able to accommodate the installation of services within the cavity under the elevated platform.
- Increases heat insulation.
- Reduces sound transmission.
- Allow access to waterproofing membrane.
Product:
Location as per drawings.
Paving supports - VersiPave GP ( https://elmich.com.au/products/versipave-2/ )
Concrete paver Adbri Euro Classic ( https://www.adbrimasonry.com.au/commercials/paving/paving-ranges/euro-classic-dc )
Size 400x400x40
Colour - Athens
Warranty: The installer contractor needs to match the manufactures warranty.
410Waterproofing
1GENERAL
1.1SCOPE OF SECTION
General
Roof waterproofing to be as per attached product data sheet.
Standard: Australian Standard
400 SHADE SAILS
1GENERAL1.1SCOPE OF SECTIONGeneral
This section refers to the shade sails. Refer to the drawings, engineers details where applicable, and project specific requirements. The Shade sail is heavy duty shade cloth is an industrial textile made from High Density Polyethylene (HDPE) yarn, which has ultraviolet stabilisers and colour pigments incorporated into the structure.
HDPE is resistant to most acids and alkalis, and fungal attack. It does not absorb water, which is a significant factor in resisting staining and inhibiting mildew growth. These characteristics make HDPE ideal as a base yarn for a lightweight, strong shade cloth.
Standard : Australian Standard As4174:2018 knitted and Woven Fabrics, Section 3.3 Resistance to degradation by light.
Warranty: The installer contractor needs to match the manufactures warranty.
Cleaning and Maintenance: Cleaning and Maintenance is to be carried out to manufacturers recommendations. (HTTps://polyfab.com.au/product/comshade Shade sail care and maintenance instructions)
Specifications:
ASBESTOS AND DEMOLITION CHECKLIST
OCTOBER 2016
Work Health and Safety Act 2011 (WHS Act) Work Health and Safety Regulation 2017(WHS Regulation)
Completed by Date Time
Company name Nominated supervisor
Site address Contact number
Checklist WHS Regulation Yes No N/A Notes/comments
Is the workplace secured from unauthorised access?
298
Are barricades erected to delineate the asbestos removal area?
469
Is there adequate signage for asbestos removal work?
469 Are adequate facilities available for workers (toilets, meal area, drinking water, means to wash hands)?
41
Is there an adequate first aid kit available?
42
Is someone trained in first aid?
42
Is there an emergency plan for the workplace?
43
Is the designated asbestos supervisor present for friable work?
459 and 529 Is the designated asbestos supervisor present for non friable work
(ie able to arrive at the workplace within 20 minutes)?
459 and 529 Does the contractor hold the correct licence for the work being undertaken?
485 and 487
Checklist WHS Regulation Yes No N/A Notes/comments
Has licensed asbestos removal work been notified to SafeWork NSW?
142 and 466
Are work surfaces and access ways clear of debris and trip hazards?
40
Is there an asbestos removal control plan prepared?
464
Is the Asbestos Removal Control Plan readily accessible?
465 Are there arrangements (eg health and safety representative, health and safety committee or other agreed arrangements) to consult with workers on safety matters?
Sections 47 49 of the WHS Act Have safe work method statements been prepared for high risk construction work?
299
Is there an asbestos register?
450 and 463 Has the structure been inspected to determine whether asbestos is present?
451453
Do all persons working with asbestos have correct training?
460
Do all workers have construction induction cards?
316
Is plant inspected on a regular basis?
213
Do workers have high risk work licences (if required)?
81 Is correct personal protective equipment provided, fit tested, and used?
44
Have all services been disconnected (ie electrical, gas, water, fire)?
163
Is dust generated by demolition activity being controlled?
35
If air monitoring is undertaken, is it done by a competent person?
475 and 482 Are workers prevented from falling through open penetrations and unprotected edges?
78 Are exclusion zones or overhead protection in place to stop building debris from falling on workers below?
54
Is a compliant scaffold provided?
225
Has the handover certificate been provided for the scaffold?
225
2/3
Checklist WHS Regulation Yes No N/A Notes/comments
For a Class A Friable Asbestos Removal License holder, is there a current certified safety management system in place?
493 Are arrangements in place for a clearance inspection to be carried out, after asbestos is removed, by an independent licensed assessor or competent person?
473 Is asbestos waste and contaminated PPE planned to be
disposed of as soon as practicable at a site authorised to accept asbestos waste?
472
Has notification of asbestos removal been given to the neighbours?
467 Are there facilities available to decontaminate the following: asbestos removal area, plant used in the asbestos removal area, workers carrying out asbestos removal work, other persons who have access to the asbestos removal area?
471 Does the licence holder have systems in place for decontamination and annual maintenance of Class H asbestos vacuum cleaners?
35 Has health monitoring for workers been undertaken by a licensed medical practitioner?
435444 Notes
Catalogue No. SW08481
ISBN 978 1 74341 158 2Copyright SafeWork NSW 1117 Locked Bag 2906, Lisarow, NSW 2252 | Customer Service Centre 13 10 50
SafeWork NSW, 92100 Donnison Street, Gosford, NSW 2250 Website www.safework.nsw.gov.au