diff_months: 11

Case studies in

Download Solution Now
Added on: 2024-11-21 07:00:22
Order Code: SA Student Vijay Management Assignment(10_23_37905_798)
Question Task Id: 497516

5

Case studies in

resourCe ManageMent

Resource management in a global environment gets very tricky and

requires continual monitoring. In particular, a global projects bud-

get management can be a constant struggle. Listening to experts

and evaluating input from experienced people outside of your proj-

ect team always helps to avoid pitfalls during the execution of your

global project.

I had a challenging experience with my companys information

technology department in one of my long- term projects. Computer

and information technology was advancing at a mind- boggling speed

at the turn of the century. A computers operating system, processor,

memory, and hard drive capacity became obsolete in six months. I

took it upon myself to improve our information technology depart-

ment in order to save my project in Case5.1.

After two months into a high volume production project, our sub-

contractor in Japan announced that they were shutting down their

operations which produced a critical component for our assembly

in three months. is was quite a shock to me and to my company.

Case5.2 describes the actions that I took to remedy this issue.

While working with leading-edge technology small- sized sub-

contractors during a project, lots of unforeseen issues can pop up.

oroughly understanding the capabilities of the personnel, equip-

ment, and processes being used in these companies can cut down on

undesirable issues as shown in Case5.3.

In dealing with international project teams from dierent coun-

tries, there is always a dierence in adrenaline rush and excitement

for meetings and project tasks. I experienced an adrenaline rush and

excitement toward project meetings and tasks at the higher end of the

spectrum from team members in countries such as Japan and Germany

and at the lower end of the spectrum from team members in countries

120

Project ManageMent case studIes

such as Malaysia, Mexico, and countries in the Mediterranean region.

I detail my encounters in dierent countries in Case5.4.

During the execution of a project, always keep the pressure on your

team members, but do not overdo it and burn them out. In this day

and age, continuous connectivity to our team members can be very

hazardous and stressful, if it is not handled with care. Such events are

detailed in Case5.5.

Listening is the greatest virtue of a project manager. When I ran

into trouble while executing a task, I listened to all ideas that would

cure the issue at hand. Such a nagging problem is detailed in Case5.6.

After trying a new interface system for over a month in our wafer fab-

rication lines, we saw signicant increases in wafer yields. Also, wafer

throughputs improved. Holdups for a shutdown process decreased

signicantly. I made this new process engineering shift interface

meeting a standard for our wafer factory.

If a task in a project reaches a re- ghting mode, your decision-

making process to cure the issue accelerates very fast. You are in an

urgent rescue mode. After being in a re- ghting mode for two weeks

to troubleshoot a control panel via telephone conversations in a remote

location in Norway with a novice engineer, I had to take drastic action

as detailed in Case5.7.

In some cases, we have to rescue our subcontractors from a bind. I

tasked two engineers on my team to improve a critical Japanese suppli-

ers falling yields. As a project manager, it was my responsibility to help

my subcontractor in any way that I could. As a result of this urgent

six- week long rescue mission, our products nal test yields improved

immensely and they were steady. ese details are given in Case5.8.

Listening to all of the input regarding your projects tasks and

ltering them down to useful ones is an art in itself. Such input is

detailed in Case5.9.

Some tasks in our global projects require us to deal with foreign

government agencies. Bureaucracy in a foreign government can hurt

your project in many ways. You have to go along with experts to solve

your problems with bureaucrats even if it costs your project an arm

and a leg as detailed in Case5.10.

As global project managers, we have to be on top of all ancillary

tasks such as shipping rules and regulations of our nished products.

If we leave these ancillary tasks alone, they might harm our project

121

case studIes In resource ManageMent

tremendously in one way or another. In Case5.11, I missed details of

the insurance coverage for my projects nished products shipment.

At the bidding phase of a project, we might have to partner with

other companies in order to strengthen our position. At the beginning

of a project, all project partners look eager and willing to win the bid.

Many unforeseen issues might surface with our project partners dur-

ing the execution phase of the project. As project managers, it is our

responsibility to remedy these project partner issues as fast as we can

without damaging the cost and schedule performance of our project.

An example is given in Case5.12.

Sometimes cost performance of a task might be hit by unexpected

increases in material costs. I had a project to design, build, and test

20 high- load capacity and high- pressure hydraulic cylinders for a cus-

tomer in Brazil. I had to scramble to get my cost performance under

control as detailed in Case5.13.

Monitoring schedule and cost performance of a global project very

closely at regular intervals is a must for a project manager. You have

to bring your companys other departments in sync with your projects

dynamic environment. e challenge is to be able to collect all sched-

ule and cost performance data in a timely fashion from your foreign

project partners as shown in Case5.14.

Case5.1: Dependence on Other Departments

During the execution of a project, a project manager depends on

performances of other departments in the company. e purchas-

ing department is the key player in purchased components for

the project and in establishing contracts for subcontractors and

consultants joining the project team. e accounting department

has to execute correctly and in a timely fashion the projects pay-

ables and receivables and charges to project charge numbers. e

drafting department has to prepare and release drawings, manu-

facturing process instructions, and quality assurance instructions

according to promised schedules. e sales department has to

coordinate with the project manager closely for a projects con-

tract extension and for related competitive bids to a project. Every

department in your company contributes to your project in one

way or another during the execution phase.

I had a challenging experience with my companys informa-

tion technology (IT) department in one of my long- term projects.

122

Project ManageMent case studIes

Computer and information technology were advancing at a mind-

boggling speed at the turn of the century. A computers operat-

ing system, processor, memory, and hard drive capacity became

obsolete in six months. You had to improve your computers per-

formance at most in a year in order to keep up with the changing

world. In parallel to improved computer performance, software

that was used in my projects was going through revisions to uti-

lize enhances in hardware performance. I had an IT department

in my company, as the saying goes, that always liked to squeeze

the lemon to the last drop. ey dragged their feet in upgrading

my teams hardware, software, and communication tools. is

type of mentality aected the performance of my engineers who

always wanted to be in sync with leading-edge technology. When

I made an upgrade request, it took them two to four weeks to

respond. I had several meetings with the head of our IT depart-

ment regarding timely upgrades to our IT tools. I told him how

demoralizing the situation was for my engineers. I told him that

if our IT tools were not at the leading edge of technology then

our company could not stay at the leading edge for long. He kept

complaining about his budgetary and personnel issues. He did

not change his style of service a bit to my requests. After two

months of frustration, I went up the ladder to his boss. I called a

meeting with the IT manager and his boss. I went over all hard-

ware, software, and communication, especially videoconferenc-

ing, issues. I sensed during the meeting that the IT manager was

being protected by his boss. Changes were not going to happen as

swiftly as I liked. eir vision was to reduce the IT departments

budget and use all IT tools that we had as long as possible.

en I went and discussed the IT department issues with other

department heads. All department heads had similar complaints

to mine, but their complaints were not as urgent as mine. I con-

vinced all department heads that something had to be done fast

to change the existing IT department mission. Two of the other

department heads and myself agreed to take our case a notch

higher to the president of the company. I called a meeting with

our president and also invited the IT department managers boss

to the meeting.

e meeting with the president, the IT department managers

boss, two department heads, and I lasted over two hours. I pre-

sented all my teams IT department issues that I encountered dur-

ing the execution of my project. e other two department heads

presented their issues too. e IT department managers boss

123

case studIes In resource ManageMent

was continually in a protective mood. At the end of the meet-

ing, our president promised to take constructive action immedi-

ately to improve the situation. A week passed and I got the news

that our IT department head had resigned or been let go. ere

was also reshuing of responsibilities in upper management.

e IT department started to report directly to the president. e

company searched and hired a new vice president of IT from a

well- known computer technology company. After six months of

continual struggle, my engineers and I started to see a bright light

at the end of the IT tunnel.

e execution of a project can be bogged down and sometimes

a project manager can experience long delays and cost overruns to

his projects tasks due to poor performance by other departments

in a company. Taking immediate action to correct issues at hand

with other departments is a must. e whole company has to run

smoothly and eciently on all cylinders in order to complete a

project successfully.

LESSONS LEARNED FROM THIS PROJECT EVENT

e IT department is a very crucial segment of your

company in this day and age.

Getting consensus with department heads to solve an

issue gathers momentum and helps you to achieve your

goal in a timely fashion.

All departments in your company have to function well

in order for your project to succeed.

Case5.2: Subcontractor Announcement

of Shutting Down Operations

We were qualied and were running a high volume production

of computer subassemblies for a U.S. computer manufacturer. A

critical component for our computer subassemblies was being sup-

plied by a sole source Japanese subcontractor. After two months

into the high volume production, our subcontractor in Japan

announced that they were shutting down their operations that

produced the critical component in three months. is was quite

a shock to me and to my company. At that time, I was head-

ing the engineering team for volume production of computer

subassemblies. I immediately had several telephone conversa-

tions with our subcontractor to understand the reasoning behind

their unexpected shutdown. Apparently, the critical component

124

Project ManageMent case studIes

manufacturing was not protable enough for them and the new

president of the company decided to end this divisions operations.

My company proposed several options to keep them going until

high volume production of computer subassemblies for our U.S.

computer manufacturer continued. To qualify a new subcontrac-

tor for this critical component would be a tremendous undertak-

ing at this stage of the game. My company oered to help them

nancially or even buy their division out to no avail.

I told our president that we should not inform our U.S. cus-

tomer until we had a detailed solid plan to qualify alternate

sources for this critical component. Our president agreed with me

and assigned me to prepare the qualication plan in three work-

ing days. After the internal review of the qualication plan, we

were going to go to our customer and present it in person.

I had three alternate subcontractor choices for this critical

component. One was in the Bay Area. e second one was again

in Japan, and the third one was in Malaysia. I immediately went

to our purchasing director and asked him to nd out in two days

their available production capacities for this critical component

and their pricing. ese were the two most important inputs to

start our qualication plan. It turned out that the sum of any

two of the subcontractors production capacities could satisfy our

needs. We ranked these three subcontractors with the purchas-

ing manager using several critical criteria such as quality control,

product reliability, stability of the subcontractor, pricing, and

capacity. e subcontractors in the Bay Area and in Japan came in

on top. We decided to prepare qualication plans with these two

subcontractors and present them to our customer.

I called our customers project manager immediately and

explained the unfortunate upcoming snag to our volume produc-

tion. I detailed our course of action with two new subcontractors.

I also detailed the qualication plans that we would be pursuing

in the next three months. I emphasized their involvement in the

qualication process. Our customer had to evaluate 200 computer

subassemblies, 100 from each new subcontractor, with new criti-

cal components in two weeks. Our customers project manager

agreed to do his part on time so that we would not disrupt the

volume production process.

I sent two engineering teams, one to each potential subcon-

tractor, for a detailed qualication process. Major areas of concern

were operator training, product change control, quality control,

and incoming material control. It took the teams one week to

125

case studIes In resource ManageMent

evaluate these two potential subcontractors. Both teams had

very promising reports about these two new subcontractors. We

decided to bring both subcontractors on board on equal footing.

We did not want to rely heavily on one of them. Both subcontrac-

tors provided us with qualication components with measured

critical parameters in four weeks. en we built computer sub-

assemblies for qualication using these new critical components

in ve weeks.

I hand carried the qualication lots to our customer. ey

tested 200 computer subassemblies in their computers while

I watched over their shoulders. Fortunately, there were no sur-

prises. Our customers project manager gave us the green light to

use the new critical component in our computer subassemblies as

promised in two weeks.

is surprising change to our product came without adequate

warning. I had to adapt to this change fast. I had to also con-

vince my customer about the steps I was taking to deal with this

change. We were lucky that there were other alternate solutions

to this problem. My mistake was originally to go with a single

source for the critical component. I should have qualied at least

two subcontractors for this critical component at the beginning of

the volume production process.

LESSONS LEARNED FROM THIS PROJECT EVENT

A surprising event can occur unexpectedly at a reliable

subcontractor.

Prepare a detailed and complete alternate plan before

approaching your customer with a way out of the

showstopper.

Always qualify multiple sources for critical components

of your project.

Case5.3: Subcontracting to Small Leading-Edge

Technology Companies

Subcontracting to small leading-edge technology companies can

be very tricky and time consuming during the execution of a

global project. Continual monitoring of such companies is a must

in order to assure that they are always up to a high level of opera-

tional standards and their personnel turnover does not hamper

your projects progress.

126

Project ManageMent case studIes

I was leading a team of engineers to supply high-volume mag-

netic recording sensors to our customers around the globe. Our

supply chain originated in our wafer fabrications in California

and branched into higher assemblies in South Korea, Malaysia,

Singapore, and Puerto Rico. Surfaces of our read- write sensors

had to be free of any contaminants before being installed into

disk drives. Our nal operations were performed in class-10 clean

room environments. We were supplying thousands of sensors a

week to dierent customers. Our major sensor lot rejection cause

by customers was contamination. Several lots per week were put

on hold or rejected by our customers for sensor surface contami-

nation. I had a subteam whose mission was to identify surface

contaminants, track down their sources, and eliminate them from

occurring again.

For U.S. customers, we brought contaminated sensors to our

material evaluation laboratories in California. We did failure

analysis using advanced state of the art auger spectroscopy, energy

dispersive x- ray spectroscopy, and atomic force microscopy. We

had well- trained technicians in all three shifts. We were able to

get surface analysis reports in a day to respond with our correc-

tive actions to our customers. Fast turnaround in corrective action

was a must in just- in- time supplier chain requirements from our

customers. I had to set up failure analysis laboratories for our cus-

tomer centers in Singapore, Japan, and Europe.

My team and I searched and sourced three leading-edge technol-

ogy contamination evaluation laboratories in each location. I sent

my engineers to these laboratories for qualication. We explained

our failure analysis requirements for surface contaminants on our

sensors. We checked their operations, nancial stability, measure-

ment costs, type of equipment they had for measurements, equip-

ment downtime, equipment repair structure, equipment spare

parts situation, their technicians measurement training and expe-

rience, sample preparation techniques, measurement prioritization

and turnaround time, failure analysis reporting time table, and so

on. After a thorough comparative analysis, we chose one labora-

tory at each location to be our failure analysis center.

My team and I had to check on these three leading-edge tech-

nology laboratories periodically. We had to make sure that they

were upgrading their equipment to the most advanced ones that

provided accurate elemental and chemical compositions of con-

taminants on the surfaces of our sensors. We had to make sure

that they were not losing their experienced technicians. We had

127

case studIes In resource ManageMent

some issues with lost sensors and miscommunication. We were

constantly discussing how to improve and how to expedite our

failure analyses within our partnership.

Several times while the failure analysis was going on, I had to

send one of my engineers and a couple of inspectors to my cus-

tomers facilities to sort our sensors. We had to separate good sen-

sors from contaminated ones under high- powered microscopes in

a Class-10 clean room environment so that my customers auto-

mated assembly lines would not slow down or come to a halt due

to the lack of our sensors.

In a just- in- time high- volume relationship with our customers,

I had to form such a global failure analysis group with leading-

edge technology small laboratories. It took my team and me six

months to form our failure analysis network, but in the end it

worked out very successfully for many years to come. Our cus-

tomers were very satised with our response time and corrective

actions to contamination issues in our magnetic recording sensors.

LESSONS LEARNED FROM THIS PROJECT EVENT

To qualify small leading-edge technology companies for

your project will require extensive scrutinizing and will

take more time.

To set up a global network for a crucial project task is

always a challenge for a project manager.

Case5.4: Latitude versus Attitude

When dealing with international project teams from dierent

countries, there was always a dierence in adrenaline rush and

excitement toward meetings and project tasks. I experienced

adrenaline rush and excitement toward project meetings and tasks

at the higher end of the spectrum from team members in coun-

tries such as Japan and Germany and at the lower end of the spec-

trum from team members in countries such as Malaysia, Mexico,

and countries in the Mediterranean region.

I dealt with team members from Malaysia, Mexico, and

Southern Turkey who often claimed that they never committed

to completing a given task on a mutually determined completion

time. eir behavior was inconsistent and uncooperative, and they

ignored my multiple requests and task deadlines. ey had to be

micromanaged and pushed to complete a task with quality. ey

had a lackadaisical work behavior. Of course this behavior was not

128

Project ManageMent case studIes

true for all team members from those regions, but most of them

had lower concentration and negative behavior. I attributed this

kind of behavior to the warm and humid climate in those coun-

tries and to their traditional work ethics.

In colder climates such as in Japan and Germany, people devel-

oped survival intelligence, they became practical, aggressive, and

competitive. Science and technology mushroomed from these

kinds of behaviors in the Western world.

For example, during my projects in Malaysia, I had issues with

my team members coming to meetings late and not being pre-

pared. Some team members walked into the conference room 10

or 15 minutes late. Some of them did not have a clue as to what

they had to present or what to contribute at that meeting. ey

obviously did not read their meeting invitation e- mail in detail.

I constantly reminded my team members that meetings were not

for kicking back and for being in another world. Everyone had

to be on their toes and contribute during a meeting even if it was

not their turn to present their part. I joked with the latecomers to

the meetings that I was going to charge a U.S. dollar per minute

that they were late to the meeting so that we could all go out and

have a feisty lunch every week. I kindly asked the latecomers to

be on time to the meetings with no success. en I went to their

supervisors and asked them kindly to correct the situation by talk-

ing to their people. e supervisors discussions with their people

helped the situation a little, but it was dicult to get rid of bad

habits. en I went up to the general manager of the company

and asked him to issue a stern memorandum for timely attendance

and well preparedness to all meetings. e stern memorandum

did the trick and all my team members got the message. After two

months of determination, my team meetings got into a productive

and a precise rhythm.

I also had issues with promised action item completion times

in countries such as Malaysia, Mexico, and countries in the

Mediterranean region. If I were given an action item completion

time by a Japanese engineer, the task was done before or right at

the promised completion time. If a Japanese engineer had prob-

lems with completing his task, he came and asked me for help or

for an extension to complete the promised action item. However,

in Mexico if an engineer promised me an action item completion

time, he came with his results a day to a week late. In these warm

regions of the world, the only way to keep my team members on

their toes was to micromanage them. I had to talk to them daily

129

case studIes In resource ManageMent

or even hourly to push them and to monitor their progress in a

given task.

Most of my team members in these warmer regions of the world

also had a relaxed behavior toward our customers and our subcon-

tractors. I emphasized that when a customer or a subcontractor

visited our plant we had to be well prepared and had to be sharp.

I want to emphasize that these lackadaisical behaviors surfaced

in the majority of my team members and not in all of them. It is

very dicult to change human behaviors in other countries. You

have to be exible, adjust, and learn how to deal with the situation

at hand. Jimmy Buetts song lyrics describe project team mem-

bers behavior in dierent countries well. With these changes in

latitudes, changes in attitudes, nothing remains quite the same.

LESSONS LEARNED FROM THIS PROJECT EVENT

In a global project environment, work habits and atti-

tudes vary vastly from country to country.

Changing well- ingrained habits in your global team

members can take lots of patience and continual guid-

ance on your part to correct.

Case5.5: Stress from 24/7 Connectivity

Internet and cell phone connections are getting faster, cheaper,

and more reliable every day. ese wireless connections are

achieved from anywhere on Earth, even ying at 35,000 feet

above the ground or while vacationing on a remote Tahitian

island. Continual advances in e- mailing, tweeting, cell phoning,

text messaging, ease of data transfer, videoconferencing, and wire-

less networking make the life of a global project manager much

easier. Anyone on your project team can instantly work with their

les, programs, and networks from anywhere on Earth just as if

they were at their own desks. A global project manager has to lay

down ground rules for 24/7 communication with all team mem-

bers, including subcontractors and customers around the world, at

kicko meetings of a project.

During the execution phase of a global project, a team member

can get inundated by e- mails, cell phone calls, text messages, and

so forth. ese 24/7 communications can occur during lunchtime,

dinner time, sleep time, or even during weekends, holidays, and

vacations. A conscientious team member will try to respond to all

messages in a timely fashion while sacricing his or her personal

130

Project ManageMent case studIes

life. ese kinds of 24/7 connections can cause overload and burn

out team members and the project manager fast. A 24/7-con-

nected environment will bring good things to a global project, but

the global project manager has to orchestrate and apply a fair bal-

ance between continuous connectivity and the private life of every

team member so that stress levels stay at normal levels during the

execution of a global project.

A good engineering friend of mine was working on an interna-

tional companys restructuring project team. He was a very con-

scientious worker. He checked his e- mails every half an hour from

the time he woke up until he went to bed. He always answered

his cell phone. One Saturday night we agreed to go out to dinner

together. He made a reservation at a good Italian restaurant, which

was very hard to get into. He brought his girlfriend. I brought

my wife. We were about to sit at our reserved table and his cell

phone rang. He answered his phone and ran out of the restaurant

to talk to the caller. We sat down at our table and waited for my

friend to return. After ve minutes he returned with a very sul-

len face. He told us that the call came from his project manager.

His project manager urgently wanted a couple of graphs from him

during the next hour. My friend told his project manager that

he was at dinner with us, but his project manager insisted on his

untimely demand. My friend had to excuse himself from dinner

and go home to his laptop. I learned later that his project manager

was a workaholic and was very rigid with his untimely demands.

He sometimes called my friend at midnight and during weekends

with excessive requests. My friend worked on that project team

for a month and then gave his notice to leave the company. He was

totally stressed out from 24/7 connectivity to his team and from

an unreasonably demanding project manager. My friend immedi-

ately started his own company and became quite successful. In a

way he was thankful for his previous project managers unaccept-

able behavior.

Interactive design and development by teams around the globe

are also an integral part of a global project. I was the project

manager of a chip design team in California that was constantly

interfacing with our German counterparts. Eight hours of time

dierence between the two design locations made me structure

feasible meeting and interaction times in order to reduce work

stress on both parties. I even allowed two of my design engineers

to work the night shift in California for two months in order to

have real- time interaction with their German counterparts. e

131

case studIes In resource ManageMent

proposal to work the night shift in real time with the Germans

during the design of the chips software was suggested by my engi-

neers. Real- time interaction between two design parties reduced

time and error in completing their design tasks.

A project manager colleague of mine was working with a sub-

team in India to manufacture computer components. A twelve

and a half hour time dierence between India and California

required him to take several steps to reduce work- related stress

from continuous connectivity. He set up videoconferencing from

7:30p.m. to 9p.m. California time on every Monday. He asked

his California team members not to call their Indian teammates

from 6:30a.m. to 7:30p.m. California time during the work week

and during weekends. He also listed all Indian holidays when

communication was to be stopped. e project manager had to

establish these communication rules for his project during the

kicko phase of his project.

LESSONS LEARNED FROM THIS PROJECT EVENT

Stress levels of your global team members can increase

exponentially in a 24/7-connected environment.

24/7-communication rules between your global team

members, your global customers, and your global sub-

contractors have to be laid out by you at the kicko meet-

ings of a project.

Case5.6: Engineering Interface

among Wafer Fabrication Shifts

Wafer fabrication engineering requires detailed recording and cor-

recting for out- of- specication conditions, scrap reasons, equip-

ment malfunctions, corrective actions, and variations in control

charts. Our wafer factory was working in three shifts for seven

days. Wafer fabrications process engineering hours were 7a.m. to

3p.m. for the day shift, 3p.m. to 11p.m. for the swing shift, and

11p.m. to 7a.m. for the night shift. I had six process engineers

in each shift. One was a principal process engineer for deposition

processes and the backup for ion milling processes. e second one

was a principal engineer for ion milling processes and the backup

for deposition processes. e third one was a principal process

engineer for photolithography and the backup for plate and etch-

ing processes. e fourth process engineer was the principal for

plate and etch processes and the backup for photolithography. e

132

Project ManageMent case studIes

fth process engineer was the principal for wafer testing and the

backup for clean room environment. My sixth process engineer

was the principal for the clean room environment and the backup

for wafer testing. All the important events that happened during a

shift were recorded in six dierent logbooks, one for every process

center, and critical action items were being sent to the next shifts

engineers by using six dierent e- mail folders, again one for every

process center.

e system was working okay, but it was not perfect. Several

items, some of them critical, were falling through the cracks.

ere were misinterpretations of messages written in logbooks

and in e- mail folders. I was getting several telephone calls a

night from the swing shift and the night shift engineers ask-

ing me to explain some of the comments written about a pro-

cess or about malfunctioning equipment. Even I could not help

explain some of the condensed phrases. Comments like sput-

tering equipment 1 is acting and photolithography curing

plates had temperature problems were causing us to do exten-

sive detective work to nd the particular malfunction. We had

to improve our wafer yields continually and the process engi-

neering communication system between shifts was hampering

our progress. I had several meetings with my engineers from

every shift and we discussed in detail how to improve our com-

munication procedures between shifts. We decided to record

more precise and detailed information regarding every issue

during a shift. All of my engineers complied very well, but still

it was not a good communication system between the shifts.

We had over 200 operations and equipment in six process

centers in the wafer factory. is kind of very dynamic and con-

tinuous process environment did not allow any mistakes or any

shortcuts to overcome the issues that popped up. All of the sput-

tering engineers had to be on the same page on all shifts. All of

the photolithography engineers had to be on the same page, even

on the same line, on all shifts.

During one of my process engineering meetings, one of the

engineers proposed a good idea to extend our shift hours by half

an hour and have a face to face between the shift engineers. I

talked to every engineer and got their consent to extend their

work hour by half an hour. I also talked with human resources

to make sure that we were not violating any overtime regula-

tions. Salaried engineers did not get paid for overtime in this

133

case studIes In resource ManageMent

company. Everyone agreed to the new schedule and to the shift

interaction meeting.

Wafer fabrications process engineering new hours were 7a.m.

to 3:30p.m. for the day shift, 3p.m. to 11:30p.m. for the swing

shift, and 11p.m. to 7:30a.m. for the night shift. We started to

have process engineering shift interface meetings from 7 a.m. to

7:30a.m. for the night shift and day shift engineers, from 3 p.m.

to 3:30p.m. for the day shift and swing shift engineers, and from

11 p.m. to 11:30p.m. for the swing shift and night shift engi-

neers. I attended all three meetings every day. I took the meeting

notes and distributed action items list to the appropriate people.

Sometimes we could not complete all current issues in a half an

hour meeting. Some meetings extended to an hour.

After trying this new interface system for over a month, we

saw signicant increases in wafer yields. Also, wafer throughputs

improved. Holdups for a shutdown process decreased signi-

cantly. I made this new process engineering shift interface meet-

ing a standard for our wafer factory. I also covered the extra time

that engineers were spending in these shift interface meetings in

their annual bonus awards. My boss and the company president

agreed to award extra bonuses for my process engineers for their

voluntary agreement to spend extra time for shift interface meet-

ings, which caused our wafer yields to improve continually.

LESSONS LEARNED FROM THIS PROJECT EVENT

24/7-production operations require face- to- face interac-

tion between shift engineers and operators.

Depending on only written communications between

production shifts can cause misinterpretations.

Written communication plus face- to- face interaction

between production shifts reduces the possibility of errors.

Case5.7: Fire Fighting during the Installation

of a System on an Oshore Oil Platform

I was the project manager of a large project to design, build, and

install an automated positioning system on a new oshore oil

platform. e design and construction of the system were com-

pleted in the United States. e system components were shipped

to Norway for installation. I had to send an application engineer

134

Project ManageMent case studIes

to Norway to see the installation of the positioning system on the

new oil platform and train the responsible people from our cus-

tomers team for its operation and maintenance.

I had a young and very inquisitive engineer on my team who

was trained for six months during the construction and testing

of the system in our facilities. He knew all the intricate details of

the automated system. He was also well versed in troubleshoot-

ing the system components. I decided to send him to Norway for

three months to oversee the installation of the system and to train

the customers team members. I discussed his mission with him.

He was very excited and elated that he was going to represent our

company by himself in such a detailed project. I told him that we

were going to have a daily telephone conference ve times a week.

I promised him that I would bring in other design specialists to

the telephone conference calls if there were any issues during

the installation. I asked him to keep an engineering notebook to

record all the daily tasks, mishaps, issues, and all important facts

regarding the system installation. I also cautioned him to carry

along a complete toolbox to be used during the system installation

and some cold weather clothing.

e rst month in Norway went well. e engineer did a great

job during the installation of our automated positioning system.

We had a telephone conference call at 8a.m. California time and

5p.m. Norway time during every working day. ere were some

minor issues such as interference with another equipment, which

was solved by removing a quarter of an inch from the side anges

of our equipment. Several bolting patterns with the oil rig oor

did not match. We had to slot our bolting holes to match theirs.

Installation was completed in a month and test runs were starting.

My engineer was freezing in Norway in the month of February,

but he was upbeat and ready to start the test runs.

e control panel of the system started to have problems during

the test runs. Watertight pressure switches were not sometimes

switching at their set points. My engineer on location tried to nd

the cause of this intermittent malfunction without any success.

I immediately collected the available brains in our plant and an

application engineer from the pressure switch manufacturer and

brainstormed the control panel problem in Norway. We provided

several suggestions to our engineer over the telephone for him

to try. Nothing seemed to work to correct this malfunction. We

tried all the re- ghting ideas for two weeks without any success.

135

case studIes In resource ManageMent

I had another option. ere was a very experienced consultant

in electro- mechanical system design. My company used his ser-

vices from time to time in the design of our control panels. I tried

to reach him by telephone and by e- mail. I learned from his fam-

ily that he was on a sailing vacation in Tahiti for a month. I asked

his family as to how I could touch base with him. Apparently,

he called his family at least twice a week when he was on land.

I asked his family to help me to touch base with him on a cru-

cial issue. I asked them to ask the consultant to call me as soon

as possible.

After two days, I received a call from the consultant from Bora

Bora in Tahiti. I explained the situation and told him that we were

in a bind. I asked him if he could cut his vacation short and y

from Tahiti to Norway and help my resident engineer solve our

control panel issue. I proposed an incentive to help him make up

his mind. I told him that I would pay him his regular hourly rate

even during his travel time and reimburse him for business class

airline fares. He agreed to my proposal and promised me that he

would be on the rst ight out of Tahiti to Europe.

After troubleshooting the control panel together with my nov-

ice engineer in a very methodical way, the consultant found the

problem that was causing our control panel to malfunction. e

power that was feeding the control panel was sometimes below

the allowable lower limit and was causing the pressure switches to

not function properly.

Being in a re-ghting mode for two weeks to troubleshoot the

control panel by telephone conversations in a remote location in

Norway with a novice engineer did not work out well. My hind-

sight told me that I should have sent my novice engineer to this

important oshore assignment in a foreign country along with an

experienced engineer as a team. In the end, my customer was not

happy because it took us three weeks to troubleshoot the control

panel malfunction. We were lucky that we were not penalized

for this delay because the new oil platform had other functional

issues. My solution to our problem was an expensive one. I was

over budget and my management was not thrilled about it.

I thanked my consultant for saving our butt by cutting his

vacation short. I showed my gratitude to him with a bonus pay-

ment. I did not forget to praise my novice engineer for performing

a very detailed and a courageous job by himself working the rst

time on an oil platform. He also received an outstanding perfor-

mance review from our customers project manager.

136

Project ManageMent case studIes

LESSONS LEARNED FROM THIS PROJECT EVENT

In a project, sometimes it takes very unusual and expen-

sive decisions to solve a nagging problem.

A novice engineer and an experienced engineer work-

ing as a team on a complicated project task can be more

ecient and more eective.

Case5.8: Engineers Sent to Japan

to Improve Manufacturing Yields

A Japanese supplier was providing ceramic magnetic recording

heads for our head stack assemblies for a U.S. disk drive manufac-

turer. Each head stack assembly was being tested for performance

and the yields were low. We formed a team of six engineers, two

from design, two from quality, and two from manufacturing, to

improve the yields of our head stack assemblies. I was heading

the yield improvement team. We investigated every process in our

plant. We tracked every suppliers component lots to nal testing.

We realized that our nal test yields were varying from 30% to

70% depending on the ceramic magnetic recording head lots we

received from Japan. ere were wide swings in performance of

ceramic performance heads from lot to lot.

I called the chief engineer at our Japanese supplier and dis-

cussed our surprising conclusion for low product yields with him.

He promised he would investigate his processes and report his

ndings to me in a week. A week passed and I did not hear any-

thing from him. I called him again to emphasize the yield issue.

He nally spilled the dire situation he was in. He told me that he

was down to one manufacturing engineer. He lost two of them

recently. He could not investigate and control all the processes for

our ceramic magnetic recording heads. I proposed to help him by

sending two of my seasoned manufacturing engineers from my

team to Japan for four weeks. I asked his company to pay for travel

expenses for my two engineers. He accepted my oer. Two of my

teams senior manufacturing engineers, one a lapping expert and

the other a grinding expert, were o to Japan.

We had a mission- dening meeting before the two engineers

left. I wanted a daily update via e- mail from them detailing their

investigation steps, their design- of- experiments, and their nd-

ings. We were also going to have a telephone conference call twice

a week on Mondays and ursdays at 5p.m. Pacic standard

time, namely, 9a.m. on Tuesdays and Fridays in Japan.

137

case studIes In resource ManageMent

My two engineers started to go over each manufacturing step of

ceramic magnetic recording heads at our Japanese supplier. Some

of the inconsistencies in their processes and in dierent shifts

were corrected. ese did not make any dierence in our over-

all yields. I asked them to conduct several design- of- experiments

involving lapping and grinding processes and especially speeds

and send me products from these experiments by specifying all

variables for a given lot. We built these special ceramic magnetic

recording head lots to nal assemblies and tested them to see the

changes in nal test yields.

e Japanese manufacturing personnel were helping my engi-

neers day and night. ey were doing up to 10 dierent experi-

ments at once. We could not nish all the designed experiments

in four weeks. We had to extend their stay in Japan another four

weeks. At the end of the sixth week, we received several special

lots with slower lapping and grinding speeds. Our nal test yields

with these slower speed lots shot up to 90%. e stresses induced

on the ceramic slider body were much lower and therefore the

stresses induced on the magnetic sensor were much reduced. I

gave my engineers and the Japanese chief engineer the exciting

good news. I asked them to send me ve more conrmation lots

with slower lapping and grinding speeds. All these special lots

too went through nal testing with ying colors. We had a very

steady 90% nal test yield.

Apparently, the Japanese manufacturing engineers increased

lapping and grinding speeds to jack up the throughput due to

increased demand from us. I emphasized to the Japanese chief

engineer not to change anything in their processes without my

approval. He agreed to it. He was very apologetic about the whole

chaos that was created by his novice engineers.

After all the 24/7 work that my manufacturing engineers per-

formed in Japan, I asked them to relax and spend a couple of days at

their leisure before heading back. e Japanese chief engineer took

them to a close by ash- spewing volcano and to some hot springs

(onsen) near the volcano. My teams two manufacturing engineers

did a great job performing a very structured design- of- experiments

at our ceramic magnetic recording head supplier. I wrote a praising

review regarding their excellent work in Japan to their supervisor

and sent a copy of my review to our human resources.

is Japanese supplier was a critical part of our product. As a

project manager, it was my responsibility to help them in any way

I could. As a result of this urgent six- week project, our products

138

Project ManageMent case studIes

nal test yields improved immensely and they were steady. Our

Japanese suppliers ceramic magnetic recording head sales doubled.

LESSONS LEARNED FROM THIS PROJECT EVENT

Degradation of crucial production parameters such as

the nal product test yield can be traced all the way to

your subcontractors processes.

You have to do all you can to help your subcontractor to

nd and correct manufacturing problems that are aect-

ing your nal product yields.

Case5.9: Listening to an Engine Assembler

I was a senior scientist on a team of ve engineers and two design-

ers. We designed from the ground up a 70 HP at 5000 RPM

rotary engine for compact cars. e design was completed in one

year and we contracted a British rm to build the engine proto-

types. We were bench testing the rst prototype engine. During

test runs from cold start, the oil pressure was always showing high

and exceeding the preset limit. Initially, we thought that there

was a design ow in some of the oil passages in the engine. We

did some investigative work, but we could not pin down where the

problem was. My teams engineers, including myself, were pulling

our hair out trying to determine the cause of this malfunction.

One of the engine assemblers, named Freddie, thought that

the oil pressure relief valve exit hole that dumps excess pressure

oil directly back into the oil sump was too small in diameter. He

showed me the relief hole and insisted from his experience with

other similar engines that it should be larger in diameter. I listened

to his constructive input and went to the project manager to inform

him about the observation from the engine assembler. I asked the

project manager if we should repeat the oil exit hole sizing calcula-

tions to see if there was an error in them that we missed.

e project manager agreed with me and asked one of our

engineers to repeat the oil pressure relief valve exit hole sizing

calculations. He asked me to be the checker for the new calcula-

tions. e oil ow velocity equation that was used initially in high

oil pressure cases was wrong and during these initial calculations

we predicted higher velocities in small diameter holes. Our new

calculations with the correct oil ow velocity equation predicted

that the required oil pressure relief valve exit hole diameter be

doubled. We changed all the required drawings and released

139

case studIes In resource ManageMent

them for the next set of engines to be built. We also modied the

existing engines. e updated engines ran with great performance

even in cold weather conditions without exceeding the preset oil

pressure limit.

I went back to Freddie and thanked him for his valuable advice

and asked him and his wife to join us for dinner at an exclusive

restaurant in the city. He was very grateful. We had a great time in

celebrating Freddies constructive input to our project.

Listening to the engine assembler saved us precious time

in nding the solution to a simple nagging malfunction in our

engines. ese types of events happen many times during the

life of a project. Listening to your customers input, to your sub-

contractors input, to the regulatory agency input, to input from

people around you from secretaries to assemblers might save your

project. Listening to all input and ltering it down to useful ones

for your project is an art in itself. As a project manager, you have

to be appreciative of all input, good or bad, and you should not

forget to reward the good ones.

LESSONS LEARNED FROM THIS PROJECT EVENT

A nagging problem can be solved easily by listening to

others.

As project managers, we have to be very open- minded

to ideas and suggestions given by others. Our easygoing

and appreciative attitude will encourage everyone around

us to sound their input for the goodness of our project.

Case5.10: Russian Federation Technical Passport Issue

Bureaucracy was a major hurdle in shipping equipment to a project

for a Russian Federation oil platform. As a part of the project, tech-

nical passports were required to ship our equipment to Russia. e

Russian Federation regulatory authorities review and approve the

equipment documents ahead of shipment. ey issue a GOST- R

certicate of conformity for customs clearance. I had to send all the

equipment drawings, specication sheets, quality and conformity

certicates, certicates of origin, and operating manuals in Russian

to the Russian authorities about three months before the shipment.

at would give them enough time for their review and for a ques-

tion and answer period and to release the certicate of conformity.

I estimated that all the documents that had to be submitted

to be around 1,000 pages. I got bids from two agencies that were

140

Project ManageMent case studIes

experts in obtaining these certicates. ese agencies do all the

translation into Russian, submit the documents, do the follow- up

and resolve all the conicts, and get the certicate in time before

shipment of our equipment. ese agencies asked $60,000 to

do the entire job. is expense was not funded in our original

bidding for the project. We had to spend this amount from our

margin. My upper management asked me to look into other ways

of obtaining the Russian Federation certicate. I researched and

found a certied Russian technical translator for $15 per page. If

we got our documents translated and submitted them ourselves,

we would increase our margin by $45,000.

I went to my management and explained to them the alternate

way of getting the certicate of conformity. We all agreed to submit

our documents to the Russian Federation regulatory authorities our-

selves. I got all the documents translated into Russian, which took

two months. I sent all the documents by FedEx three months before

the shipment to the Russian Federation regulatory authorities.

I followed up the approval process by e- mail and by telephone

with my Russian translator next to me every week. We always

received an answer from a secretary that our documents were in

the review cycle and we should get the approval any day. A month

had passed and I started to get edgy. Two months passed and

we got the same response, that the review cycle was almost com-

plete. I could not wait anymore. I had only one month to ship our

equipment according to our contract with our customer. I talked

with my customers project manager about the runaround I was

getting from the regulatory authorities in Russia. He warned me

that their response was typical. He advised me that I should have

gone with an expert agency to get the certicate of conformity.

ese agencies knew how to push the paperwork and get the cer-

ticate of conformity on time.

I immediately contacted one of the agencies I had dealt with

before. I got a new bid from them to obtain the certicate of confor-

mity in a month with all documents already in Russian. is time I

received a $40,000 price tag. I went to my upper management and

laid out the details and the risks to them. We decided not to wait

anymore. We had to go with the expert agency to obtain the certi-

cate of conformity. ese agencies had oces in Moscow and they

hand carried all the documents and followed their progress daily. If

there was a hiccup they took care of it right there. ey promised to

obtain the certicate of conformity within a month and I received

it by overnight FedEx two days before our equipment shipment.

141

case studIes In resource ManageMent

After all this hoopla, I made an extra $5,000 in our margin,

but it was not worth it. I had several sleepless nights and spent a

lot of my time following a Russian Federation regulatory author-

ity process, which I had no control over. I should have put my foot

down with my upper management and should have gone with an

expert agency from the beginning of the process.

I received the certicate of conformity for my original applica-

tion four months later by mail. Bureaucracy in a foreign govern-

ment can hurt your project in many ways. You have to go along

with the experts to solve your problems with the bureaucrats even

if it costs your project an arm and a leg.

LESSONS LEARNED FROM THIS PROJECT EVENT

Let certied people or companies handle government

bureaucracies in foreign countries.

Do not cut corners to reduce your cost when dealing with

foreign governments.

Case5.11: Natural Disaster Insurance

We were contracted to design, build, and install communication

equipment in a gas pipeline in Bangladesh. We prepared and

tested all subassemblies of the equipment in our facilities. en

we packaged them in waterproof crates and shipped them using

land/ ocean/ land routes to their destination. We had a reliable

freight forwarder who insured the goods that were being shipped

against all risks of physical loss or damage for door- to- door trans-

portation. All risks cargo insurance covered damages during

loading and unloading, all transportation, war, strikes, riots, civil

commotion, theft, and nondelivery of any portion of the ship-

ment. Our cargo insurance even covered jettisoning of containers

during the voyage in the ocean that could be encountered due to

adverse conditions.

e total cargo insurance cost for all the equipment that lled

up two 40-foot containers was over $60,000. e shipment was

scheduled to arrive at the port of Chittagong, Bangladesh in ve

weeks. At the beginning of the fth week, I received an e- mail

from our freight forwarder that the shipment had arrived at the

port of Chittagong and our containers were unloaded success-

fully. I got ready to send my engineering team to Bangladesh for

the installation process.

142

Project ManageMent case studIes

One of my engineers informed me that there was a cyclone

forming in the Bay of Bengal and it was heading north toward

Bangladesh. I immediately called our freight forwarder regarding

the status of our two containers at the port. He assured me that he

would talk to his agent in Bangladesh and get the two containers

transported inland away from the cyclone hit areas of the coast.

He also told me that our all risk insurance did not cover natural

disasters. at was very disturbing news to me. Apparently, we

had to buy separate insurance coverage for natural disasters such

as earthquakes, cyclones, ooding, and so on. To save us around

$10,000 our shipping department and our freight forwarder

decided to bypass the natural disaster insurance for my projects

equipment. I was very worried at that point. I called my manager

and the company president and explained to them the pickle we

were in. en I called my customer to warn them about the status

of their equipment shipment with the upcoming massive storm

and our lack of insurance coverage for natural disasters.

I could do nothing, but wait and pray. I was hoping that my

freight forwarders agent in Bangladesh could move our containers

inland before the cyclone hit land. I started to follow the cyclone

news on the Internet. It was a massive and powerful cyclone pack-

ing heavy rains and destructive winds. It was heading toward the

Indian and Bangladesh coastlines. Satellite images showed the

cyclones spinning tails covering a huge area. Weather forecasters

predicted the storm to make landfall the next day near the border

between India and Bangladesh.

I could not sleep that night. I followed the storm very closely.

ere was no news from our freight forwarder regarding our two

containers whereabouts. e next morning I saw on the news

that the cyclone had made landfall closer to the Indian shoreline.

Chittagong and its vicinity got hit by heavy rains and 100-mph

winds. At 8a.m., I received a call from our freight forwarder that

our two containers were still at the Chittagong port. ey could

not move them inland due to the storm. Our two containers were

under 3feet of water. Luckily, our equipment was very well pack-

aged and all weather protected. e cyclone had a large footprint,

but only its tail hit the port of Chittagong. We came very close to

losing all of our equipment.

As a project manager, I should have questioned in detail the

insurance coverage of my shipment. When I heard that we had

all risk insurance, I did not dig into further detail. at was a

mistake. My team, my management, my customer, my freight

143

case studIes In resource ManageMent

forwarder, and myself had a very scary 36 hours. I wished we had

the extra coverage for natural disasters. What we went through

was not at all worth the $10,000 saved.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to cover and ask smart

questions about every segment of our project. We cannot

leave any unturned stone that might come back and bite

us at the end.

Saving a little money in a large project is not worth the

trouble and the agony you have to go through.

Case5.12: Project Partners

Bidding for a project can get quite complicated. You have to

strengthen your companys position in a bidding war by partner-

ing with other companies in order to have a winning chance. In a

project you might partner with another company or companies for

nancial reasons, for technical reasons, for domestic content rea-

sons (in international bids), and for rules and regulations coverage

reasons. Project management can get complicated in a multicom-

pany team environment. You have to have the responsibilities of

each party well dened. You have to have a well- agreed- upon

pecking order for project management authority.

In a volume production project to build an advanced passenger

vehicle, a complex team of international companies agreed to par-

ticipate in a start- up automotive company. I performed a detailed

feasibility study for the volume production project. Design of the

vehicle was completed by the start- up company and the vehicles

manufacturing was in the prototype phase. In volume production,

the vehicles unibody frame construction was going to be man-

ufactured in Italy by a well- known automotive company. e

drivetrain was going to be supplied by a well- respected French

automotive company. e nal assembly and test of the vehicle

were going to be done in a new volume production plant in the

United States by the start- up automotive company. e project

was being nanced by a couple of high- powered venture capital

investors in the United States. It took about a year of negotia-

tions to bring all involved companies together as a team and to

sign nal contracts. e technical project partners and nancial

project partners were all on solid ground. Everyone was upbeat for

a successful project.

144

Project ManageMent case studIes

e project manager of the whole project, a good friend of

mine, formed three separate project teams, one in Italy, one in

France, and one in the United States. Every team had well- dened

project tasks, project schedules, and a team leader who reported to

him. e project manager had to travel a lot between three project

groups to coordinate and be up to date regarding every task. is

project was in the 1980s, and Internet communication was just

starting and international calling systems were not as good. You

had to be on location in order to assess the true status of a project.

e projects manager had to present cost performance analysis of

the project to nancing groups on a weekly basis. Final assem-

bly and test facilities for volume production were near completion

after a year. During that time, 60 prototypes of the advanced pas-

senger vehicle were built and tested thoroughly and successfully.

Everything for the volume production project was going as

planned. e rst vehicle was scheduled to roll out of the volume

production line in January of 1988. However, stock markets around

the world crashed all of a sudden in October of 1987. Financial

backers of the project had to drop out of the project with their losses.

Eorts to raise additional capital to get the project moving were

fruitless in that nancial turmoil. At the end of 1987, operations at

the new start- up automotive company came to a halt. e project

manager did a heck of a job for three years to bring this highly

complicated multinational project to the gates of volume produc-

tion, but his luck ran out as a result of an unforeseen nancial crisis.

In another project, I was leading a project team to design,

build, manufacture, test, and install high- pressure hydraulic cyl-

inders in a very low temperature environment. My company had

to team up with a seal manufacturer in Germany during the bid-

ding phase of the contract. e German company was responsible

for designing, manufacturing, and delivering to us special cyl-

inder seals. e German companys technical know- how was in

designing and manufacturing high- pressure seals operated in very

cold temperatures. e German company brought a good techni-

cal boost to the winning bid combination. e German company

had a well- dened responsibility, a schedule, and a project team.

ey were supposed to deliver the rst articles in six months. e

project was progressing on schedule. At the end of the fourth

month, there was a shue in the German project team without my

approval. e new team members were novices and they started

to delay their seal delivery dates. e special seals were constantly

failing very low- temperature life tests. I started to get worried.

145

case studIes In resource ManageMent

I met with my companys president and explained the alarming

situation to him. We decided to send our quality manager imme-

diately to Germany to evaluate our projects progress on-site. His

project status reports to me were not favorable at all. is private

and small German company was going through an upper man-

agement shake- up. ey had lost several of their experienced

designers. e quality managers recommendation was to drop

the German company and to nd another partner for designing

and manufacturing special seals for our hydraulic cylinders. I dis-

cussed this emergency situation with my companys president. We

decided together to cancel our seal project partnership with the

German company because of their failure to fulll our joint con-

tract commitments. We could go this route only after getting an

okay from my customers project manager. My customers project

manager agreed with my proposal to change our German part-

ner. My purchasing department and I scrambled to nd another

seal company that could design and provide us special seals in an

expedited schedule. Luckily, we found one close to our facilities

in the United States. My customers project manager and I visited

our new seal design and manufacturing partner for qualication.

e qualication visit was very successful. We signed a contract

with our new special seal design and manufacturing partner in

one week. I monitored their progress very closely. I also had one

of my project team engineers reside at the new seal company for

the duration of the whole project. When everything was said and

done, my company was late one month in delivering our hydraulic

cylinders to our customers site. However, I was very lucky to be

able to turn around the special seal crisis.

At the bidding phase of a project, all project partners look

eager and willing to win the bid. Many unforeseen issues might

surface with our project partners during the execution phase of

the project. As project managers, it is our responsibility to remedy

these project partner issues as fast as we can without damaging

the cost and schedule performance of our project.

LESSONS LEARNED FROM THIS PROJECT EVENT

In a multicompany partnership project environment,

there has to be a mutually agreed upon project manager

who is responsible for the whole project.

You have to be proactive and drop some of your project

partners in a timely fashion if they are not performing

up to par.

146

Project ManageMent case studIes

Case5.13: Cost Overrun Due to Steel Price Increase

I was heading a project to design, build, and test 20 high- load

capacity and high- pressure hydraulic cylinders for a customer in

Brazil. Each cylinder was priced at $200k. e total project rev-

enue was $4M. Each cylinders cost was broken down to distrib-

uted design costs, manufacturing costs, and testing, which was

$120k per cylinder. Material costs for each cylinder were $40k.

Packaging and shipment of the cylinders were the customers

responsibility, namely, delivery was ex- factory. So each cylinder

would have a cost of $160k with a total project cost of $3.2M,

which resulted in a project margin of 20%.

e material cost was mainly the special steel cost used in build-

ing the hydraulic cylinders. We could only use steel from the cus-

tomers qualied countries and qualied suppliers in those countries.

My purchasing agent was screening all the qualied steel manufac-

turing suppliers and dealers. Due to a large demand for steel from

China, steel prices skyrocketed during my project, which we did

not account for in our pricing. With high steel prices our material

costs were going to increase by 50% to $60k for each cylinder. is

unexpected cost increase in steel would have lowered our project

margins to 10%. I had a meeting with my team and with my upper

management to brainstorm the skyrocketing price of steel for my

project. One of the vice presidents suggested that I should discuss

this issue with our customers project manager too. Our customer

had large steel construction projects. Maybe purchasing our steel

under our customers umbrella would give us some relief in price.

After our internal meeting, I immediately sent an e- mail to our

customers project manager to set up a teleconference with him

regarding our projects steel costs. During the teleconference, I

told him that we were going to get a big hit to our project margin

with the current steel prices. We discussed several ways to solve

the high steel pricing issue at hand. He promised to look into the

matter in his company to see if they could help us in any way. ey

also purchased a lot of steel themselves for their other projects.

Our customers project manager got back to me in a week with

exciting news. He said that they just qualied a new steel ven-

dor in South Africa. ey were ready to purchase a substantial

amount of steel for themselves for another project. He discussed

our high steel price issue with his material purchasing manager.

His material purchasing manager agreed to piggyback us onto his

order in order for us to get a reasonable discount. His material

purchasing manager was leaving for South Africa in two days to

147

case studIes In resource ManageMent

nalize his steel order. I proposed that I send my purchasing agent

along with him so that we could get steel for my project at a rea-

sonable price by riding on their coattails. Our customers project

manager and their purchasing manager were very understanding

and helpful in accepting my proposal.

My purchasing agent traveled to South Africa with our cus-

tomers purchasing manager. After a couple of days of negotia-

tions, together they negotiated a good deal for us with the new

South African steel supplier. We only had to pay $8k extra for

each cylinders steel. is steel supplier was also able to provide

the steel in a timely manner for my project with the required

material certicates. I was lucky that I was able to piggyback my

projects special steel order with my customers substantial steel

purchase order. is deal was quite a success story for my project

during continually rising steel prices. It saved our projects margin

from going down to 10%. With this new South African steel deal,

our projects margin eroded down to a reasonable value of 16%.

I was elated with the help I received from our customer on this

steel deal. I sent our customers project manager and his purchas-

ing manager two bottles of ne whisky for their excellent support

in helping us to get my projects steel at a very reasonable price. I

also gave my purchasing agent a dinner gift certicate for two at

a restaurant of his choice.

I kept my upper management informed continually about the

status of the South African steel deal. ey were very happy about

the nal steel deal. I asked the president of my company to write

a thank you letter to the president of our customer while praising

the help we got from our customers project manager and from

their purchasing agent in our steel deal. Teamwork like this went a

long way in making a project a success in a win- winsituation.

LESSONS LEARNED FROM THIS PROJECT EVENT

An unexpected rise in material costs during the execution

of a project will bite into your companys prot margin.

It is a good practice to lock down material costs at the

beginning of a project without any delay before surprise

increases hit your project.

Case5.14: Actual Cost of Work Performance

As the project manager I had to keep track of the schedule per-

formance index and cost performance index for every task group.

148

Project ManageMent case studIes

I presented these two important schedule performance and cost

performance indices to upper management every two weeks or at

most every four weeks. Schedule performance indices were eas-

ier to calculate because input to work completion estimates were

determined by me and task groups. However, it was very dicult

to obtain input for cost performance indices.

I had to chase our accounting department every month in

order to be able to collect all costs charged to my projects charge

numbers. e accounting department was always late in getting

all charges collected. ey also made unthinkable mistakes. I saw

many charges from unrelated company personnel to my project.

I saw several equipment costs charged to my project by mistake

or knowingly. At the end of every scal month, dened as four

weeks, four weeks, and ve weeks, I had to get these erroneous

charges cleaned up before I could determine the actual cost of the

work performed by every task group of my project.

I expressed my concerns about delays and errors occurring in

the accounting department to my manager. My manager set up

a meeting with the chief nancial ocer. During the meeting, I

voiced my concerns with examples. I emphasized that my project

was a very dynamic one with a tight budget. I had to know the

charges made to my projects charge numbers, 14 of them, at most

within a week from the end of the scal month. I asked them to

allow me to sit down with the accounting departments personnel

at the end of every scal month to go over all the charges made

to my projects account numbers. e chief nancial ocer agreed

to my requests and promised to improve cost reporting delays and

errors.

One month passed yet the situation with cost accounting did

not improve. Two months passed and it was the same old story. I

had to get my projects cost accounting xed. I, myself, made an

appointment with the chief executive ocer of the company and

laid in front of him the details of our companys cost accounting

delays and errors. He told me that he was aware of the slow pace

of our accounting department in preparing the scal monthly cost

report. I told him that I could not fulll my project management

duties in a timely manner and take the necessary steps to correct

for cost overruns at this tempo. He promised me that he would

discuss the accounting department issues with the chief nancial

ocer immediately and they would make the necessary improve-

ments to enhance the companys cost account speed and error rate.

149

case studIes In resource ManageMent

At the end of the next scal month, the cost report came out in

two days. ere was one error in my projects cost report. I was so

happy. I sent thank you e- mails to our chief nancial ocer and

copied our chief executive ocer and my manager. I was able to

get the actual cost of work performed within two days after every

scal month. I was able to balance my under budget task groups

with over budget task groups and determine what actions to take

to improve my projects cost estimates to completion. More often

than not, my projects overran the budgeted cost of work. en I

had to present the overrun reasons to my upper management and

get their okay to dip into my projects contingency funds or dip

into the companys company margin.

ere was another major issue with the project cost account-

ing, which was the timely submission of travel expense reports.

My team members led their expense reports within a week of

their return to home base. However, some manufacturing depart-

ment engineers and some quality department engineers submitted

their trip expense reports one to six months late. I had to nudge

every one of them and their managers to get their trip expense

reports led with the accounting department in a timely fashion.

Finally, I got tired of nudging them and took the trip expense

report timely ling issue to my upper management. After a couple

of discussions with upper management, it became a requirement

in the company for everyone to submit their trip expense reports

within one week of their arrival to home base.

Monitoring schedule and cost performances of a project very

closely at regular intervals is a must for a project manager. You

have to bring your companys other departments in sync with your

projects dynamic environment. e challenge is to be able to col-

lect all schedule and cost performance data in a timely fashion

from your foreign project partners.

LESSONS LEARNED FROM THIS PROJECT EVENT

Your projects cost performance can be hampered by your

nance departments delays and errors.

A trip expense report for a project should be led and

approved within a week of completion.

Periodically always check every item charged to your project.

151

6

Case studies in

teaM ManageMent

Every team member of your project has a dierent personality and

behavior. You are a mentor, a role model, and a psychologist to all

your team members.

Stability in the lives of the project teams members helps tremen-

dously to run a project smoothly. I had to help a troubled team mem-

ber straighten out his family issues as outlined in Case6.1.

A senior scientists adverse behavior aected my teams morale and

started to hamper the progress of my project. I had to take serious

steps to bring him in line so that my project could progress smoothly.

Case6.2 outlines the steps that I had to take in order to bring har-

mony into my project team.

Errors are part of real life in engineering projects. ey can happen

in design, in a customers specications, in manufacturing, in qual-

ity control, in receiving inspections, at subcontractors, at certication

laboratories, and so on. e key is to catch them in a timely fashion.

Hopefully, the error will only cause a minor distraction to the proj-

ect. If everyone involved with the project can learn from the mistake

made, you will be making a big contribution to your company as a

project manager. Such an encounter is detailed in Case6.3.

To execute a project in a foreign country can be very challenging. It

helps a lot in the progress and success of your project if you and your

team members are immersed in the foreign countrys traditions and

language. In Case6.4, my team had to be trained on the ins and outs

of Japanese business culture and business language.

In one of my projects, a senior engineer on my team decided to take

a three- month sabbatical leave from the company right in the middle

of the project. He was a crucial member of my team. ese kinds of

unexpected situations can arise in any project. As the project manager,

152

Project ManageMent case studIes

my task was to nd a remedy to this crisis fast without hampering the

progress of my project as described in Case6.5.

Traveling to foreign countries for a job can be very strenuous. It

requires detailed preparation. Passport issues, visa issues, money

issues, security issues, language dierences, hotels, transportation,

and foreign contacts all have to be dealt with in utmost detail and

accuracy ahead of a trip. As project managers, it is our responsibility

to make sure that all the is are dotted and all the ts are crossed before

a foreign trip is made as shown in Case6.6.

Nonperforming and/ or underperforming team members are always

an issue during the life of a project. Keeping them on the team or

getting rid of them has to be weighed very carefully. Risk analysis of

your actions has to be thought out in utmost detail. e eects of an

underperforming team member can be very destructive in a dynamic

team environment. Such a situation is detailed in Case6.7.

One of the important tasks of a project manager is to attend special

ceremonies involving your team members. ese ceremonies can be

birthday parties, weddings, patent presentation banquets, technical

society presentations, and so forth. As a team leader one of your main

functions is to participate in your team members celebration events.

Such an international event is detailed in Case6.8.

A work environment should be like a second family environment

away from home. Every employee should be able to talk and express

his or her issues and concerns to their managers, upper manage-

ment, and/ or to human resources without any reservations or fears.

ese issues and concerns can be personal ones, work- related ones, or

community- related ones. As managers, our responsibility is to help

every employee as much as we can to make them feel that they are

always under our companys family umbrella as described in Case6.9.

In a project environment, during the course of events, several

unexpected sacrices can come from any one of your team members.

Sometimes these sacrices can come from people outside of your

team. As the project manager, you have to recognize and appreciate

these kinds of above and beyond duties. Such an example is detailed

in Case6.10.

I have seen many project teams go through a honeymoon period at

the beginning or at the middle of a project throughout my career. As

project managers, we have to watch for slacking signs from every team

153

case studIes In teaM ManageMent

member and take the necessary action to keep the pressure cooker at

a constant stress level. An unfortunate slacking period is detailed in

Case6.11.

When a good employee who helped you a lot in your project is leav-

ing the company, you have to provide a memorable farewell to him or

her. I managed to give a great farewell party to my senior mechanical

tool designer when expenses were very restricted in my company as

detailed in Case6.12.

As I gained experience in project management, I only made prom-

ises that I could keep to my team members. I researched thoroughly

beforehand, if I could keep my promise. When I gave a time frame

for a promise, I always accomplished it within that time frame as

depicted in Case6.13.

Several unexpected events can occur during the course of a project.

Some project managers get upset and blow their tops, but this type

of behavior does not solve anything. Negative reactions make things

worse. You have to be coolheaded, versatile, and rm to nd other

solutions fast in order to bring the dicult situation at hand under

control as shown in Case6.14.

As project managers, we have to sometimes act as psychologists.

We should not take drastic actions on a whim or with a burst of anger.

We have to consider all repercussions that an immediate action might

cause in our project as shown in Case6.15.

Specialists and/ or scientists can be very moody and demanding in

a team environment. As a project manager, you need their expertise.

You have to treat them with respect. You have to create a exible

boundary with their needs and with your projects requirements. If

you become a hard- liner with such people, your project will suer in

the end as shown in Case6.16.

A projects work atmosphere can be very dierent after a personal

vacation or after holidays. As project managers, we have to settle

down anxiety or lackadaisical behavior after such events as detailed

in Case6.17.

Maternity leave can be very disrupting to a projects progress. As

project managers, we have to work with our human resources depart-

ment in order to make the right decisions and appropriate arrange-

ments to solve the issues at hand as detailed in Case6.18.

154

Project ManageMent case studIes

As project managers, we have to encourage and empower our team

members constantly to make improvement suggestions to their tasks.

Such improvement suggestions can come from unexpected sources.

We have to praise and reward contributing suggestions to our project

as detailed in Case6.19.

Eciently run meetings are the backbone of a project. Meetings

have to be standardized and managed properly so that team members

precious time is not wasted. A team member should not be bored and

he or she should contribute constructively while present during a proj-

ect meeting. Especially in large team groups, as it was in Case6.20,

breaking up a meeting into smaller subgroups can be very eective.

Mishaps happen more often than not while preparing for critical

meetings or deadlines in a project. Overworked and overtired team

members become prone to mistakes and accidents. As project manag-

ers, we have to watch over our team members and over ourselves for

fatigue and for burnout conditions as detailed in Case6.21.

Case6.1: Getting a Senior Wafer Fabrication

Engineers Life Stabilized

e project was to set up a new 6 wafer fabrication for computer

disk drive heads into production. I had an engineer assigned to

every piece of equipment in the new wafer factory. ey were

tasked for sourcing the equipment, qualifying the equipment, and

optimizing that particular equipments process for the computer

disk drive head specications using design of experiments. e

project was fast paced with a duration of six months.

One of the senior engineers in charge of the nickel iron plating

module was starting to slack o and he was falling behind in his

tasks. He was the owner of the nickel iron plating module. He wrote

the specications for it. He sourced the manufacturer. He went

to North Carolina to accept the module. He was now performing

design of experiments to optimize the pulsed power supply, current

density, bath temperature, and agitation of the electrolyte solution

for critical nickel iron parameters.

I went to his oce and started to discuss the delays in his tasks

and asked him if he needed any help to catch up. He said he had

some family issues and he was certain that he would be able to

complete the design of experiments in time and qualify the nickel

iron plating module. A week passed. I sensed that things were

155

case studIes In teaM ManageMent

not progressing smoothly. is plating engineer was under a lot

of stress. I called him to my oce and started to have a heart- to-

heart discussion about his missed commitments. He started to

open up and explain to me his family issues. His wife left him

and they were going through a divorce. During this turmoil,

his 12- year- old son was staying with him. He had to run every

day and take him to school and back from school. He was trying

to sell his house. e poor guy was ready to ip due to extreme

stress. I asked him if I could be of any help. I told him to think

about it. I did not want to lose him at this juncture of the project

and bring in a new engineer from the cold. I asked him if we could

have lunch together that day. He said okay.

Until lunchtime I made a couple of telephone calls to human

resources and I saw my supervisor to nd out if the company

could provide him a company- owned apartment for the next six

months. I explained my senior engineers situation in condence

and how it was aecting my project. I received favorable responses

from all sources. He did not have to pay any rent and the company

apartments were very close to his sons school.

We had a heart- to- heart discussion about his family situation

during our lunch. I told him about the companys apartment oer.

He was very appreciative and accepted it. I asked him if there was

anything else I could help him with in order to stabilize his family

life. He told me that he was looking for a good divorce lawyer. I told

him that I would investigate nding a good divorce lawyer for him

through our legal department. I emphasized to him the importance

of his work for the start-up of the 6 wafer factory. I also empha-

sized to him to come to me if he ran into any other dicult hurdles.

I had to walk a ne line when I dealt with this troubled senior

engineer. I wanted to help him all I could without becoming too

friendly with him and without losing his respect for me. Getting

sucked into non- work- related issues with a team member can be

very tricky for a project manager. I had to go along with the com-

pany rules and regulations. I would not promise him something

that I could not deliver. Above all, my projects health was my

main concern.

I went to our legal department and discussed the divorce law-

yer issue with the companys head legal counselor. He called a

divorce lawyer friend of his in town and arranged a meeting with

my senior engineer. e two met and agreed on terms. e senior

engineer was very grateful to me. On top of everything, he got a

substantially reduced rate from the divorce lawyer.

156

Project ManageMent case studIes

In two days time, the senior engineer moved into the com-

panys apartment. He signed his son up for an afterschool pro-

gram so that he did not have to rush to school in the middle of

the afternoon. His performance at work improved instantly. He

put in some extra hours and nished his tasks only one week late.

As a project manager, I was very gratied that I could help

a troubled member of my team. Other options such as replac-

ing the team member in the critical segment of a project or

assigning another junior engineer to help him could have been

more risky.

Identifying risky areas in a project should be a continual task

for a project manager. After a risky situation is identied, you

should identify various paths to cure the risky situation. You

should choose the path that you as the project manager can have

the most control over. Risk management in a controlled fashion is

very crucial to a projects success.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to be good psychologists

too.

Identifying and dealing with a team members stress

level and risky condition are our number one responsi-

bility as project managers.

Helping a project team member to get on track in his or

her personal life is very gratifying.

Case6.2: A Recalcitrant Engineer on a Project Team

I was asked to develop the next generation of thin lm magnetic

heads with a team of four physicists and electrical engineers in

one year in order to keep ahead of the competition. e magnetic

head design had to be very ecient and increase the areal density

of magnetic recording at least an order of magnitude. I had a very

bright and innovative group on my team. e team was given to

me and I did not have any say in picking the team members.

We started the project on a very positive footing. After a week,

one of the prominent members of the team started spreading neg-

ative rumors about the company and he was not attending some

of our team meetings. He came to work late and left work as he

pleased. He had a Ph.D. in physics from MIT and he behaved like

a disobedient child. His behavior aected my teams morale and

started to hamper the progress of my project.

157

case studIes In teaM ManageMent

I called him to my oce and had a heart- to- heart discussion

with him about his attitude. I told him that he was a very valuable

member of my team and we depended on his magnetic design

calculations and recommendations. He told me he was what he

was and he did not like to work in a team environment. I asked

him not to spread rumors against the company and discourage

the team members and asked him to try to work with the team

members as eciently as he could. I told him I would not mind

him using exible hours at work. He agreed that he would try his

best and left our meeting with good intentions.

Another week passed, but nothing had changed. His behavior

got worse. He started to bring some of the other team members to

his oce and shut the door to have hours of discussions. I learned

that these discussions were not about our project. ey were dis-

cussing the stock market, who was going to make a bid to buy our

company, when our companys president was going to be red, when

was a layo going to happen, and so on. is physicist was a team

breaker and not a team builder. I had to take more serious steps to

bring him in line so that the project could progress smoothly.

I went to his supervisor and discussed this physicists behavior

in condence with him. His supervisor told me that this physicist

was a recalcitrant person and he did not like to be under anyones

authority, he looked down on everyone, and he thought his knowl-

edge was superior to anyone around him. I told his supervisor that

I needed this physicists contributions to my project. I told him

that I was going to control this grown up and obstinate scientist

very closely so that my team could successfully complete the project.

I had a team meeting without the recalcitrant physicist. I asked

my team members not to interact with this physicist. I told them

that I would be the only interface between him and the team. I

went over the reasons for my actions. e rest of my team mem-

bers understood the delicate situation with this physicist. After

the team meeting, I called the disobedient physicist to my oce

and explained to him that team harmony was necessary to succeed

in our project. I told him that we needed his invaluable input to

the project. I asked him to interface only through me regarding

the project and not with the team members. I also asked him to

move his oce next to mine, which luckily was not occupied at

the time. I asked him not to attend the team meetings. I cautioned

him not to have demoralizing discussions with my team members.

I told him that my actions were not to punish him, but to make

the project a successful one. He reluctantly agreed to my requests.

158

Project ManageMent case studIes

en I went to the human resources department and explained

to the head of the human resources department the diculties I

was having with this particular employee on my team. I outlined

all the actions I was taking to remedy the issue. I also emphasized

that I needed this physicists contributions for my project. She

asked me to write a review letter about him and list all the actions

I was taking to remedy the behavior of this physicist. I wrote a

detailed review letter and discussed it with the recalcitrant physi-

cist. I gave a copy to him. I also gave copies of my review letter to

his supervisor and to the human resources department.

is obstinate physicist worked under my very close supervi-

sion for the next six months and he contributed extensively to my

project. He heavily cut his demoralizing activities during these six

months. I made him work in a completely isolated environment.

Unfortunately, at the end of six months, he was let go during a

layo because of his behavior. He predicted the companys layo

timing right on the dot. He was a paragon of magnetism as a

physicist, but he was not a team player at all.

LESSONS LEARNED FROM THIS PROJECT EVENT

You have to take immediate action to deal with people

who are disrupting your project teams harmony and who

are demoralizing your project team members.

Some high- level scientists behave like a child in a team

environment. ese kinds of people need to be micro-

managed with very close supervision.

Case6.3: Error in Motor Mount Moment

of Inertia Calculations

I was heading a vehicle design group to design an all terrain vehi-

cle for a German customer. e design was completed on time

and approved by the customer. My companys manufacturing

group was starting to build 20 vehicles for beta testing. All chas-

sis were built and all the motor mounts were built. ey were in

the process of welding them together. During this juncture of the

project, one of my structural engineers walked into my oce with

a red face and told me that he made a calculation mistake during

the design of the motor mount beams. He forgot to divide the

beams moment of inertia calculation by a constant, namely by

12, and he was very sorry about it. Another structural engineer

who checked his calculations also missed this moment of inertia

159

case studIes In teaM ManageMent

calculation error. is error created unacceptable bending stress

levels in the motor mount beams during dynamic loading.

I immediately called our manufacturing manager and asked

him to put a hold on all chassis and motor mount construction. I

told my structural engineer to keep cool. I told him we all make

mistakes. e important thing was to learn from our mistakes

and not to repeat them again. I called the calculation checker to

my oce. I advised him in a similar fashion. I told both of them

that I would control the damage. I asked them to get together,

focus, and revise the motor mount calculation and come back with

relined drawings in a day. I called a team meeting to explain this

unfortunate error to all team members and to discuss what steps

we should take so that similar errors would not occur again.

e team meeting was very productive. I praised the structural

engineer for coming forward and discovering his error in the early

phase of manufacturing. e focus of the meeting was to nd a

better way to check our calculations so that they would be error-

free. We decided to double our checkpoints for all critical calcula-

tions. One of the checkers was going to be outside the project team,

namely an independent and a well- qualied checker. is new

design process would add a couple of extra days to the release of

calculation documents, but would give us more reliable results. e

manufacturing manager and the manufacturing lead for the proj-

ect were also invited to the team meeting. We discussed time and

cost damages due to the design error. All 20 motor mounts were

going to be scrapped. e total time lost in manufacturing would

be about ve days and it would cost the project an extra of $20k

to build the new motor mounts. Manufacturing processes in other

subassemblies would be able to move forward. ese schedule and

cost impacts were mild and they were recoverable.

en I called a meeting with my manager and the structural

engineers manager. I explained the unfortunate events to the two

managers. We went through my solutions. ey were both satis-

ed with my teams solutions to the error. However, the structural

engineers manager got upset with his engineers. He was a ashy

type of a person. He wanted to discipline both of them. He even

leaned toward ring them. I asked him to cool down a little bit.

I told him that we all make mistakes, but the key was to learn

from these mistakes and not to repeat them again. I asked the

structural engineers manager not to discipline his engineers. I

told him that these two engineers are very promising young ones.

ey needed grooming and needed a positive support from a

160

Project ManageMent case studIes

negative event. ey would contribute immensely to the company

projects in years to come. I told the structural engineers manager

that the structural engineer came forward to me on his own with

a red face. He was very honest and very sorry about the error he

made. We were lucky to catch the error in the early phase of man-

ufacturing. My project was going to get a minor hit, but in the end

the two structural engineers would gain a real- life experience. We

discussed the issue heatedly for an hour. e structural engineers

manager nally agreed with my recommendations and promised

not to do anything counterproductive to discourage them.

Errors are part of real life in engineering projects. ey can

happen in design, in the customers specications, in manufactur-

ing, in quality control, in receiving inspection, at subcontractors,

at certication laboratories, and so on. e key is to catch them

before the project is completed. Hopefully, the error would cause

a minor distraction to the project. If everyone involved with the

project could learn from the mistake made, you could make a big

contribution to your company as a project manager. I have heard

of several major errors made during a project too, such as in a

space project when the payload of an unmanned space probe was

calculated in pounds instead of kilograms.

LESSONS LEARNED FROM THIS PROJECT EVENT

Errors are more likely to occur during the execution of

a project.

As project managers, we have to be coolheaded and make

sure that our team learns from a mistake made in order

not to repeat it again.

As project managers, we have to correct errors in a

timely fashion.

As project managers, we have to gather our project team

in order to explain what the error was and how we are

going to take care of it.

Case6.4: Training in the Japanese Language

My company, a customized computer component designer and

manufacturer, planned to increase our market share in Japan. I

was given the engineering responsibility for guiding our design

and application engineers to go periodically to Japan to visit our

potential customers. We had to present our future products and

convince our potential customers as to how advanced our products

161

case studIes In teaM ManageMent

were and how advanced and controlled our manufacturing pro-

cesses were.

I went to Japan several times with my design and application

engineers. We all were struggling to get to know the Japanese

culture and their workplace ethics, such as how to greet people

from your customers end, how to exchange business cards, how

to exchange small gifts, how to behave in a meeting, how to make

small talk, how to behave at lunches and dinners, and so on. When

I returned to the United States from my second visit to Japan, I

decided that we should be trained in the Japanese business culture

and language. I requested a meeting with my companys president

regarding the necessary training, if we wanted to succeed in busi-

ness in Japan.

My company president was very receptive to my training idea in

the Japanese business culture and language. He further proposed

that this training should be a requirement for all of our employees

who dealt with Japan. He asked me to arrange it with our human

resources department. Our human resources department found a

perfect trainer from the University of California. He was Japanese

and he was studying for his Ph.D. degree in psychology. He came

to our company every Tuesday for a year at lunchtime and trained

us on the ins and outs of Japanese business culture and business

language. He taught us important Japanese phrases that we could

use during our encounters with our Japanese customers. He gave

us recorded tapes lled with Japanese phrases so that we could

practice the pronunciations at our leisure. Since Japanese is a pho-

netic language, we learned pronunciation of phrases with ease.

Every one of my engineers who dealt with Japan, all of our

sales personnel, purchasing personnel, and even executives who

dealt with Japan took this one- year training course. Brown paper

bag lunches were provided by the company. ere were 26 train-

ees in the class. We had written and oral examinations once a

month. Fifteen of us passed the course with ying colors includ-

ing all of my engineers who dealt with Japan. Ten of us unked

the course and one dropped out because of health reasons.

e course taught us a lot of small talk phrases and greeting

phrases in Japanese. We learned greeting phrases such as pleased

to meet you (hajimemashite), good morning (ohayo gozaimasu),

and thank you very much (domo arigato gozaimasu). We learned

the telephone hello response, which was moshi moshi. At the end

of a long meeting in Japan, it was customary to write down action

items on the board with the names of owners and due dates. After

162

Project ManageMent case studIes

everyone agreed on the action items list, the scriber of meeting

minutes sent the action items list to everyone involved by e- mail.

Once, at the end of a 12-hour meeting, I started the action items list

by writing action items in Japanese Kanji characters on the board.

All of our Japanese colleagues almost dropped out of their chairs.

ey had a good laugh at the end of a long and strenuous meeting.

We learned how to sit in pecking order around a conference

table. As guests, our team always sat on the side of the table that

was away from the conference room entrance door. We learned

when to talk during a meeting. e highest-ranking member of

our team always answered their questions. If that ranking member

needed help from other members of his team, he mentioned that so

and so would be responding to their particular question. Dinners

were less formal, but again high- ranking members of both teams

sat at the ends of the dinner table. A 12-hour meeting from 9a.m.

to 9p.m. and afterward a 3-hour business dinner until midnight

was a normal day in Japan.

e one- year business culture training course for Japan helped

my company to gain ground in their marketplace. After two years,

we saw a 10-fold sales increase for our products in Japan. e

president of my company thanked me for suggesting the Japanese

business culture classes for our people. Also, everyone who took

the course was very appreciative for gaining such an eye- opening

experience into Japanese culture and language.

LESSONS LEARNED FROM THIS PROJECT EVENT

Every member of your team dealing with a foreign coun-

try has to know that foreign countrys history, culture,

and workplace ethics.

Knowing the business language of a foreign country that

you are dealing with goes a long way in negotiations and

in gaining mutual respect among players.

Case6.5: A Project Engineer Left the Company

under Adverse Conditions

When I started a project with a team, I made sure that I had all

the information about each team members vacation plans, wed-

ding and honeymoon plans, and other time- o plans. I put every

team members personal time- o plan into the project schedule

and I made sure that there were no conicts with project tasks and

deliverables.

163

case studIes In teaM ManageMent

In one of my projects, a senior engineer on my team decided to

take a three- month sabbatical leave from the company right in the

middle of the project. He was a crucial member of my team. He

was doing dynamic stress analysis for the product we were design-

ing. He asked me to have a meeting together with his manager.

During the meeting, he explained that he was an avid cyclist. He

was invited to train with a cycling team and to enter an interna-

tional race with this cycling team. He requested a three- month

sabbatical leave starting in two weeks. is was quite a shock to

me. I told them that it was not possible for him to leave my project

at that critical juncture. ere was no one else in the company

who could step in and take over his tasks. He insisted that he

had to take three months o from work, he had already made a

commitment to his cycling team, and no one could stop him. I

was upset with his irresponsible behavior. I told him that his rst

responsibility should have been to the project which he was an

important part of. He should have rst consulted with us before

making a commitment to his cycling team. He should have told

us his sabbatical leave intentions four months ago when the proj-

ect started. He understood that he was not going to get anywhere

with me. So he said to his manager that he wanted to give his

two- week resignation notice and leave the company. He immedi-

ately left his managers oce without saying goodbye.

His manager was very upset too with his engineers childish

and obstinate behavior. He called the human resources depart-

ment in front of me and explained to them the unfortunate situa-

tion. e human resources director immediately went over to the

senior engineers oce to discuss if there was a way out of this

quagmire. She reported to the senior engineers manager and to

me that there was no solution to the senior engineers adamant

request. ey decided to walk him out the door at the end of the

day without any delay. I was able to salvage some of the modeling

and test runs he had done for my project before he left for good.

I had to scramble to nd a replacement for my teams dynamic

stress analyzer. I had a design review coming up in two months

with the customer and my team had to nish all the pertinent

calculations and designs before the phase 1 review meeting. To

nd a replacement engineer with a similar skill set would have

taken at least two to three months. A novice engineer right out

of college would not be able to help me. I needed an experienced

mechanical engineer in stress analysis. Even if we had to steal one

from another company, it would have been awhile to get him or

164

Project ManageMent case studIes

her to be productive on my team. e only solution was to go out

and nd a consulting rm in dynamic stress analysis and bring

them on board for my project.

I went to a couple of prominent stress analysis companies in

the United States and interviewed them for my project. ey were

expensive. I did not have any contingency funds in my budget to

cover these unexpected extra costs. I started to look at the possi-

bilities outside the United States. I found a stress analysis company

in India and one in the United Kingdom. I interviewed them by

teleconferencing. I also checked their references. I made sure that

they were using the same version of the stress analysis software

as we used in house. e stress analysis company in the United

Kingdom had the right expertise to help my project. eir price

was in the middle between the U.S. and Indian companies. I went

to my manager and discussed my search results with him and I

told him that I was going to sign a contract with the UK subcon-

tractor to complete my projects dynamic stress analysis require-

ments. He was pleased that I was able to nd a potential candidate

in a week. He assured me that the company would absorb the

extra cost of the UK subcontractor in the project margin. My pur-

chasing department and I completed the subcontract agreement

with the UK subcontractor in three days. ey started to work on

my team two weeks after the senior engineers departure.

I did all the communication by teleconferencing with the UK

subcontractor. ey came up to speed fast. ey also worked 60 to

70 hours per week without charging me overtime. I was able to get

all the required calculations and designs completed in two months

time before the phase 1 review. I did not inform my customer

about this crisis we had because this crisis was totally an internal

issue and it did not aect the progress of the project. I resolved

this crisis without disturbing my customers project manager.

ese kinds of unexpected situations can arise in any project.

As the project manager, my task was to nd a remedy to this crisis

fast without hampering the progress of my project.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to make sure that at the

beginning of a project, we have all the information

about each team members vacation plans, wedding

and honeymoon plans, and other time- o plans on our

project schedule.

165

case studIes In teaM ManageMent

A team members work plan can change suddenly, which

can aect your projects progress adversely.

Replacing a specialized and experienced engineer is very

dicult at a moments notice.

Case6.6: On- Site Equipment Training

One of the requirements of building and installing a hydraulic

mover on an oil platform project was to train the customers person-

nel on-site. As the project manager of the project, I decided to send

a senior engineer for this training. e training was in the North

East region of Russia and it was for two weeks in April. April was

supposed to be the beginning of spring weather in that region. My

senior engineer prepared an extensive MS PowerPoint presentation

for the training. He got his laptop computer and his thermal under-

wear and left for this cold region of Russia in early April.

He was to connect with our companys liaison in Vladivostok

and then travel together to the oil platform site. My engineer did

not speak a word of Russian, but our companys liaison was going

to help translate his training presentations. e training was sup-

posed to be done with two groups of 10 personnel who did not

speak or understand a word of English. All the meeting dates and

locations in Vladivostok with the company liaison were arranged

and conrmed by Internet correspondence. My engineer arrived

at the airport. During passport control the agent asked him why

he was entering Russia. My engineer honestly said that he would

be training 20 Russian workers on an oil platform. e agent

emphasized that my engineer did not have the proper visa to enter

Russia for training purposes. On top of that, his passport expira-

tion date was within six months of his exit date. His passport

expiration date should have been six months beyond his exit date

from Russia. My engineer started to plead that he was there for

only two weeks to help the Russian workers get trained on crucial

equipment at an oil platform. e passport control agent took my

engineer to a small cubicle with a glass enclosure and called his

supervisor who spoke a little English. My engineer pleaded his

case to the supervisor. ey together tried to call our companys

liaison in town, who was not to be found at work or home. e

supervisor threatened to send him out of the country with the

next international ight, asked him to stay put, and left the cubi-

cle. My engineer waited in the cubicle for three hours and nally

the supervisor showed up again with smiles. He told him that 166

Project ManageMent case studIes

he discussed his situation with authorities in Moscow and they

decided that he could enter Russia for only two weeks as a tour-

ist. Finally, my engineer said, Let me be a tourist for two weeks

in your country. en they shook hands and his passport was

stamped with the tourist entry date.

My engineer took a taxi downtown to our company liaisons

oce. He found a secretary there who did not speak any English.

ey were able to communicate with hand motions and by writ-

ing. Finally, my engineer understood that our companys liaison

was out of the country in South Korea for a two- day trip. Our

companys liaison never informed us about the change in his plans.

My engineer decided to stay in Vladivostok for two days and wait

for the company liaisons return. He checked into a boutique hotel

close to the company liaisons oce and called me to detail all the

hurdles that he crossed when he arrived in Russia. I agreed with

him that he should wait for two days for the companys liaison

before traveling to the training site because of the language barri-

ers. I told him to hang in there and told him that I would inform

our customer about the two- day delay in starting the training.

My engineer almost froze to death at the boutique hotel where

he was staying. Apparently, the hotel personnel turned o the heat

at night from 9p.m. to 7a.m. to save on fuel costs. e poor guy

had to buy extra blankets to keep warm at night. He started to

check out after two days at this freezing hotel, but his credit card

bounced because his credit account was maxed out. He did not have

enough cash on him to pay the hotel. He called the companys liai-

son oce and nally he was able to touch base with the companys

Russian liaison. e companys liaison came to the hotel and paid

my engineers hotel bill. My companys liaison was not even sorry

that he was two days late to his appointment with my engineer.

Together they traveled by bus to a village that was 20miles away

from the oil platform. en they took our customers shuttle boat

to the platform. ey stayed on the platform for 10days because

my engineers visa expired two days after the end of training. He

had to condense his training into two ve- day sessions. He could

not use his laptop computer on the platform because his computer

battery died. He could not charge his computers batteries since

he did not have the right adapter to the oil platform outlets. He

transferred his MS PowerPoint training le to the company liai-

sons laptop computer and used his computer during the training

sessions. It was so cold, 20C, in North East Russia in April that

my engineer had to sleep wearing his sweaters, pants, and alpaca

167

case studIes In teaM ManageMent

socks at night. He was lucky that he did not get sick during those

10 training days. Overall the training went well. He exited Russia

without any issues and made it safely back home.

I had a long meeting with him when he got back. I told him

that it was my fault not to warn him about the validity of his pass-

port duration. It was also my fault that I did not advise him on the

type of visa that he should get for training purposes. He should

have gotten a business visa. We discussed his credit card balance

issue. He accepted that it was his fault not to straighten out his

balance before he left for his trip. I went to my upper management

and laid out the details of my engineers troubles in Russia and

made sure that my company cut ties with our liaison there.

Traveling to foreign countries for a job can be very strenuous. It

requires detailed preparation. Passport issues, visa issues, money

issues, security issues, language dierences, hotels, transporta-

tion, and foreign contacts all have to be dealt with in utmost detail

and accuracy ahead of a trip.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to be extra sure that people

working for us in foreign countries are dependable.

Before we send our team members oshore, we have to

verify the validity of their travel documents.

Case6.7: Getting Rid of a Lackadaisical Team Member

I was heading ve separate groups of engineers in a wafer fabrica-

tion project. Each group had its own manager. One of the engi-

neering groups was responsible for quality control of the incoming

materials and outgoing product. ere were visual inspection corre-

lation issues regarding the outgoing wafers with our South Korean

plant. My quality engineering groups manager and I decided to

send one of the seasoned quality engineers to South Korea to train

the South Korean engineers and inspectors per our inspection cri-

teria. We wanted to eliminate our dierences in visual inspection.

My quality engineering groups manager explained in detail to

our seasoned quality engineer what his responsibilities would be

in South Korea. He had two weeks to train the South Koreans

and then return to his home base. He made his trip and trained

the South Koreans and got back. He gave me and my quality

groups manager a brieng in my oce about his accomplish-

ments in South Korea. To our surprise, he only trained the South

168

Project ManageMent case studIes

Koreans on one inspection parameter, which was the highest cor-

relation discrepancy on the Pareto chart. He did not deal with any

of the other inspection parameters. He made his trip and spent

thousands of dollars to improve our inspection correlation only

in one parameter. He overlooked all other 15 parameters which

were on his checklist. I asked him why he neglected all the other

inspection parameters. He responded in a spiritless manner that

he had time to x only one parameter. I asked him why he did

not call his manager to discuss an extension of his stay so that he

could complete his tasks fully. He said in a lackadaisical way that

he felt that he completed his mission in South Korea. I politely

asked the seasoned quality engineer to leave my oce and com-

plete his trip report.

I closed the door to my oce and started to discuss the per-

formance status of the seasoned quality engineer with my quality

groups manager. e seasoned quality engineer had been with our

company for 15years and his performance went downhill every

year. He was experienced, but he was denitely lazy. My quality

groups manager did not document instances of his poor perfor-

mance. His annual performance reviews were mediocre. I told

my quality groups manager that this seasoned engineer would be

a listless mentor for our young and dynamic engineers. I asked

him if there was a way to revive the spark in work habits of the

seasoned quality engineer. My quality groups manager told me

he discussed the mediocre performance with the seasoned qual-

ity engineer several times during his annual performance reviews

and told him that his performance was not good enough for his

advancement in the company. e seasoned quality engineer told

my manager that he is content with his job level and that he did

not care about advancement. I told my quality groups manager

that we should get rid of him as soon as we could. My quality

groups manager agreed with me.

I immediately called our human resources director and asked him

to come to my oce. e three of us discussed the seasoned quality

engineers poor performance, his spiritless behavior, and his termi-

nation steps. Our human resources director told us that our com-

pany had an at- will employment policy and that we could terminate

a nonperforming employee at any time without waiting for a layo.

He also cautioned us that my quality groups manager should docu-

ment the seasoned quality engineers poor performance and spiritless

behavior during the South Korean trip and discuss the performance

document with the employee. is performance document and his

169

case studIes In teaM ManageMent

annual performance reviews provided legitimacy to his termination

and prevented any lawsuits that his termination was discriminatory.

My quality groups manager wrote a performance document for

the seasoned quality engineer. Our human resources director and

I reviewed the document. After some minor changes, my qual-

ity groups manager and our human resources director, together,

went over the performance document with the seasoned quality

engineer. I heard that even during his performance review, the

seasoned quality engineer was spiritless. He accepted all poor per-

formance claims and signed the performance review document.

In the late afternoon, our human resources director walked the

seasoned quality engineer out the door of our company.

We went through all that hoopla in order to get rid of an

underperforming seasoned engineer. My company had a layo

two weeks later. We could have gotten rid of him easily during

the layo process.

Nonperforming and/ or underperforming team members are

always an issue during the life of a project. Keeping them on the

team or getting rid of them has to be weighed very carefully. Risk

analysis of your actions has to be thought out in utmost detail. e

eects of an underperforming team member can be very destruc-

tive in a dynamic team environment.

LESSONS LEARNED FROM THIS PROJECT EVENT

It is always dicult to spark a re under lazy and under-

performing personnel.

You have to coordinate with your human resources

department and go through the required legal process

step by step if you want to terminate personnel.

It is much easier to clean up underperforming personnel

during an ocial company layo.

Case6.8: A Japanese Wedding

One of the important tasks of a project manager is to attend special

ceremonies involving your team members. ese ceremonies can be

birthday parties, weddings, patent presentation banquets, technical

society presentations, and so on. As a team leader, one of your main

functions is to participate in your team members celebration events.

One of the most memorable events in my project management

career was to attend a Japanese wedding for one of my Japanese

team members. He asked me to attend his wedding ceremony as

170

Project ManageMent case studIes

a guest of honor in Tokyo and he also asked me to give a speech

during the reception. His wedding ceremony date coincided with

my semiannual trip to Japan to check out the progress of my proj-

ect team there. I accepted his kind oer with excitement. is was

my rst experience in a Japanese wedding ceremony and recep-

tion. I was going to be the guest of honor representing our team

and our company and I was going to give a speech.

I had to research how to prepare for this honor. I had to learn

what to wear, what kind of gift to get for the couple, and what

to say during my speech. He also invited four colleagues from

our Japanese team and one colleague from our U.S. team to his

wedding ceremony and reception. I learned that the wedding cer-

emony and reception was going to be a nonreligious one taking

place in a banquet room at a very nice hotel in Tokyo. e recep-

tion party afterward was going to be in the same banquet room

and all my teams members and I were going to be seated at the

same table. I learned that we were required to wear tuxedos with

black ties. I decided to stay at the same hotel where the wedding

ceremony and reception were. I arranged for a tuxedo rental place

through the hotels concierge. e tuxedo rental places tailor came

to the hotel two days before the event and tted me with a nice

tuxedo. I investigated what the new couples needs were so that I

could get a wedding gift for them. ere was no registry process for

wedding gifts like we have in the United States. I learned from his

colleagues that a at-screen TV might be a good gift for their new

home. I went to Tokyos electronic stores district and bought a nice

42 at-screen Sony TV for them and sent it to their new home

with a congratulatory card from me, from our team members, and

from our company. Later, I discussed the wedding gift cost issue

with human resources. I was able to charge the wedding gift cost to

a human resources overhead account instead of my project.

e last thing I had to do was to prepare my speech during the

reception. I was allocated ve minutes for my speech. I was going

to be the last one to give a speech. I learned that the wedding

ceremony and reception followed a strict order of events and time

allocated for each event was xed down to the second. e entire

reception was going to take exactly two hours and ten minutes

with all the speeches, cake cutting, newlyweds rst dance as hus-

band and wife, and so on. I asked one of the engineers from our

team in Japan to help me to include several Japanese phrases into

my speech. My closing statement was also in Japanese. Anata wa

issho ni, otto to tsuma to shite, naganen, onaji makura no ue ni kenko

171

case studIes In teaM ManageMent

to kofuku ni kite taisetsu ni ari. In English it went something like

May you together, as husband and wife, cherish many years to

come in health and happiness on the same pillow. I reviewed my

speech several times and read it to the engineer who helped me

with the Japanese phrases. He said that my Japanese pronuncia-

tion was close to perfect. I was ready for the big event, which

was on a Saturday afternoon.

e wedding ceremony and the reception went like clockwork.

e bride wore a gorgeous kimono and she had heavy makeup,

a wig, and a head covering. e groom wore a standard tuxedo.

I gave my ve- minute speech very uently. At the end of my

speech, I asked everyone to raise their glasses and toast kampai

for the new couple. en the bride went to a changing room to

change from her kimono to a Western-style dress. Every guest

started to relax, eat, and drink. After dinner, the new couple cut

their colossal wedding cake and then they had their rst dance as

a couple to rock and roll music. Toward the end of the reception,

the newly wed couple went around to every table and gave every

attendee a gift for sharing their important event.

I attended similar events in Malaysia, South Korea, and in

Germany. Attending these special events takes a lot of thought

and preparation because you are representing your team and

your company.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to give lots of thought and

attention to our team members special events.

Especially if you are attending a special event in a for-

eign country, you have to learn all the dos and donts for

that event.

Case6.9: An Engineer Wants to Return to Her Old Job

I had an interesting employee rehire case during my career. I had

a quality engineer working on my project team and reporting

to the quality engineering department manager. She was a very

dedicated and a thorough engineer. She was commuting between

her home and work 120miles every workday. We always chatted

about her commute at the beginning of our weekly meetings. We

talked about speed traps, getting trac violation tickets, trac

jams, what are the best hours to drive on the freeway, and so on. I

had a good rapport with her. She did not mind the commute and

172

Project ManageMent case studIes

I thought she enjoyed it. I valued her contributions to my team.

One day I got a call from her manager informing me that she gave

her notice that she was leaving our company in two weeks.

I was surprised at her departure announcement. I went to her

oce and expressed my disillusionment. She told me that she was

sorry to leave my team. She really enjoyed working on my team.

She said that she found a great job very close to her home at a

start-up engineering company. Her new job was a perfect t for

her and she would miss my team and also the daily commuting.

I had to scramble to nd a replacement for her in the company

to join my team. I nally got a novice engineer to replace her. He

needed a lot of monitoring and hand-holding. She and my novice

engineer were able to interface for about a week so that she could

transfer her tasks to him. I also asked her to leave all her engi-

neering books and e- mail les with me regarding my project. Her

manager and I gave her a great farewell luncheon. All of my team

members attended her luncheon.

After her departure from my company, I still kept in touch

with her. We e- mailed each other at least once a month asking

how things were going. About four months passed and I received

a telephone call from her. She told me that her new job was not

what she hoped for. She wanted to quit her job and rejoin my

company and especially my project team. I was very surprised to

hear her dismay at her new job. Apparently, there was no organi-

zational structure at the new start-up company. She had to take

care of everything on her own. Working hours were very long.

She was working on average 12 hours a day. Her boss was enforc-

ing unreasonable deadlines on her. All they did was to rush- rush

to get a prototype out to their customer so that they could guaran-

tee their next phase of funding. She wanted to return to our more

structured and employee- valued environment. I told her that our

company had a no- rehire policy, but I promised her that I was

going to try my best to get her back.

e next day, I set up a meeting with her old manager and the

human resources director. I explained to them in detail the call I

had from her. I expressed my favorable views about rehiring her.

After an hour of discussion, we came to a just solution to be able

to bring her back to our company. She was going to join my team

as a consulting quality engineer. e novice engineer would move

back to the quality department. She would contribute to my team

for the rest of my project, which had another year and a half to go.

After a year and a half, the quality department manager would

173

case studIes In teaM ManageMent

reinstate her as a senior quality engineer into his group. is way

we were not going to break the no- rehire rule of our company.

I called her immediately after our meeting and told her our

solution for rehiring her. She was ecstatic that she was coming

back to work for my company and very grateful for my help. She

accepted our proposal to work as a consultant for a year and a half

and join the quality group full time afterward. I told her that she

would get a formal call in the next day or two from the quality

department manager and the human resources director to nalize

the details of her return.

ree weeks after her pleading phone call to me, she started to

work for me. Her work ethic and contributions to my team were

of the highest standard. She was reinstated into the quality group

after 18months on a full- time basis as promised. I thought the

company gained an excellent employee by taking her back. We

did not break the no- rehire rule of our company, but we had to

bend it a little.

A work environment should be like a second family environ-

ment away from home. Every employee should be able to talk and

express his or her issues and concerns to their managers, upper

management, and/ or to human resources without any reserva-

tions or fears. ese issues and concerns can be personal ones,

work- related ones, or community- related ones. As managers, our

responsibility is to help every employee all we can to make them

feel that they are always under our companys family umbrella.

LESSONS LEARNED FROM THIS PROJECT EVENT

After leaving your job at will from a company, it will be

very unlikely for you to go back to your old job.

Job hopping is an unwritten taboo between competing

high technology companies.

As project managers, we have to help a good person in

our team all that we can when that person makes a per-

sonal mistake.

Case6.10: A Deserving Vacation

I had a long- term project to ramp up volume production for a

communication chip in Malaysia. I had a good team of engineers

in the United States supporting our eorts in Malaysia. I was

sending them back and forth from the United States to Malaysia.

We were training the Malaysian engineers. ey were taking over

174

Project ManageMent case studIes

full responsibility of their assignments after about six months of

training. One of the areas where I was having my doubts was the

wafer testing in the clean room. ere were three young, novice

electrical engineers trying to learn and take over all the testing

functions such as operator training, tester maintenance, tester

upgrading, and tester software development.

I had to send one of my senior test engineers to Malaysia the

beginning of November. I assured him that he would only stay there

for three weeks and he would be back home by anksgiving. He

was a strong family man. He had a wife and a 12- year- old son. We

put together a detailed three- week agenda for him. We discussed

and agreed on all agenda items with the Malaysian engineers.

e senior test engineers progress was going smoothly during

the rst week of his mission in Malaysia. However, when he saw

the reality of the testing environment in Malaysia, he started to

add more items to his to-do list that required extensive training.

e Malaysian engineers were struggling in the software develop-

ment phase of the testers. During our daily telephone discussions,

I asked him if he could stay another three weeks to complete his

extended tasks and skip anksgiving at home. He agreed to my

proposal. I thanked him for his dedication and I told him that I

would strongly emphasize his commitment to our company dur-

ing his annual review.

Another two weeks passed and Christmas was coming, but my

senior test engineers to-do list was growing instead of shrinking.

We again discussed what to do about his stay there. He missed

his family and he wanted to return home. I did not have anyone

else on my team and not even in the whole company with similar

extensive experience to send to Malaysia to relieve him. I had to

ask him to extend his stay until his mission was complete. I made

him a proposal for his extended stay. I told him if he extended his

stay until the end of January and completed his mission, I would

treat his wife and his son to a vacation in a place of his choice in

Southeast Asia. He was very appreciative of my vacation proposal.

He said that he would discuss my all paid vacation proposal with

his wife.

e next day during our telephone call, he informed me that

he would take my vacation proposal and spend the rst week in

February on the island of Langkawi at the northwest coast of pen-

insular Malaysia. Finally, they would get together as a family to

relax on a tropical island after three months of separation. He

and his wife enjoyed the marine life and beaches. His wife was

175

case studIes In teaM ManageMent

anxious to absorb some of the Malaysian culture. ey were also

able to take a week o for his son from his schooling. ey chose

the Langkawi Island as their vacation spot.

My senior test engineer stayed in the Malaysian plant for three

months instead of three weeks as originally planned and he com-

pleted his mission with ying colors. He missed anksgiving,

Christmas, and the New Year holidays at his home. My all

expenses paid one- week vacation proposal for him hit the spot.

at was his familys rst trip to Southeast Asia. ey had a

great time on Langkawi Island. My gesture cost my project about

$4,000, but every penny spent was worth it. He sacriced his

family and his holidays and completed his tasks in Malaysia with

exceptional professionalism.

In a project environment, during the course of events, these

kinds of unexpected sacrices could come from any one of your

team members. Sometimes these sacrices could come from peo-

ple outside of your team. As the project manager, you have to

recognize and appreciate these kinds of above and beyond duties.

A cash bonus, a gift certicate to a restaurant, a couple of tickets

to a sporting event, even a contribution to his or her choice of a

nonprot organization can go a long way.

LESSONS LEARNED FROM THIS PROJECT EVENT

If a team member has to extend his or her stay in a for-

eign country for unforeseen reasons to help your project,

you should recognize and reward his or her sacrices

accordingly.

Being away from family for a long time in a foreign

country can negatively aect your team members overall

performance.

Case6.11: Honeymoon Period

I was assigned to lead an oshore oil rig equipment design, build,

test, and installation project. e project was to last one year from

the start of design to nal installation and acceptance on-site in

the North Sea. I had a team of eight design and manufacturing

engineers. Our customer was in England. I had a two- week vaca-

tion preplanned after the third week into the project. I left the

project team in the hands of a senior engineer and left for my fam-

ily vacation. I had a heart- to- heart discussion with my replace-

ment before I left for him to check on the engineers daily and to 176

Project ManageMent case studIes

take care of their needs so that the schedule would not slip. We

had on the contract a 5% of total cost penalty for each week of late

acceptance on-site. Everyone on my team was very well aware of

our tight schedule and of the late acceptance penalty. No one had

any slack time for his or her assigned tasks.

I came back after two weeks from my vacation and got a brief-

ing from my replacement project manager regarding the status of

all current and completed tasks. I saw that we were behind about

a week to two weeks in several tasks. I went around and discussed

task- delaying reasons and the issues in detail with every engineer

on my team. I saw a relaxed atmosphere in the whole team. ey

all were behaving like they were on a honeymoon. It was sum-

mertime and excessive heat, beaches, surng, sailing, and outdoor

barbecues were giving them all a cozy feeling. My replacement

project manager did not do a good job of monitoring and putting

adequate pressure on the team members. ey all said to me we

would catch up eventually and not to worry. I heard the emer-

gency bells ringing in my head. I went to my oce to evaluate the

whole project task by task and to decide on my course of action.

e next day I called an emergency team meeting. During the

meeting, I went over every task with my team. I showed them on the

schedule that with the present pace we would be at least one week

and at most three weeks late for the acceptance of on-site comple-

tion. I emphasized that the progress we had made was not acceptable

to our customer nor to our company. I asked everyone for his or her

input as to how to catch up and not delay the project by even one day.

ere were some great suggestions from the team. I thought

the whole team woke up from a summer honeymoon dream.

ere were six critical tasks that fell behind. Six engineers that

fell behind oered to work some extra hours to catch up during

the next two weeks. At the same time, other engineers and I were

going to give them an extra hand in several minor tasks. I was

going to meet with every engineer daily for 15 minutes to discuss

the condition of his or her tasks.

e stress levels on the team members were high for the next

four weeks. We nally caught up to the critical task on the sched-

ule, which was the internal design review meeting. At the begin-

ning of the internal design review meeting, I praised all my team

members for giving extra eort in order to catch up to the sched-

ule. I invited them to a team beach barbecue with their families

on Friday afternoon. ey all accepted my invitation. We all had

177

case studIes In teaM ManageMent

a great time at the beach after roller coaster stress levels at work

for the last three months.

During the course of a project, stress levels go up and down for

every team member. A good project manager has to keep these

stress levels as normal as possible without burning out his or her

people. It is normal for the stress levels to go up before a criti-

cal design review meeting, before a regulatory agency inspection,

after an unexpected malfunction of your product, before a nal

product acceptance event, and so on. However, as the project

manager, your important task is to smooth out these stress levels

during the course of a project.

I have seen many project teams go through a honeymoon

period at the beginning or at the middle of a project. You have to

watch for the slacking signs from every team member and take the

necessary action to keep the pressure cooker at a constant stress

level. It is also a good idea for the project manager not to go on a

vacation during the course of a project that has no slack time on

its schedule and that has performance penalties in its contract.

LESSONS LEARNED FROM THIS PROJECT EVENT

A project managers replacement during his or her absence

from a project can have adverse eects on team members.

It is always dicult to shake o a honeymoon periods

relaxed atmosphere in a team environment.

As project managers, we might have to delay our vaca-

tions to after the completion of a project.

Case6.12: Farewell Luncheon

e computer company that I worked for had a chief operating

ocer whose top priority was to generate a favorable balance sheet

for Wall Street every quarter. When we could not meet our ship-

ment forecasts, he used to ship products that were in our inventory

out the door on the last day of the quarter and receive them back

as warranty return the next day. If the sales forecast for a par-

ticular quarter was down, he used to monitor all travel and extra

expenses such as luncheons and in- house birthday parties, and so

on. He tracked every penny that was spent.

During tight expenditure periods, we had to get the chief

nancial ocers approval before going on a trip or before taking

someone out to lunch or dinner at company expense. Airplane

travel was to be only in economy class. We had strict per diem

178

Project ManageMent case studIes

expense limits depending upon the place we were traveling to.

We could not take our customers or colleagues to lunch or din-

ner without prior approval. Controlling expenses and austerity

policies were good for prot and loss management, but the chief

operating ocer should have given company managers reasonable

leeway in managing their budgets.

I had a senior mechanical tool designer on my project team. He

was moving to his home state to be close to his aging parents after

15years of service to our company. He participated in several of

my projects during his last 10years with his highly professional

work ethics. My team and I wanted to give him an unforgettable

farewell party. However, we were right in the middle of a nan-

cial crunch. I had to get every expense preapproved. My team

and I decided to throw his farewell party ourselves without going

through the expense preapproval process.

I met with each of my team members and asked for their sug-

gestions. First, we decided to give a morning break chocolate cake

party around his cubicle. My secretary volunteered to bake the

cake. We were going to invite all top management people includ-

ing the chief operating ocer to the morning break party. One of

the team members suggested that we get a commemorative plaque

for all his contributions to our team. We agreed to chip in $10

each for a silver plaque.

Afterward we planned to take him out to a farewell luncheon at

his favorite Mexican restaurant and to give him several presents. I

assigned a team member to get the presents before the luncheon.

I knew that my tool designer was a skier and a golfer. We decided

to get him a pair of ski goggles and half a dozen LED lighted golf

balls. e cost for each team member was $16.

e morning break chocolate cake party was well attended.

I gave a little speech praising my tool designer and wished him

well in his new life. I asked our chief operating ocer to present

him the silver plaque. e chief operating ocer said some inspir-

ing words and did his presentation. It was a great 20-minute get-

together and the delicious chocolate cake was all gone. I thanked

my secretary on the side for her great cooking skills. I also men-

tioned to our chief operating ocer that we were paying all fare-

well party expenses from our pockets. He was very tickled to

hear that.

en my team and I took him out to lunch and had outstand-

ing Mexican food in my tool designers honor. Everyone around

the table gave spirit- lifting speeches about him. I gave him his

179

case studIes In teaM ManageMent

presents and thanked him again for his outstanding contribu-

tions to my projects. He was ecstatic about his presents. He gave

a gracious farewell speech too thanking each individual on my

team and me for coaching, mentoring, and providing assistance

all throughout his career at our company. Lunch cost for each

team member was $7. Overall we had a great farewell party for

my tool designer. e cost of the farewell party for each team

member was $33.

e company overall saved a $330 expense. We managed to

give a great farewell party to my senior mechanical tool designer

without going through the pre- approval process for expenses. All

our eorts were for a good colleague and we accomplished every-

thing without any help from the company.

LESSONS LEARNED FROM THIS PROJECT EVENT

Sometimes you have to be creative and go around strict

company rules and policies without breaking any laws.

As project managers, we have to always show our appre-

ciation for good eorts put into our team by a fellow

team member who is leaving the company under favor-

able conditions.

Case6.13: Promises to Team Members

As a project manager, my ultimate target was to gain the respect

of my team members nationally and internationally. e best way

to gain respect was to keep all my promises to team members in a

timely fashion. I learned this approach the hard way. Earlier in

my project management career I made promises that I could not

keep. ese unkept promises created conicts and disharmony in

my project teams. A simple promise to upgrade one of my team

members workstation was not fullled on time due to my com-

panys budgeting conicts. My design engineer was livid about

my not keeping my end of the bargain in a timely fashion. I had

to authorize an upgrade to his workstation instead of waiting for

the IT department to act and charged the upgrade to my project.

More conicting promises arose from things that were outside

of my control as a project manager. Examples of these uncontrol-

lable promises were salary increases, bonuses, changing depart-

ments, and extra vacation times.

I had a design engineer from our Japanese division working

for me in California. I brought him to the United States for two

180

Project ManageMent case studIes

years of extra training and for him to help me in projects dealing

with our Japanese customers. He brought his family to the United

States too. During his stay in the United States, he still reported

to his supervisor in our Japanese division. He was at engineer 2

level. Engineer 2 level was dened according to our Japanese divi-

sion standards, which was dierent from the U.S. engineer 2 level

ones. He was always complaining about his salary level to me.

Our level 2 engineers were making 20% more than what he was

making. He was a good and hard working engineer and his con-

tributions were as valuable as his U.S. counterparts. During one

of our weekly meetings, I promised him that I would discuss his

salary situation with his supervisor and request an increase in his

salary. I called his supervisor and negotiated hard with him about

increasing his salary by at least 10%. His supervisor would not

budge. His supervisor told me that this young Japanese engineer

had two more years to go at engineer 2 level. After two years

depending on his performance, he could be promoted to engineer

3 level and get a handsome bump in his salary, which would be

comparable to U.S. engineer 2 level. My hands were tied. I could

not do anything else to keep my promise. I made a promise that I

should not have. I should have called his supervisor and discussed

his salary increase before promising him anything. I called the

young Japanese engineer to my oce and explained to him my

discussions with his supervisor. I told him that I would give him

a very high recommendation for the work he was doing in the

United States for me. He could be promoted to engineer 3 level in

two years and then could achieve the salary level he was aiming

for. He understood his salary situation. He was working for me

in the United States under our Japanese divisions rules. He con-

tinued his good and hard work and he got his promotion on his

return to Japan after two years. He called me and thanked me for

my very favorable recommendation.

I had another unfullled promise early in my career. I had a

team of six engineers to design and create software for feasibility

studies of industrial investments. We tested and released the soft-

ware on time and within our budget. During our project closure

meeting, I promised my team members good year- end bonuses

for their extraordinary eorts. Our feasibility software was being

used for every new industrial project planned by our corpora-

tion. My six engineers reported to three dierent managers in

our corporation. I talked to every one of them about the success

of my team. I emphasized that our corporation was gaining a lot

181

case studIes In teaM ManageMent

by optimizing investments made to new industrial divisions by

using our feasibility software. All managers agreed to recommend

handsome year- end bonuses for my teams engineers. In January,

all year- end bonuses were announced, but none of my teams

engineers got a penny. I was very disturbed and I could not face

my teams engineers. I went to see their managers to understand

what happened. ey all gave me the same story. Due to corporate

prot crunch, year- end bonuses were given to very few people.

My engineers missed the bonus pot. I had to explain to every one

of my teams engineers what happened despite my eorts. I was

wrong in raising the hopes of my teams engineers for something

that I had no control of.

In another empty promise case, one of the engineers on my team

was not happy at all with her supervisor. She wanted to change her

department and report to another supervisor whom she thought

very highly of. I promised her that I would talk to both supervisors

and would help her to switch departments. I discussed her wish

with both supervisors and with our human resources director with

no success. e department that she wanted to move to had to

generate a new opening at her level and her capabilities. en she

had to ocially apply for this new job opening. I did not have the

authority to accomplish her desired move in any way. Her options

were to quit the company or to learn to deal with her supervi-

sor. She chose the second option. She had to endure another three

years before her supervisor was assigned to another position.

In one of my design projects, we had a very tight schedule.

Our salespeople underbid my project. My project hours were

reduced by 25%. My four engineers were putting in 12-hour days

and working Saturdays and Sundays to keep up with our proj-

ect schedule. My team was close to burnout and they were not

enjoying their jobs. ey were joking with me by saying that they

wished they were hourly employees. ey would be making at

least double their salaries if they were hourly employees. I had to

keep them energized and happy. I worked the long hours along-

side them. I promised them an extra week of vacation time after

the project was completed. I talked to their supervisor in detail.

He did not agree with my generous vacation oer. He said that

his engineers were salaried personnel and they were judged by

the quality and the quantity of their accomplishments and not

by the hours that they put in. I was dumbfounded. I did not agree

with his assessment of salaried personnel at all. I took it on myself

to correct these unfair working conditions. I gave my engineers a

182

Project ManageMent case studIes

day o during the week if they spent a weekend day at the oce.

I showed these days o as working days on my project. is way I

eased their stress levels. In the end, I overran my budget by 9%,

but it was all worth it. We were only late by a week to complete

a yearlong project. I was apologetic to my team members that I

could not give them an extra week of vacation time. ey were

all appreciative that I leveled their stress levels by a day o during

the week.

As I gained experience in project management, I only made

promises that I could keep to my team members. I researched

thoroughly beforehand whether I could keep my promise. When

I gave a time frame for a promise, I always accomplished it within

that time frame.

LESSONS LEARNED FROM THIS PROJECT EVENT

Promises not fullled in a timely fashion to team mem-

bers will create disharmony and underperformance dur-

ing the execution of your project.

Do not make a promise to a team member that is beyond

your control.

Always discuss your idea for reward with the supervi-

sor of your team member and obtain his or her consent

before announcing it.

Case6.14: A Critical Team Member Getting

Married and Going on a Honeymoon

In the middle of an oshore oil platform equipment design and

construction project, one of my critical software design engineers

decided to get married and go on a honeymoon. He came to my

oce one day right in the middle of our projects very high activ-

ity period and surprised me by saying that he was going to get

married in a month in Mexico and then go on a honeymoon to

Australia for three weeks. He was going to be o the project close

to four weeks. ese surprising events were not planned in my

project scheduling at all. He was responsible for designing and

generating the software for the control system of the equipment.

He was right in the middle of his tasks. I told him that this was

quite a change of events in the middle of our project. His absence

period coincided with the initial testing of the equipment using

his control system. I had no one capable of taking over his tasks. I

had to think and nd ways to manage his tasks during his absence.

183

case studIes In teaM ManageMent

I could not get mad at him or ask him to delay his plans. He was

one of my ace engineers. I congratulated him on his decision to

get married, but I also told him that he should have planned for

his marriage at least six months ago. I told him that I was going to

prepare a plan to take care of his responsibilities in his absence. I

told him to meet with me again the next day on the subject.

He had four more weeks of work before he left for Mexico.

His eciency was going to drop, as he got closer to his wedding

day because of intense activities for his wedding ceremony. e rst

thing I had to get him to do was to bring the control system soft-

ware to a preliminary and operable phase before he left. He had to

provide me with a preliminary version of the software. He had

to leave me with his computers password and software le loca-

tions. I was not going to ask him to release his control software

through document control in its preliminary version. He was

going to train me on the usage of his software during his last two

days in the oce. I did not want to get any other team members

distracted spending time on his software. en I was going to

ask him to give us a call every morning at 9a.m. Australian east-

ern daylight time (3p.m. Pacic daylight time) so that we could

discuss all problems and hiccups that we had encountered while

operating the equipment control system software. I did not want

to call him and disturb him on his honeymoon every time I had

an issue with his software.

I had an hour meeting with him the next day. I laid out my

proposed solutions for his absence. He agreed with me that he was

going to be able to complete a preliminary version of his software

before he left for Mexico. He was not going to be able to complete

user instructions for his software by the time he left. He agreed to

train me on the usage of his software for two days before he left.

He also agreed to call me on Skype Tuesday through Saturday

mornings ve times a week at the agreed time. He was very appre-

ciative of my understanding of his situation. He told me that one

of my projects team members was going to be a groomsman at

his wedding.

I checked his progress daily during the next four weeks. He

completed as promised a preliminary version of his software before

he left for his big day in Mexico. He trained me for two days on

all the inputs, outputs, and possible trouble areas of his software.

He called me from Australia on the agreed upon call schedule.

Some of the calls lasted ve minutes, but several of them lasted

over an hour. We tried several ways to solve software operating

184

Project ManageMent case studIes

issues while he was live on Skype. With the daily calls, we got

along okay in his absence. He completed and released his con-

trol software and its user instructions two months after his return

from Australia. My team members and I contributed handsomely

to get a great present for our newlywed colleague.

Several unexpected events like this one occur during the course

of a project. Some project managers get upset and blow their tops

o, but this type of behavior does not solve anything. Negative

reactions make things worse. You have to be coolheaded, versa-

tile, and rm to nd other solutions fast in order to bring the dif-

cult situation under control.

LESSONS LEARNED FROM THIS PROJECT EVENT

Many surprising and unscheduled events can occur dur-

ing the execution of your project.

As project managers, we have to be coolheaded, versatile,

and able to orchestrate a viable solution to keep our proj-

ect moving ahead unharmed.

Case6.15: A Project Manager Goes on a Sabbatical Leave

I was a senior scientist in a team of several engineers and designers

that were assigned to design and build prototypes of a new rotary

combustion engine in 18months. Our team leader was a dedi-

cated automotive engineer and an excellent team leader. Right at

the height of the project, he had to take a three- month sabbatical

leave to fulll his compulsory military service. He asked me if

I could lead the team during his absence. I accepted the chal-

lenge without any hesitation. I knew all the team players well.

All tasks were progressing smoothly. I did not see any problems

on the horizon. We agreed that he was going to call me twice a

week in the evenings to get a brieng about the project. He gave

me authorization to sign o on all time cards and all expenses for

the project. We had a team meeting and he explained his situation

to the team. He introduced me as the interim project manager

for the project for the next three months. e next day he left

to fulll his military service obligation.

I started to manage the team without any incidents. e rst

week passed without a glitch. e project was on track on all

cylinders. My management style was dierent from our project

manager. He liked to micromanage every team member to the

extreme. On the other hand, I gave a calculated space to team

185

case studIes In teaM ManageMent

members working under me. I gave a task to a team member and

asked for results in a given time frame depending upon the team

members experience and dedication to his or her work.

During the second week, one of the design engineers started to

slack o. His behavior was reminiscent of a mouse playing because

the cat was gone. His work eciency dropped drastically. His outside

interests increased. He started to take long lunch hours. He called in

sick on Mondays. At rst I cautioned him verbally. Nothing in his

behavior changed. He thought he could get away with it since I was

the interim project manager. I discussed his behavior with the proj-

ect manager during our bi- weekly brieng. He asked me to write a

warning letter and review the letter with the design engineer in the

presence of a human resources representative. I reviewed the written

warning with the design engineer and led it with human resources.

I started to micromanage him and tried to help him get on track and

catch up with his tasks. I did not want to take drastic measures and

re him before our project manager returned from his sabbatical

leave. Everyone else on the team was performing well. I was patient

and limped along with the design engineer for three months.

Our project engineer came back and relieved me from my team

management responsibilities. He was also very upset with the proj-

ect engineer for not completing his tasks as scheduled. Our project

manager gave him a written warning too. He was ready to re the

project engineer. I asked the project manager to give me another

week to straighten out the project engineer. I told him that the

design engineer was very knowledgeable in material science and it

would not be easy to replace him in the middle of the project. He

agreed with me. I took the project engineer out to lunch to have

a heart- to- heart discussion about his work behavior and perfor-

mance. I told him that he had to pull himself together without

any delay and had to improve his work performance or else he had

to nd another job. I emphasized to him that management was

ready to re him if he did not improve his work behavior and per-

formance fast. He started to share his personal problems with me.

He had a new girlfriend who was apparently very demanding. He

was prioritizing his new girlfriend before his work responsibilities.

Our two- hour long lunch discussion did the trick. Finally, the

gravity of his deteriorating situation at work dawned on him. He

started to work harder. He put in many extra hours to catch up

with his commitments. Our project manager thanked me for sav-

ing the design engineer from being red. at disruption would

have put a dent in the progress of our project.

186

Project ManageMent case studIes

As project managers, we have to sometimes act as psycholo-

gists. We should not take drastic actions on a whim or in a burst

of anger. We have to consider all repercussions that an immediate

action might cause in our project. A colleague of mine used to

always remind me to measure twice or better three times before

you make a critical cut.

LESSONS LEARNED FROM THIS PROJECT EVENT

Diculties can arise between you and your team mem-

bers when you take over a project in the middle of its

execution.

As project managers, we have to consider all options

before we make a critical decision.

Case6.16: Technical Publishing during a Project

I always encouraged my project team members to publish their

leading-edge ndings in reputable journals as long as their publi-

cations did not disclose any intellectual property of our company

and of our customers. I also encouraged them to subscribe and to

read all technical journals in their elds so that they could stay up

to date in their elds of expertise. I asked every team member to

share his or her news about technological advances in our weekly

team meetings. As engineers we were always in a technology race.

As soon as we stopped learning and closed our eyes to the outside

world, we would fall behind in our eld and we would evaporate.

Our publications enhanced our resumes to a higher level and gave

us an insurmountable edge over our competition in promotions

and in job searches.

In my project management career, I had to provide my team

members a fair balance between time spent on writing papers and

on doing actual project work. I had a Ph.D. physicist working for

me on an advanced magnetic head design project. His knowledge

of advanced magnetics was excellent. He spent almost 50% of his

working time writing papers for dierent journals. He was also

refereeing submitted papers on several journals during working

hours. He came to work exactly at 8a.m. and left exactly at 5p.m.,

not a minute later. He copublished most of his papers with other

contributors from my project team. If he did not copublish, he

acknowledged all the contributors in his papers. He was a well-

respected scientist in his eld. I valued his achievements but I had

187

case studIes In teaM ManageMent

to get more out of him on my projects side and reduce his com-

mitments to publishing during working hours.

I went to his oce and had a heart- to- heart discussion about

his excess commitment to publication during working hours. I

told him that it was okay with me if he spent 10% to 15% of his

working hours on publication- related issues. I reminded him that

his project tasks in advanced magnetic head design were falling

behind. He told me that he was always in a race with other scien-

tists to publish a new idea. He wanted to be the rst one to publish

a new idea in the scientic world. He also had to get approval

from our patent lawyers before submitting his papers. He believed

that it was always desirable to have our companys name rst in

leading journals.

I agreed with all his comments and left his oce without a res-

olution regarding his time spent on writing and refereeing papers.

I had to think hard not to antagonize him and get a fair resolution

to our problem. I did not want to go to his boss and complain

about the situation at hand. I had to deal with him myself and

nd a fair solution. I thought about a middle-ground solution for

a couple of days. en I called him to my oce in order to propose

and negotiate my solution. I told him that he could spend all the

time he wanted on publishing and refereeing papers as long as

he put in an honest 32 hours of work on my project every week.

I gave him freedom in 20% of his weekly working hours to do

whatever he wanted to do in publishing. If he wanted to spend

more time in publishing, he had to do it after 5p.m. at work or

at home. He could not argue with my proposal. He told me that

I was trying to put brakes on his publishing eorts. I emphasized

that my projects tasks were more important than his publishing

eorts. I reminded him that our company could only survive, if

we were the leader in our products, not in publishing. Finally, he

came around and reluctantly accepted my proposal. I told him that

in dire situations such as a deadline, he could spend more work

time for publishing as long as he notied me. is ne loophole

gave him more condence in our relationship. Finally, he started

to spend 32 hours per week on my projects tasks.

Specialists and/ or scientists can be very moody and demand-

ing in a team environment. As a project manager, you need their

expertise. You have to treat them with respect. You have to cre-

ate a exible boundary with their needs and with your projects

requirements. If you become a hard- liner with such people, your

project will suer in the end.

188

Project ManageMent case studIes

LESSONS LEARNED FROM THIS PROJECT EVENT

Getting a team member to focus on your projects tasks

can be challenging when that team member has a lot of

other interests besides your project.

Your exibility in solving a dicult case regarding a

team member will benet your project in the long run.

Case6.17: Team Atmosphere after Vacations and Holidays

As global project managers we have to know every team members

vacation plans in advance. We have to know all national holi-

days of the countries we are dealing with. We have to know all

religious holidays that each one of our team members and coun-

tries are observing. Religious holiday observance days might get

very confusing, if you are dealing with multi- ethnic countries like

India and Malaysia. It is always a must to include all these events

into your project schedule at the initial stage of your planning.

You might come across many surprises that can aect your proj-

ects critical tasks and deliverables.

In one of my project teams, I had a novice engineer who could

not get into a work mood easily after he came back from holidays.

He was still dreaming about turkey dinners, apple pies and ice

cream, a Christmas gift he got, and New Years celebrations. He

was going around discussing his experiences during the holidays

in detail with child- like excitement with his colleagues. I had to

micromanage him daily after the holidays so that he could get

back to his work and start focusing on his tasks. After a couple

of holidays, he started to act more professionally and discussed

his holiday experiences with his teammates only during breaks.

is novice engineer took his two- week vacation after a year

of employment and went to Tahiti with his girlfriend. After he

got back he acted like a lost soul under lots of stress. He could not

switch easily from a relaxed atmosphere to the rhythm of orga-

nized work. His e- mails and his phone messages accumulated

quite a bit during his two weeks of absence. He did not know

which task to tackle rst. He came to my oce and asked for my

help. I told him to rst review all his e- mails and phone messages

and jot down important ones and ones that needed action and

response from him. en I asked him to come back to my oce

with his list the same day. He came back and we together reviewed

his action items list and prioritized every item on it. We also put

completion dates for each action item. is kind of personalized

help showed my novice engineer how to deal with numerous action

189

case studIes In teaM ManageMent

items on his to- do list after a relaxing vacation. He appreciated my

guidance and thanked me a lot for easing his stress level. He went

on to become a very organized and productive engineer in two

years. After two years, I recommended him to be promoted to an

engineer 2 level. He received his promotion. He was very grateful

to me and he always wanted to work on my projects.

In an opposite case, an engineer from our Malaysian facil-

ity was working on my project in California. I brought him to

California for a six- month period to help me in several tasks in my

volume production ramp- up project and to be trained in certain

inspection methods. One day he came to my oce and asked if I

could send him back to Malaysia for a week to see his family dur-

ing a religious holiday that was coming up in 10days. His request

came to me by surprise at a very high activity phase of our project.

I told him that it would put a big dent in the progress of our project

if he were gone for a week. I could not outright reject his request. I

had to do all I could to nd a way to send him home for a week to

spend his important religious holiday with his family. I told him

that I would try to bring in another engineer to ll in for him for

a week. I also told him that I could not pay for his trip expenses

from my projects budget. I promised him a response in a day.

I discussed my Malaysian engineers holiday request and my

projects dire need for backup engineering manpower for a week

with our quality engineering manager and got one of his engineers

to help me. I immediately gave the good news to my Malaysian

engineer that he could leave our team for a week. Somehow he

found a cheap round trip ticket in a short time and went home for

his religious holiday. After he got back, he worked very hard and

long hours on my project team to pay me back his gratitude.

Unexpected vacation and holiday requests from team members

can occur during the course of a global project. Vacations and

holidays tend to bring instability to the progress and atmosphere

of a project. As project managers, we have to deal with them in a

timely fashion and try to smooth out their ripple eects.

LESSONS LEARNED FROM THIS PROJECT EVENT

It takes awhile and your continual guidance to get some

of your team members into an eective working mood

after holidays and vacations.

Unexpected vacation or holiday requests can come from

your team members. You have to deal with these requests

in a positive manner.

190

Project ManageMent case studIes

Case6.18: Project Team Members Maternity Leave

Maternity leave can hit your project team any time. You have to

restructure your team and get new personnel reinforcements in a

timely fashion in order not to aect the progress of your project.

In a new wafer factory setup project, I had a very talented female

engineer on my team. She was very experienced in experimental

design and in industrial statistics. She was designing all qualica-

tion experiments for new equipment along with equipment engi-

neers who were cognizant of wafer processes and then analyzing

resulting data with them. She came to my oce one day and told

me that she was four months pregnant. She had already talked

with our human resources group. She was very excited about her

rst child. She was planning to take o a week before her due

date, which was predicted by her doctor, and she was going to

take a total of 12weeks for maternity leave. She was going to have

her full salary and her full health benets during her maternity

leave. She was also going to have full job protection. She wanted

to come back and continue to work on my team after her mater-

nity leave was over. She also would not be able to y after her

sixth month of pregnancy, which was going to be in two months.

I congratulated her and wished her a healthy pregnancy. I asked

her to think about how to replace her temporarily for 12weeks. I

asked her to get together with me on the subject in a week.

I considered my options too during the week. I analyzed all her

upcoming tasks. Her maternity leave was occurring right in the

thick of things in my project. I had to nd a reliable replacement

for her fast so that the two of them could spend a month together

before she went on her leave. She came to my oce the following

week to discuss her temporary replacement. We could not agree

on an internal replacement. No one in our company had the broad

and in- depth experimental design skills that she possessed. We

decided to go outside to a consulting rm. is consulting rm

had given her lots of training in the past. We called the consult-

ing rm and set up a face- to- face meeting. We agreed on a senior

consultant to come and help us during her maternity leave. is

senior consultant was at one time her training instructor. He was

very expensive, but he was the right person for the job. He agreed

to start a month before her maternity leave for a phase- in period

for her tasks. I asked my purchasing department to put together

a contract with the consulting rm. We had to cover his travel,

191

case studIes In teaM ManageMent

lodging, and meal expenses too. e senior consultants expenses

were going to put a huge dent into my projects cost performance.

I went to my upper management and negotiated to charge to my

project only the amount equal to my engineers salary. e rest of

the consultants expenses were to be absorbed into the company

overhead. at was the just way of splitting the consultants cost

to my project.

e consultant started to work on my team along with her a

month before her maternity leave. e phase- in and phase- out

process was smooth. She gave birth to a healthy boy on the day

predicted by her doctor. My team and I sent her hospital con-

gratulatory owers. I talked with her on the phone and discussed

her and the babys health. Everyone was doing great.

Two months passed after her birth, I got a phone call from

our human resources group informing me that she wanted to take

o another six weeks after her maternity leave was over for baby

bonding. She was going to have 50% of her salary, her full health

benets, and her full job protection during this baby bonding

period. is was quite a shock to me. She did not even call me

to discuss her decision to extend her maternity leave. My human

resources director told me that she had the right for this baby

bonding leave under California law.

I discussed the six- week baby bonding extension with the senior

consultant. He said he could not extend his contract because he

already had other commitments. He had three more weeks left on

his contract with us. During these six weeks, all her tasks were

on the critical path of my project. I had to scramble again to nd

a replacement for her for another six weeks. I decided to groom a

willing engineer internally for my team. Internal grooming was

also benecial for my company in the long run. I discussed the

issue with all engineering departments heads. Two names came

up as possible candidates. I interviewed both engineers. I decided

to give a novice and ambitious mechanical engineer a try. He

spent three weeks next to the senior consultant. I called my female

engineer at home to discuss the bind I was in. She oered to help

my new engineer on the phone from home. We limped through

six weeks of her baby bonding period. Finally, my female engineer

returned to her tasks after 18weeks. During this chaotic period

in my project, my company gained another bright engineer who

went on to become an expert in experimental design and in indus-

trial statistics.

192

Project ManageMent case studIes

LESSONS LEARNED FROM THIS PROJECT EVENT

When a maternity leave request comes to you, always

bring your human resources department into the picture

to learn all federal, state, and company rules, regulations,

and options.

You have to be ready for surprises during a maternity

leave so that your project does not suer.

Case6.19: Shelf Life of Photoresists in Wafer Fabrication

In wafer fabrication of magnetic heads the photoresist played a

very important role. As the photoresist aged, its sensitivity to light

exposure and its light absorption characteristics changed. is

variability in turn aected our products steep wall proles. Our

product lost wall edge acuity. erefore, all of a sudden lots of

wafer scraps started to occur. is phenomenon occurred inter-

mittently in our wafer fabrication when I was heading the engi-

neering group. I had several meetings with my photolithography

engineers. We could not determine the cause of the degrading

edge acuity phenomenon. We did lots of design of experiments,

but we could not pin the yield drop to the age of the photoresist

used in the factory.

One of my quality engineers in wafer fabrication suggested

my team perform an experiment with the age of photoresist

versus steep wall edge acuity. Everyone on the team agreed to

these experiments. I assigned the quality engineer who suggested

the experiment along with a photolithography engineer to per-

form the required tests in two weeks. ey ran experiments with

one-, two-, three-, four-, ve-, and six- month- old photoresists.

ey found out that steep wall edge acuity in our products started

to degrade when the photoresist was older than three months.

ey also ran conrmation experiments to verify these results.

I immediately issued a memorandum to all shifts in wafer

fabrication not to use any photoresists that were older than three

months. We had another problem with the photoresist contain-

ers. e manufacturing date of the photoresist was indicated on

a sticker by the manufacturer, but this sticker very often fell o

the container. So we sometimes had no idea when the photo resist

was manufactured. I called the photoresist manufacturer with

our receiving inspection and purchasing managers. We asked

them to put permanent laser markings on every photoresist con-

tainer identifying the lot number and the manufacturing date.

193

case studIes In teaM ManageMent

e photoresist manufacturer agreed to our container markings

request. Two weeks after our telephone discussion, we started

receiving photoresist containers that were permanently marked

with the lot number and the manufacturing date.

e photoresist usage expiration date had to be on every con-

tainer. I discussed this issue with our stockroom manager. We

decided to laser scribe usage expiration dates on the body of the

container in large fonts. We kept the photoresist in special stor-

age rooms with temperature, 5C to 10C, and relative humidity,

30% to 50%, control. Upon my request, all stockroom personnel

were instructed by their manager not to issue to production any

photoresist containers that were over the usage expiration date.

ey were also instructed to dispose of any containers that were

over the usage expiration date.

With all the steps taken to control the useful life of the photo-

resist, our products steep wall edge acuity became very stable.

We did not have any intermittent out- of- specication wall pro-

les. Our wafer scraps due to out- of- specication wall proles

decreased tremendously.

We spent months to nd the cause for our steep wall pro-

le defects. We performed numerous full factorial design- of-

experiments with two or three factors and each factor having two

or three levels. None of these complicated, time- consuming, and

expensive experiments provided us with any reliable solution.

e photoresist useful life eects on steep wall prole were

not even suggested by one of my photolithography engineers. e

suggestion came from one of my quality engineers. She was not at

all involved with our photolithography processes. She was a qual-

ity engineer in our plate and etch group. During our weekly engi-

neering team meeting, I praised her for suggesting the solution to

one of our mind- boggling problems. I also gave her a handsome

bonus during our annual review. I patiently learned to listen and

evaluate all suggestions that were proposed during our engineer-

ing team meetings. Being a good listener provided my team mem-

bers with upbeat empowerment and helped us nd solutions to

dicult issues in our wafer fabrication.

LESSONS LEARNED FROM THIS PROJECT EVENT

A good solution to a nagging engineering issue can come

from unexpected sources.

As project managers, listening and evaluating everyones

input to a problem increases our chances of success.

194

Project ManageMent case studIes

Case6.20: Excessive Meetings

I was leading a project with a U.S. and overseas team in Malaysia

to set up a manufacturing plant there. My U.S. team consisted of

12 engineers split equally into design, manufacturing, test, and

quality subteams. I had 12 Malaysian engineers based in Penang

as counterparts of my U.S. team. We had weekly teleconferences

to bring everyone on the team up to date regarding the tasks that

everyone was working on. It took us two hours every Monday

afternoon (Tuesday morning in Malaysia) to go over all the tasks.

It gave every engineer about ve minutes on average to present the

status of his or her task responsibilities.

We were spending 48 man- hours a week on this teleconfer-

ence meeting. Everyone was waiting for his or her turn. Some

engineers were twiddling their thumbs during the presentations

that they had no interest in. Some engineers were busy with their

laptops. Some Malaysian engineers were not at the meeting when

their turn came up. ere was a lot of wasted time during these

teleconference meetings. It was an inecient way to manage a

meeting. I decided to take some action to correct the situation.

I talked with my dierent subteams in the United States and in

Malaysia about improving the weekly teleconference meeting. We

brainstormed several ideas to improve the eciency of our weekly

status meeting. e best idea came from an engineer in Malaysia.

She proposed that we break up the meeting into four half- hour

segments, namely design, manufacturing, test, and quality seg-

ments. During the design segment, only the design engineers

would attend the meeting. During the manufacturing segment,

only the manufacturing engineers would attend the meeting.

During the test segment, only the test engineers would attend the

meeting. During the quality segment, only the quality engineers

would attend the meeting. If there were any issues crossing the

subteam groups, I would record them as action items in the meet-

ing minutes and a particular issue would be handled by e- mail

or by telephone by its action item owner. If any one of the team

members were interested in a certain task in a dierent subteam,

he or she could review the released meeting minutes from docu-

ment control.

I issued the new weekly teleconference meeting process. From

4 p.m. to 4:30p.m. (U.S. Pacic time zone), it was the design task

groups turn, from 4:30 p.m. to 5p.m., it was the manufacturing

task groups turn, from 5 p.m. to 5:30p.m., it was the test groups

195

case studIes In teaM ManageMent

turn, and from 5:30 p.m. to 6p.m. it was the quality groups turn.

I also rotated the groups turns every two months so that one task

group did not get stuck with the late afternoon meeting time in

the United States or the early morning meeting time in Malaysia.

I also had a monthly half- hour general project status teleconfer-

ence meeting for all team members, domestic and international.

is new communication setup worked very well all through-

out the project for two years and we saved about 75% man- hours

that were being wasted during the weekly status meetings. On top

of that, engineers were not bored during the meeting. ey came

into the meeting room, gave their presentation, and left the meet-

ing room in half an hour. Sometimes there were shifts in presen-

tation timing. If a subteams presentation ran over half an hour,

I informed the other subteams about the delay and they showed

up at the new modied presentation time in the conference room.

My counterpart in Malaysia did the same thing.

Meetings are the backbone of a project. ey have to be stan-

dardized and managed properly so that a precious team members

time is not wasted; the team member is not bored, and he or she

contributes constructively during his or her presence in the meet-

ing. Especially in large team groups, as it was in this case, break-

ing up a meeting into smaller subgroups can be very eective.

LESSONS LEARNED FROM THIS PROJECT EVENT

Project meetings can accumulate lots of wasted team

members time.

Plan ecient project meetings and make sure that your

team members around the world are not twiddling their

thumbs and they do not look bored during a meeting.

Case6.21: First Article Mishap

I was heading the project of designing, manufacturing, and test-

ing a new generation of battery- powered electric buses. Forty- foot

long electric buses provided four and a half hours of stop- and- go

level terrain travel on a single charge fully loaded with 80 pas-

sengers. e electric buses were for a mall shuttle operation. My

team was getting ready for the rst article acceptance meeting

that was scheduled to start on a Monday and was supposed to

last for three days. On Friday morning before the start of the rst

article acceptance meeting, my manufacturing manager brought

196

Project ManageMent case studIes

the rst article bus to the charge station in our plant to charge

its batteries. e charging operation took about eight hours. We

were running around like our heads were cut o to complete last

minute nishing touches and tasks for the Monday meeting. We

were all tired and were looking forward to a restful weekend

before the big Monday presentation. All my team members and

I had been working 70-hour weeks for the last month to prepare

the rst article for this crucial acceptance meeting.

At 4p.m. on Friday, I unplugged the battery charger eagerly

and started to drive the bus to its presentation spot. ere was a

short steel post in front of the charge station hidden behind the

bus. While backing the bus out of the charge station, I ran the rear

side of the bus into the steel post. One of the side rear windows

broke and there was minor bodily damage too. It was my mistake

to rush to drive the bus to its presentation spot. I knew where the

steel post was and I thought I was clearing it during my maneuver.

I was so mad at myself for rushing and causing this damage to the

bus right before the rst article acceptance meeting.

I immediately called a meeting with our manufacturing

manager and our body shop personnel. e meeting was held

at the damaged rear of the rst article bus. I told my team that

I was devastated by my mistake and I asked them if the dam-

age was xable by Monday. We all assessed the damage and

agreed that the damage was xable before Mondays meeting.

We decided that three body shop technicians would be needed

to x the damage during the weekend. I asked my team who

would volunteer for the weekend overtime repair task. ree out

of six technicians volunteered immediately. I told them that I

would be at the plant too along with them during the week-

end and bring breakfast and lunch for them. My gesture was

received very favorably. We were able to replace the broken win-

dow easily with another one. e body damage took most of the

repair time. e body damage was repaired by straightening the

surface sheet metal and then painting over it during Saturday

and Sunday.

e rst article electric bus was ready for the acceptance meet-

ing at 9a.m. Monday morning. e fresh paint at the rear of the

bus was not even dry. I was afraid to drive the bus to the presen-

tation site. I let my manufacturing manager do the honors. For

three days, the rst article acceptance meeting went well. Our

new generation of battery electric bus got excellent grades from

197

case studIes In teaM ManageMent

our customers representatives. ey accepted our battery electric

bus with minor modications.

I told our customers representatives of what happened on

Friday. ey were amazed that we were able to work all weekend

to get the bus xed and ready in top shape. Our customer was very

appreciative of our performance. After the last meeting, they took

my whole team of 20 people out to dinner.

ese kinds of mishaps happen more often than not while pre-

paring for critical meetings or deadlines in a project. Overworked

and overtired team members become prone to mistakes and acci-

dents. As a project manager, I had to watch myself and my team

members for fatigue and for burnout conditions. We had to slow

down and take a break from running a 100miles an hour. One

solution would have been to delay Mondays rst article meeting

for a couple of days.

LESSONS LEARNED FROM THIS PROJECT EVENT

You have to control your pace and fatigue level and your

team members pace and fatigue level when you are pre-

paring for a crucial event for your project.

It might be wiser to postpone a crucial project event than

to burn out yourself and your team members preparing

for it.

1

1

Case studies in

stakeholder ManageMent

Stakeholders that can aect your project can vary from your

customer(s), your company, your project partner(s), your companys

investors, to your subcontractors. During the course of your global

project, you have to manage all these entities as needed.

Health of the cash ow in your company can be a project derailing

factor as it happened to me in Case1.1. Changing and condensing the

project schedule in order to help my company to get paid two weeks

earlier was a challenging eye opener for me.

Protecting the intellectual property of my company during tech-

nology transfer to a Japanese company was a very challenging project

assignment to me as detailed in Case1.2. Detailed preparations and

training of my people before Japanese engineers invaded my com-

panys facilities were key elements for the projects success.

Our corporate closed down our companys operations during the

2000 to 2002 dot- com bust. I was right in the middle of a data com-

munication chip design project. My team and I had to jump over

hoops and had to make lots of sacrices, but we held together as a

team in order to complete our project successfully. is challenging

event is detailed in Case1.3.

As travel costs for an internal project to Malaysia skyrocketed, my

travel budget was frozen by my companys upper management. My

team and I took many steps to curb our travel costs. I pleaded with

my upper management for my projects travel budget increase. Every

time I was rejected. ey emphasized that I should cut down on travel

and keep my travel budget as it was. We did all we could as shown in

Case1.4, but in the end we still exceeded our travel budget.

During a project every member of my team reported to their partic-

ular departments manager and reported to me on a dotted line basis.

I had no control of their performance reviews, promotions, salary

2

Project ManageMent case studIes

increases, training, and personal issues. One day I lost the services

of our whole quality department. I had to scramble to nd replace-

ments without hampering the progress of my project as described in

Case1.5.

I was given the internal project of putting together an extensive

feasibility study in three months in order to give direction to our mag-

netic head manufacturing processes for the next generation of our

products. ere were three dierent approaches in three dierent

countries that were being considered by dierent groups in my com-

pany. I detailed the actions I took to generate the feasibility study and

the nal decision process in Case1.6.

Upper management changes in a company can impact positively

or negatively internal project directions, project teams, manage-

ment styles, and project reporting styles. Personnel and responsibility

changes in upper management and on my team caused tsunami eects

to my project. I outlined these eects in Case1.7.

A project manager has to fully understand at the beginning of the

project all contract agreement conditions for delays in deliveries, pat-

ents, copyrights, trademarks, force majeure, subcontracting rules and

governing laws, and arbitration. In addition to understanding all con-

tract agreement conditions, he has to relay them to his team members

in laymans terms. Our legal department saved my bacon from a dis-

pute that arose at the end of a project with my customer as detailed

in Case1.8.

Salary and compensation variations in a multinational company

can cause stress, disputes, and jealousy in an internal project team

environment. Team members have to be very sensitive and careful not

to discuss salary and compensation issues with each other locally or

internationally. Such a are- up is discussed in Case1.9.

Lessons learned from previous projects within a company let a proj-

ect manager start his or her project on a strong footing. Undocumented

historical projects and uncontrolled lessons learned items create a

large vacuum for a project manager. Such an occurrence is detailed

in Case1.10.

A companys upper management cannot decide on the future direc-

tion of the company internally by themselves. ey mostly go outside

to get help. ey approach consulting rms, experts in their eld,

3

case studIes In stakeholder ManageMent

even friends outside the company in order to get a fresh outlook and

ideas for the future of their company as shown in Case1.11.

Your customer(s) are crucial stakeholders in your project. You have

to do all you can to manage your customer(s) too. In order to ease ten-

sions between my Korean engineering project team and my Japanese

customers visiting qualication team, I decided to go to Korea rst

for two weeks to prepare and train my Korean team for our Japanese

customers qualication process both psychologically and technically.

Historical animosities between two countries can aect the prog-

ress of a project. Preparing carefully for such complicated encounters

between projects parties is described in Case1.12.

A customer placed a resident engineer into my project group in

the United States to oversee all our activities and to make sure that

their intellectual properties were fully protected. e customer also

assigned a resident engineer to our volume production plant in South

Korea. is resident engineer also traveled to Japan to check on our

subcontractor every fortnight. Complications that were encountered

during the execution of my project with two resident engineers are

detailed in Case1.13.

I could never close out a project because the nal project evalua-

tion by the customers project manager was missing. I had to jump

through many hoops in order to get my customers nal project evalu-

ation report as detailed in Case1.14.

Communicating ltered information is the backbone of a projects

control structure. How much information to pass on and how much

you want to disturb the cart are crucial factors during the life of a

project. If every little detail regarding your project goes to your cus-

tomer, you are mismanaging your project. You have to lter out rip-

ples in your communicated information. At the same time you have to

realize what information and when to inform your customer without

any delay. Such challenges were encountered in Case1.15.

For a global project manager, keeping track of all national and reli-

gious holidays of countries that you are dealing with are a requirement.

You have to also know religious beliefs of every individual you are

dealing with in order not to run into surprises as depicted in Case1.16.

I received a call from my customers project manager that the proj-

ect goods shipment arrived safely in South Korea, but they could not

4

Project ManageMent case studIes

clear the cargo from South Korean customs because the spare parts

were missing from the nal inspection reports packing list. e cus-

tomers inspectors, the customers bank, and my shipping department

all missed the 10 spare parts from the packing list. is incomplete

packing list caused me a lot of headaches as shown in Case1.17.

In every project, almost all hands in a company swarm around a

critical project person with good intentions to get a feeling of how

things are going. ey waste his or her valuable time. If the project

person has an easygoing personality, he or she tries to accommodate

everyones inquiries and questions. Valuable time can be wasted and

the project schedule can unintentionally go down the drain. You have

to caution your team members to let you know if there are unneces-

sary interferences with their work. As a project manager, you have to

protect your team members from these unnecessary distractions as

depicted in Case1.18.

I had a distasteful ordeal with an authoritarian director during one

of my projects. Case1.19 details the events that occurred during an

unfortunate management clash.

After 14months of challenging problem- solving sessions, board

meetings, communications, and travels between our U.S. plant in

California, our subcontractor in Boston, and our plant in Malaysia,

my project team, our subcontractor, and the Malaysian project team

had continual changes in every task of a challenging project to imple-

ment two automation assembly modules in our Malaysian plant as

detailed in Case1.20.

Closing a project appropriately can be painful and time consum-

ing for a project manager. However, the rewards for a properly closed

project can be invaluable for your team members and for your com-

pany. Lessons learned tasks are the most important ones on a projects

closure to-do list. As project managers we have to nalize lessons

learned tasks at all cost as detailed in Case1.21.

Everyone on our team and every member of our companys upper

management has to understand the penalties involved in a projects

contract. Late deliveries and resulting price reductions in a contracts

value and also resulting liquidated damages can damage a company

irreversibly. Such cases are detailed in Case1.22.

5

case studIes In stakeholder ManageMent

Case1.1: Company Cash Flow Issue Aecting

Design Review Pull- In

In the middle of an equipment design, build, and test project

for an oshore oil platform, the company president came to

my oce and explained to me that the company had a short-

age in cash ow during the coming months. He asked me if I

could bring in the customer design review and design drawings

approval phase of my project, which was due in eight weeks, by

two weeks so that the company could get paid 10% of the total

project funding two weeks earlier. I told the company president

that I would work on his request with my team members and

with the customers project manager and get back to him in three

working days.

is was quite a challenge that was thrown in my lap on top

of all my other project management responsibilities. e company

presidents request went to the top of my action item list because

the companys cash ow health meant a lot to the morale of my

team members and to myself. Another twist on this issue was the

inner workings of our customer who was Finnish. is was our

rst project for them. I had no idea if the customers project

manager and nance department would entertain such an earlier

design review and phase 1 payment to us. My team had to design,

check, and release close to 40 drawings, 15 calculations, a struc-

tural interface drawing approved by the customer, and the control

panel software code before the design review meeting. We had to

cut our tasks duration by 25%.

e rst step was to discuss the situation with my team mem-

bers. I had a team meeting with them the next day. I explained to

them the company presidents request to accelerate the rst phase

of our project by two weeks. I had six full time engineers working

on the project. We went over every task, 140 of them, that had to

be completed and over all the task interactions. e team mem-

bers had good suggestions.

One of them was to bring into our project a senior engineer

from the manufacturing department full time for six weeks to

check the design calculations and drawings.

Another suggestion was to get two more workstations assigned

by the IT department full time to our project for parallel nite

element scenario runs.

e third suggestion was to put in an extra hour a day to com-

plete all the tasks before the design review

6

Project ManageMent case studIes

e fourth suggestion was to deliver the structural interface

drawings in four weeks to our customer. I had to ask our customers

project manager to commit to review and approve structural inter-

face drawings in two weeks by the design review meeting date.

All these suggestions came from my team members. Nothing

was forced down their throats. ey all had a can- do attitude.

I issued the meeting minutes in a controlled fashion through our

document control and made sure that the company president got

a copy.

After the meeting I went to the manufacturing department

managers oce and explained the situation. I asked him to assign

a particular engineer as a checker to my team for six weeks. I also

mentioned to him that checking by his senior manufacturing

engineer would benet him later too in his manufacturing pro-

cesses. His senior engineer would catch early all the missing criti-

cal dimensions and tolerances in the drawings for manufacturing.

He was very kind and he accepted my request. He had no other

choice. If he refused, my next step was to bring the company pres-

ident into the picture.

My next stop was to the IT department managers oce. I

asked him for two more workstations for six months, which he

did not have laying around in the company. We agreed to lease

them for six months and get the expenses charged to my project.

en I sent an e- mail to my customers project manager to have

a call with him at 6 a.m. in the morning my time and 4 p.m. his

time in Helsinki, to discuss a change in the design review date.

I wrote in my e- mail that we would like to pull in the design

review date by two weeks. I also mentioned that if he was not

available at my requested call time, he should specify a time that

was convenient for him.

Around 10:30 p.m. that night, I checked my company e- mail

from home and saw that I had received an answer from Helsinki.

My counterpart at the customer informed me that he would be

ready for my phone call at 4 p.m. his time. I set my clock to 5 a.m.

and went to bed anticipating a long day in front of me.

e next day, I called my customers project manager at 6 a.m.

my time. After initial greetings I explained to him that I had

excess manpower in my project and things were looking ahead of

schedule. I would like to transmit to him the structural interface

drawings in four weeks and asked him to review them and approve

them in two weeks after receipt. He did not see any problems with

that. en I explained to him that we would be able to complete

7

case studIes In stakeholder ManageMent

all the design calculations and drawings in six weeks for the design

review. Could he and his colleagues come to our facilities two

weeks earlier for the design review meeting? He said he would dis-

cuss the new design review meeting date with his two colleagues

and inform me in 24 hours by e- mail if they could make it.

Next, I brought up the phase 1 payment issue. I told him if all

goes well during the design review meeting could he also pull in

the phase 1 payment by two weeks. He said he had to discuss that

with their nancial and purchasing people and also get back to

me. I emphasized that this payment was important to my com-

panys cash ow and asked him to do his best to make it happen.

He promised that he would do his best to pull in the phase 1 pay-

ment. en I got an e- mail from him that evening informing me

that he and two of his colleagues could make it to our facilities

two weeks earlier at the specied new design review date. He was

also working on the phase 1 early payment issue.

I called the next day to thank him for accepting the earlier

design review, and found him at his desk. I told him that I would

make the hotel arrangements close to our facilities at the company

rate and we would also provide them with a company car. ese

small gestures were very much appreciated by him. He told me

that he was still working on the phase 1 early payment issue. He

estimated that he would have a nal answer to me in a week.

I documented the highlights of my calls to the customers con-

tract manager and released them in document control and made

sure the company president got a copy. Next I made an appointment

with the company president, as I had promised in three days, and

explained to him the status of the two week pull- in of my project.

I told him that the condensed time schedule was doable with the

added resources and equipment. I also emphasized all the cost over-

runs that had to be absorbed. Our customers review team could

make it to the design review meeting at the new specied time.

e only open issue was early payment by our customer for phase 1.

I told him that the customers project manager was working on this

issue diligently and would have an answer to us in a week. I asked

my company president not to disturb the boat and go to higher- ups

in our customers company for this early payment issue. I was more

than optimistic that the customers project manager would come

through after dealing with their inner procedures and politics.

My teams work stress level went up a couple of notches for the

next six weeks. e customers project manager came back with

good news in a week that they would be able to pay us two weeks

8

Project ManageMent case studIes

earlier, if we met all the phase 1 requirements. All of us, especially

our company president, were very happy to hear this news from

our customer. We all worked hard to make the condensed project

schedule. We sent out the released structural interface drawings

to our customer in four weeks. ese drawings were approved

by them before the design review meeting. We had our internal

design review a week earlier than the formal one. We made sure

that our design conformed to all customer specications. After

some minor modications we were ready for our customer except

the control panel software code.

e control panel software code was similar to an earlier one

we designed for another customer. e code needed several modi-

cations, but my teams electrical engineer would not have enough

time to complete, test, and release it in time for the design review

meeting. We decided to present the earlier version of the code

and the required modications to the customer. We were going to

propose to the customer releasing the code in two weeks after the

design review. is would not have aected any of the manufac-

turing processes, which were the next phase of the project.

e two- day design review meeting with the customer went

well. We had the meetings start at 8 a.m. in the morning and con-

clude at 2 p.m. in the afternoon considering our guests jet-lagged

condition. I did not forget to put the U.S. and Finnish ags in

the middle of the conference table. We had lunch brought in dur-

ing the meetings. We provided our guests with private oces

with Internet connections, printers, and phones as they needed.

e customers review team was very understanding to grant us

a waiver from phase 1 deliverables and a two- week extension for

the release of the control panel software code. Overall the design

review meetings went well. We accepted all of the minor modi-

cations the customer requested. Toward the end of the meeting,

I arranged for our company president to come into the conference

room and give a short appreciation and thank you talk to our cus-

tomers team and to my team.

At the end of the second day, I provided our customers team

with the released meeting minutes and action items list. Afterward,

the customers team and my whole team went out to a Mexican

dinner to celebrate the achievement of a crucial milestone in our

project two weeks early. Our Finnish guests enjoyed dierent a-

vored quesadillas and margaritas. e customers team left town

with great satisfaction. Our company president was very happy.

I was very proud of my project team.

9

case studIes In stakeholder ManageMent

LESSONS LEARNED FROM THIS PROJECT EVENT

Your companys nancial stability can change suddenly

and can aect your ongoing project unexpectedly.

How to change your project goals in a team environment.

How to approach your customer for an unusual request.

Utilizing other company resources eciently when you

are in a bind.

Case1.2: Protecting Intellectual Property during

a Technology Transfer to a Japanese Company

My computer component company made a nancial agreement

with a Japanese company. As a result of this agreement we had to

develop and transfer an advanced magnetic recording head tech-

nology along with its wafer manufacturing processes to them. I

was assigned as the project manager for this intellectual property

transfer to Japan. e Japanese company decided to send, as part

of the agreement, to our wafer factory in California four Japanese

engineers for a year to learn all details of wafer processes and our

design specications for intellectual property transfer.

I had to get ready for my guests in four weeks. ey were going

to come to the United States with their families. First, I arranged

for them to stay in our company apartments, which were within

walking distance to our factory. Second, I had to be very careful

about the intellectual property transfer. We had many custom-

ers products going through our production facilities. Every one of

our customers was a erce competitor of this Japanese company.

We were only transferring a portion of my companys intellectual

property to them. I had to set up guidelines for restricted areas in

our plant. I had to conne these four engineers to certain sections

of our plant. I had to identify the people that they could talk to or

ask questions of. I had to make sure that they did not cross paths

with our other customers when our other customers were visiting

us. While preparing all the restrictions and precautions, I had

to make sure that I was not violating any parts of the agreement

between my company and the Japanese company.

Most importantly, I had to train all of the 3,000 people in our

plant as to what to do and what to say when they encountered

these Japanese engineers.

I had to move some of our engineers and create an isolated

working space with four cubicles and a conference room for my

Japanese guests. I also moved my oce into this isolated section.

10

Project ManageMent case studIes

We had special telephone and Internet connections for them that

were separate from the company ones. Japanese engineers could

come to work from 8 a.m. to 5 p.m., Monday through Friday.

ey could not enter the plant during the swing and night shifts

and during the weekends. If they had an inquiry or a question,

they had to ask me rst. I had to connect them with the right

people from my company for the answers.

Training of my people was the hardest. I had to do the training in

all shifts. I prepared a PowerPoint presentation that lasted 20 min-

utes. I presented the highlights of our agreement with the Japanese

customer. I presented the names and the titles of the Japanese engi-

neers that were visiting us. I outlined the isolated working space for

them and when they were supposed to be in our plant. I detailed the

dos and donts to protect our companys intellectual property. We

were not to discuss anything except the advanced magnetic recording

head technology along with its wafer manufacturing processes that

was in our agreement. We were not to discuss with them any of our

other customers and their products. We were not to discuss with them

any of our other advanced magnetic recording head technologies.

e most crucial part of my training presentation was about

the interface rules. I had to bring the Japanese engineer(s) with

their questions to a particular person in our factory. Especially in

our clean room wafer fabrication processes and in testing these

interface rules were important. I did not want the Japanese engi-

neers to observe our other proprietary processes. I trained every-

one in our plant in four weeks including our president and our

vice presidents.

e Japanese engineers came with their families and spent a

very productive year with us. ey obeyed all the rules and regu-

lations I outlined for them. My company people were also very

cautious and obedient to our intellectual property protection

guidelines. I took them out to long sushi lunches and town tours

when we had an important customer visit to our plant. I did not

want to take the chance of them running into each other.

I became very good friends with these Japanese engineers. ey

taught me one Japanese word every day. So I learned close to 250

Japanese words and expressions from them. I invited them with

their families to barbecue dinners at my house. I kept in touch

with them many years after we all went our own ways in our lives.

Detailed preparations and training of my people for my com-

panys intellectual property transfer to this Japanese company were

11

case studIes In stakeholder ManageMent

the key elements for success. Even the Japanese company execu-

tives praised my project management guidelines to my superiors.

ey were very kind to send me a stainless steel water cooler as an

appreciation gift for the work I did with their team.

LESSONS LEARNED FROM THIS PROJECT EVENT

Intellectual property transfer within certain agreed upon

boundaries can be very tricky between two companies.

When a competitors engineers visit your company for

intellectual property transfer, the whole plant has to be

ready to protect your technology.

Interaction rules and guidelines with a competitors engi-

neers have to be fully detailed and explained to everyone

in your company.

Respect and good treatment of your competitors engi-

neers always pays o in the long run.

Case1.3: Corporate Division Shutdown

I was a project manager for a data communication chip design

company during the dot- com boom and bust periods. e dot- com

bubble grew due to speculative investing for Internet- based com-

panies, but these companies failed to turn a prot in a timely fash-

ion. From 2000 to 2002, the Nasdaq Index lost about 80% of its

value due to a rapid burst in the dot- com bubble. One day in 2001

we got the bad news that our corporate was going to close down

our companys operations. I was right in the middle of a data com-

munication chip design project. My customer was U.S. based. I

had a group of ve engineers working on my team. We all got very

excited. e rumor mill was circulating at a very fast pace. My

teams work eciency immediately dropped. Everyone started to

worry about his or her future rather than focusing on their tasks.

is chaotic situation lasted about 10days. en a group of

executives from corporate came to our facilities and they nalized

the details of our companys shutdown with our president. ey

gathered us in a large conference room and explained to us how

the company shutdown was going to take place. It was a phase-

out process. e rst week they laid o 50% of the total work-

force. ey gave everyone a compensation package consisting of

outstanding vacation pay and bonuses depending on seniority

and salary level. en they decided to phase out every projects

12

Project ManageMent case studIes

remaining tasks. My project had another three months to go. A

junior engineer from my team was laid o during the rst week of

the phase- out plan. I had four engineers and me to complete the

project in three months.

I gathered my team and went over the remaining tasks one by

one. If we worked eciently without any glitches we were hopeful

to complete the remaining project tasks in three months. I told my

team members that they could spend a reasonable amount of time

during the day to look for their future jobs. I emphasized that I

would allow them to go to interviews during the week as long as

they made up the lost time during o hours. We also decided that

I was going to deal with our customers project manager during

these three months so that my team members did not get dis-

tracted and lose any precious time.

en I called my customers project manager and gave him

the bad news about our companys closure. I assured him that his

project was going to be completed in three months with a nal

acceptance review meeting before my team members and I left

the company. I skipped the news about my junior engineers early

departure from my team. My customers project manager had

high condence in me because I always delivered my commit-

ments on time and with highest quality to him.

My team and I worked very closely during those nal three

months. Our oces were like a ghost town. All the cubicles were

emptied out. During the phase- out process, we were saying good-

byes to several colleagues every week. I had lunch with my team

members daily during those three months. During lunch we only

discussed everyones future plans. We never discussed the project

tasks. We became a very close- knit bunch during those 13weeks.

I wrote outstanding recommendations for all my team members.

We had to work a couple of weekends to complete all the remain-

ing tasks. During the nal week we had our internal acceptance

review meeting. ere were a couple of tasks that needed to be

polished and retested. We had to extend our project one more

week for the customers nal acceptance review.

I discussed my projects status with the company president. I

told him that we needed an extra week to complete the project.

He told me that he did not have any funds to cover my teams

expenses for an extra week. During our team luncheon, I dis-

cussed the bind we were in with my team members. We all agreed

to work another week without any compensation and complete

13

case studIes In stakeholder ManageMent

the job. I immediately called my customers project manager and

explained our situation. I told him that we would be ready the

following week for the nal acceptance review. I told him that

my team and I were working pro bono for a week to complete the

project. He was very appreciative of our sacrices.

e projects nal acceptance review went without a hitch. Our

customer accepted the data communication chip design without

any change request. Afterward our customers project manager

took my team and me out to dinner to celebrate. Working as a very

close- knit team during these hard times paid o well. We com-

pleted our project in 14weeks. We came out of the dot- com bust

with ying colors. My team members and I found jobs at other

companies and immediately switched over to our new positions.

LESSONS LEARNED FROM THIS PROJECT EVENT

Downsizing and/ or shutting down a division of a corpo-

ration is very painful.

Keeping up your project teams morale during dicult

times is a challenge.

A close- knit project team can overcome tough hurdles in

chaotic times.

Your customer always comes rst.

Case1.4: Airline Travel Fares Increased

I was the project manager to set up a volume production factory in

Malaysia for our U.S.-based corporation. I had a team of design,

manufacturing, quality, and test engineers in the United States

and their counterparts in Malaysia. My engineers continually

traveled back and forth from the United States to Malaysia to

train and help the Malaysian engineers during the start-up period.

During the initial months of the project, airline fares were very

reasonable and I allowed my engineers to travel business class to

Malaysia during their long 18-hour ight. Business class air travel

gave them a fresh start at their destinations. ey had a minimum

amount of jet lag. ey also accumulated a lot of airline miles

for their personal use. My travel budget was about $200,000 per

year. My travel budget allowed me to send about 40 engineers per

year to Malaysia. I also brought several Malaysian engineers to

the United States for training. We formed a kind of air corridor

between our headquarters in the United States and our plant in

14

Project ManageMent case studIes

Malaysia. We had an in- house travel agent who took care of our

travel needs. All of a sudden due to uncontrollable world events,

the price of jet fuel started to increase. Airlines started to add sur-

charges on airfares. I started to overrun my travel budget.

My airline travel budget was going to almost double. I had

to do something. I could not cut the number of trips made to

Malaysia. e Malaysians needed hand holding and advice dur-

ing the critical start-up period. I had a long meeting with my

team. After several strong objections, I made them agree to y in

economy class. ey were free to upgrade to business class with

their own miles. It was not easy for my team members to buy into

ying economy class for 18 hours. ere were several other good

suggestions made during our meeting. We agreed to y dur-

ing weekdays and to avoid holiday times such as anksgiving,

Christmas, New Year, and spring breaks. One engineer sug-

gested that our companys travel agent should secure a set of

airline open tickets from airline promotions and sales events. We

would use these open tickets when needed. I took on the assign-

ment of negotiating the open ticket suggestion with our compa-

nys travel agent. Another suggestion was to station some of my

teams engineers in Malaysia for a longer period of time instead

of shuttling them back and forth every two or three weeks.

Another suggestion was to increase and to emphasize videocon-

ferencing meetings with our counterparts in Malaysia. I tried to

implement all these suggestions. Most of these suggestions did

not apply during emergency assignments. During an emergency

situation, my engineers or me hopped on a plane immediately

and ew to Malaysia. ese were the budget breaking trips. e

airline fares for these emergency trips were doubled or tripled.

We had several of these emergency trips every year.

When I started the Malaysian project, fuel costs were about

10% of the airline operating costs. In two years, fuel costs edged

up to about 35% of the airline operating costs. Airlines were pass-

ing on these operational cost increases to their customers. Air

travel cost increases was reected not only in ticket fares, but also

in luggage fees, extra leg room fees, and so on. I went several

times to my upper management to ask for an increase in my travel

budget. I explained to them the steps we were taking to lower our

travel expenses. I pleaded with them for a travel budget increase.

Every time I was rejected. ey emphasized that I should cut

down on travel and keep my travel budget as it was.

15

case studIes In stakeholder ManageMent

With all the cautionary steps we took, I was still over my travel

budget at the end of the project. When I presented my nal cost

performance report to my upper management, I separated the

travel expenses budget from the rest of my project budget. My

cost performance index for the travel budget was well below one.

However, my cost performance index for the project budget,

excluding the travel budget, was a little over one. My team and I

did okay in our projects cost and schedule performances, except

the travel cost dilemma. In the end, my upper management was

very sympathetic about my travel budget cost overrun. ey appre-

ciated all the precautions we took to keep the travel costs down.

LESSONS LEARNED FROM THIS PROJECT EVENT

A projects budget can be easily overrun by unexpected

events.

A team discussion to solve a nagging project issue always

brings about good solutions.

Detailed and logical project budget presentations to

upper management can turn things around in your favor.

Case1.5: Quality Assurance (QA) Department Undergoing

a Major Overhaul

My project teams consisted of members from dierent depart-

ments in the organization. Every member reported to their par-

ticular departments manager and reported to me on a dotted line

basis. I had no control of their performance reviews, promotions,

salary increases, training, and personal issues. I always tried to

help them in these areas. I made sure that their managers got my

fair assessment and evaluation input in these areas in a timely

fashion. In my reviews of each team member, I covered team play,

customer relations, integrity, quality of work, reliability, stress

management, ambition, attitude, attendance, communication

skills, knowledge, and training and improvement needs.

During the manufacturing phase of an advanced safety vehi-

cle project, I had two quality engineers on my team. ey were

responsible for receiving inspection of raw materials and subcom-

ponents for the vehicle, for inspection of every weld on the vehi-

cle, and inspection of every critical parameter on the vehicle. One

day I came to work and learned that the manager of the quality

department was let go due to some disagreements with the upper

management. at same day, I learned that two quality engineers

16

Project ManageMent case studIes

on my team who reported to the departed manager also gave

notice and quit by taking their two- week vacations. e departed

manager and two quality engineers had a very good and loyal

camaraderie. I was suddenly without two quality engineers. I had

to ll the quality engineering gap fast because the manufacturing

of 10 vehicles was proceeding in full swing.

I went and discussed the quality engineering issue with my

management and my human resources group. One remaining

quality engineer was transferred to another group and she was

not available for my project. She was fresh out of college and she

did not have any experience in welding inspections. Our whole

quality department was gone in a ash. I had to go outside and

nd other help in quality engineering. Hiring good engineers

always took time. Finding experienced engineers was more time

consuming. My only option was to go the consultants way. My

human resources department and I started to screen quality engi-

neering consultants. We found a good consulting rm which was

120miles away from our manufacturing operations. We inter-

viewed them and agreed on hourly rates. My expenses for two

consulting quality engineers were going to double. I had to get

the okay from my management for an emergency budget increase.

I called a quick meeting with my management and outlined the

cost of the two consultants to my project. I explained to my man-

agement all the tasks the two quality engineers did for my project.

Two quality engineers put in 50 to 60 hours each a week to com-

plete my projects quality requirements. After an hour of bickering

about signing up only one consultant instead of two, my manage-

ment gave in and agreed with my two consultants proposal. Our

human resources and purchasing departments came together and

signed a contract with the consulting rm in two days. e con-

sulting rm assigned two of their senior quality engineers to my

project. e consulting engineers stayed in a motel close to our

facilities on our nickel during the week. ey each put in 40 hours

per week. My quality engineering budget went up by almost 100%

during the next nine months.

I also had to micromanage both consultants. I had to indoctri-

nate them to our way of reporting and to our customers contract

requirements. ey got acclimated fast and contributed heavily to

my project.

It took my management one year to set up a new and stable

quality department from scratch. I had to do whatever it took to

17

case studIes In stakeholder ManageMent

complete my projects manufacturing phase on time within my

customers specications.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to live peacefully and

eectively with our team members who are not our

direct reports.

Unexpected events can happen in all company depart-

ments during the execution of your project, which are

beyond your control.

You have to stand your ground with your upper manage-

ment in order to get the best solution for your project.

Case1.6: Internal Project Direction

Disk drive magnetic head assemblies needed very precise align-

ment of their components. In volume production alignment of

components was being performed by skilled operators under high-

powered microscopes using precision tooling. Skilled labor costs

were increasing and the sale price of the magnetic head assemblies

was decreasing. It was a very competitive and fast- paced industry.

e only way to get around the skyrocketing labor cost issue in

the United States forced my company to move our magnetic head

assembly operations to South Korea and to Malaysia. To set up

oshore operations was a tough decision by our board of directors.

e motto in the computer industry in the 1980s was to emigrate

or to evaporate.

My company was very successful in their operations in South

Korea and in Malaysia. I was heavily involved in setting up our

Malaysian plants operations. I lived there for six months to moni-

tor, spearhead, and train our new Malaysian engineering group.

However, at the same time the magnetic recording heads were

getting smaller and component alignment requirements were get-

ting tighter and tighter. Our alignment process capabilities were

coming to a limit with skilled operators under high- powered

microscopes using precision tooling.

e next step was to implement assembly processes using auto-

mation. Handling of small components delicately and aligning them

to specications of 0.0001 of an inch in volume production could

be done by microrobots in an automated assembly module. is was

a new concept for our volume production assembly lines. We were

going to load components at one end of the automated assembly

18

Project ManageMent case studIes

module and unload an assembled magnetic head at the other end. If

successful, we could reduce our assembly labor force quite a bit and

tighten our alignment process capability by twofold. Also an auto-

mated assembly module would give us a very favorable edge in the

eyes of our customers. e executive vice president of engineering

in our company was in favor of this futuristic automated assembly

system, but the initial project cost was a major hurdle. erefore,

the company president and our board were against it.

ere was another group of manufacturing engineers in our

company who favored a semiautomated approach to our alignment

processes. In this approach, a microrobot was going to handle the

components, but again a skilled operator was going to perform

the alignment operation under a high- powered microscope. is

semiautomated alignment process was cheaper to implement, but

it did not reduce our assembly labor force and it did not improve

our alignment process capability. is semiautomated alignment

process improved our throughput and reduced the amount of

damaged components.

e executive vice president of engineering gave me the task of

putting together an extensive feasibility study in three months in

order to give direction to our magnetic head manufacturing pro-

cesses for the next generation of our products. I chose two senior

manufacturing engineers for my feasibility study team. First, three

of us put together detailed system specications for an automated

assembly module and for a semiautomated assembly module. An

important characteristic of both types of modules was exibility and

programmability from one product to another in a short time. en

we sourced three potential automation houses in the United States

that were experienced in handling delicate micro components with

robots. We visited them several times and received bids from them

per our specications. We chose an automation house in the Boston

area as the leading candidate, if our board of directors would approve

along with the automated or semiautomated assembly project.

We compared three dierent assembly systems with their

advantages, disadvantages, and investment payback periods in

three dierent countries, namely, the United States, Malaysia,

and South Korea. We performed sensitivity analyses to risk fac-

tors such as project delays, personnel training, and spare parts.

e whole feasibility report ended up being close to 300 pages.

en we prepared a ve- page executive summary for the whole

report. e report had to go through several review phases before

being presented to our board of directors. We rst presented

19

case studIes In stakeholder ManageMent

the report to our manufacturing managers in the United States,

Malaysia, and South Korea. en we made a presentation to the

group of manufacturing engineers in our company who favored a

semiautomated approach to our alignment processes. All of them

had constructive criticism and good input to improve our feasi-

bility report. We modied our report accordingly and made our

nal presentation to our executive vice president of engineering.

He liked the report as it was and praised our very detailed and

methodical approach and timely completion of the project. He

told us to be ready to present it to our board of directors during

the boards next meeting.

I made a half- hour presentation to my companys board of

directors about three assembly options in three countries that

we studied. e manual assembly line in the United States was

our baseline for comparative analyses. Board members were only

interested in investments payback periods and their eects on

our cash ow projections. ey did not ask one question regard-

ing technical aspects of the automated and the semiautomated

projects. I was amazed. At the end of the meeting, we got the

automated assembly project approved unanimously for our

Malaysian plant. Our executive vice president of engineering

was very happy with the result. He took my team out to lunch

and congratulated me and my team members for a job well done.

Internal projects in a company can have very competitive direc-

tions. To nd the right project direction for the company might

require a detailed prestudy. I have experienced several projects

ending up on the shelf and costing bundles because of rushed and

personally favored executive decisions.

LESSONS LEARNED FROM THIS PROJECT EVENT

ere are several dierent ways to approach improve-

ment projects for the future of a company.

ere are always conicting views and passions for

improvement projects within a company.

Decisions for a companys future projects should be made

by relying on sound data and good analysis instead of

shooting from the hip.

Case1.7: Upper Management Stability during a Project

Stability in the upper management of a company aects smooth

progress of a project tremendously. Personnel and responsibility

20

Project ManageMent case studIes

changes in upper management during the execution of a project

can cause ripple eects and sometimes tsunami eects to your

project. It is possible to shield your project from these eects to a

certain extent, but in most cases your project gets hurt too.

A challenging case of upper management shue occurred dur-

ing the execution of an internal product development project that

was under my direction. During the execution phase of my devel-

opment project, the board of directors of our company red our

president and brought in a new one who was hijacked from a well-

respected technology company. e new president brought in a

dozen of his colleagues from the computer industry in order to

pursue his vision of our company. Some of the new arrivals were

positioned into upper management, especially into the engineer-

ing divisions. Others were positioned into the research and devel-

opment group. Two new senior scientists joined my product

development group. ese scientists were good buddies with the

new president. ey had worked together more than a decade.

I presented my projects mission, team, and status to the new

management. ey all had numerous inputs to my projects mis-

sion and schedule. ey completely changed the direction of my

project with new target completion dates. My project was turned

topsy- turvy by the new upper management. All the changes were

approved by the new president without any hesitation. He had

complete condence in his new upper management team. I had

six engineers working for me on my team. With the addition of

two senior scientists, my team expanded to eight people. All of a

sudden the morale of my six engineers went downhill. Everything

we had done for a year before these changes occurred was thrown

out the window.

First, I had a team meeting with the old engineers on my team.

We discussed what we had accomplished and what we had to do

under the new upper management direction. I had to convince

them one by one that we did very well in our product develop-

ment. e new product development direction was not their fail-

ure, but it was a new outlook for the future of our company and

to our competition. Also, I emphasized that we had to be open-

minded and welcome two new members of our team and make

them feel at home in their new environment.

As a project manager I had to start a brand new project with

a new mission and new deadlines. On top of it all, I had to

blend the two new senior scientists into my team and make sure

that there were no animosities between the old-timers and the

21

case studIes In stakeholder ManageMent

newcomers. I had to accept all proposed changes to my project.

ese were the new bosses. We could not continue with our

old ways. We had to go along with the new leaders. I had an

extended team meeting to brainstorm our new project, to dis-

cuss new tasks and team members responsibilities. During the

meeting, I had to carefully bring the two new senior scientists

into our team atmosphere. I had to make them realize that I was

the team leader and they had to execute tasks that were assigned

to them by me in a time frame that was on our schedule. Most

importantly they had to coordinate with other team members

very closely. ey were good buddies with our new president,

but they had to realize that their rst priority was my project.

e new project started well. After a couple of weeks, the two new

senior scientists on my team started to deviate from their task objec-

tives and specications without notifying me. Evidently, they were

being redirected by our new president. ese ripples also aected my

other six team members and they started complaining to me about

sudden changes in the projects direction. I had to correct this dishar-

monious situation immediately. I made an appointment directly with

the new president and explained to him politely the issues I was hav-

ing in managing my new product development project eectively. He

apparently was going out to lunch weekly with the two new senior

engineers on my team. ey were discussing the status of my project

and he was making some suggestions on the spot without realizing

his suggestions eects on the whole execution of the project. We

nally agreed that if he had any new suggestions regarding my proj-

ect, he would e- mail me rst. After my assessment of the impact of

his suggestions on my projects schedule and cost, I would inform

him the consequences before making a nal decision to my projects

modied direction and specications.

Upper management changes in a company can positively or

negatively impact internal project directions, project teams, man-

agement styles, and project reporting styles. As project managers,

we have to deal cleverly and in a timely manner with the changing

world around us.

LESSONS LEARNED FROM THIS PROJECT EVENT

Stability in your upper management helps in smooth

sailing of your project.

A change in the upper management of your company

always brings new ideas and new management styles that

can aect your project.

22

Project ManageMent case studIes

As project managers, we have to mold our project team

members into our new managements styles.

As project managers, we have to have open minds in

dealing with our new upper managements directives,

which aect our projects.

Case1.8: Help from the Legal Department

e legal department of a company can help a project manager a

lot in detailing a projects contract agreement conditions. Some

conditions might contradict each other. Others might be written

in a very complicated legal language. Some conditions have to

be renegotiated with the customers legal department. A contract

manager has to fully understand at the beginning of the project

all contract agreement conditions for delays in deliveries, patents,

copyrights, trademarks, force majeure, subcontracting rules, and

governing laws and arbitration. In addition to understanding all

contract agreement conditions, he has to relay them to his team

members in laymans terms. e whole project team has to real-

ize what happens if there is a delay in deliverables or if there is

an invention during the execution of the project. If some of these

contract agreement conditions are overlooked, they might come

back to bite you during the execution of a project or at the end

of the project and lead to irrecoverable damage to your company.

I had a very interesting case regarding delivery of nal docu-

ments and drawings at the end of a project. I delivered my projects

hardware on time, but I was delayed six weeks in delivering nal

documents and drawings to my customer. Delays in nal docu-

ments and drawings deliveries were mainly caused by delays in

my customers timely approval of preliminary versions. Also, I lost

two of my engineers to other projects during the winding down

period of my project. My contract agreement specied a penalty

of 0.1% of total contract value for each week of delay in delivery of

nal documents and drawings. Six weeks of delay added up to a

handsome penalty to my company.

I discussed this delay issue with my customers project manager

on the phone every week. He told me not to worry about the pen-

alty clause regarding delivery of nal documents and drawings.

He knew that his teams delays in their responses were a major

part of the blame. I delivered all nal deliverables six weeks late

and the project came to a close. More than a month passed and

I got a call from our chief nancial ocer. He told me that my

23

case studIes In stakeholder ManageMent

company was being penalized 0.6% of total contract value due

to delays in delivering nal documents and drawings to my cus-

tomer. is was quite a shock to me. I explained the nal docu-

ments and drawings delivery issues to our chief nancial ocer. I

emphasized the lackadaisical comments of my customers project

manager. I told him that I had all of the recorded delivery dates

to our customer for every document and drawing. I also had all

of the receipt dates and comments from our customer to me for

every document and drawing. We agreed that we should not be

penalized for this delay. We had every right to appeal the penalty.

en we called my customers project manager to understand

the reasons behind the penalty. My customers project manager

insisted that he had nothing to do with the penalty. Higher- ups

in his company decided to apply the penalty clause because of the

six- week delay in delivering nal documents and drawings. My

customers project manager apologized for misleading me and he

stressed that he could do nothing to reverse the penalty.

en our chief nancial ocer and I agreed to bring our legal

department into the picture to pursue our rightful case. Our law-

yers talked to their lawyers. Our presidents were also involved as

they too discussed the penalty case. My customer was not budg-

ing regarding the penalty at all. We decided to take the case to

the next level, namely to arbitration, because of the stiness of

the penalty and because we felt that we had the upper hand to

win the case. According to the contract agreement conditions,

disputes between parties arising in connection with or related

to my project had to be settled by nal and binding arbitration

under the rules of arbitration of the International Chamber of

Commerce in Helsinki, Finland. ankfully, the arbitration lan-

guage was English.

I briefed one of our lawyers with all details of the case. I pro-

vided him with all recorded delivery and receipt dates of docu-

ments and drawings. Our lawyer applied for the arbitration. He

had to go to Helsinki for the hearing. After a full day of arbitra-

tion sessions, the arbitrators decided to drop the penalty. Later

our lawyer told me that the reason we won the case was due to my

detailed delivery and receipt dates of documents and drawings. I

made the mistake of not getting the nothing to worry about the

penalty clause comments in writing from my customers project

manager. Our legal department came to my rescue. I was very

appreciative of our legal departments eorts. We celebrated our

victory over a nice dinner when our lawyer got back from Helsinki.

24

Project ManageMent case studIes

LESSONS LEARNED FROM THIS PROJECT EVENT

A companys legal department is a crucial advisor and a

lifesaver to a project manager.

Some conicts between you and your customer or

between you and your subcontractors have to be resolved

with the help of your legal department.

Keeping accurate records of communication and of

deliveries between you and your customer and between

you and your subcontractors is a must.

In a project execution, verbal promises and directives

are worthless.

Case1.9: Salary and Compensation Variations

in a Global Team Environment

I did engineering, engineering management, and engineering

project management for over 46years. I loved my engineering

challenges. I stayed in my eld and did not regret a bit in choos-

ing this very fullling eld early on in my life. e majority of

my engineering colleagues were also satised with their career

choices. Despite long work hours, every engineer I knew wanted

to grow and wanted to be challenged in his or her work. is was

the engineering environment that I experienced in the United

States. As I got to know and to work with engineers from other

countries, professional satisfaction levels degraded quite a bit.

e motivation levels of engineers dropped due to lower salary

and compensation packages in other countries. For example,

engineers in Europe and in Japan are compensated about 70% of

what U.S. engineers get. Salary and compensation packages get

worse, about 20% of those in the United States, in countries like

Malaysia, India, and China. As engineering project teams and

workforces get more and more integrated globally, engineering

salary and compensation packages are ratcheting up in develop-

ing countries.

When Malaysian engineers were part of my volume produc-

tion setup team, I always reminded my U.S. engineers not to

discuss salaries, compensation packages, raises, or bonuses with

their Malaysian counterparts. Money issues were very touchy sub-

jects in a global project environment. I made many recommenda-

tions for salary increases and for bonuses to the supervisors of

Malaysian engineers who were on my team without any success.

e main mission of our Malaysian operations general manager

25

case studIes In stakeholder ManageMent

and Malaysian supervisors was to keep costs down. ey did not

value engineering qualications, experience, and work ethics like

we do in the United States. ey were also leaving most engineer-

ing positions unlled in order to keep costs down and thereby

squeezing long work hours from their engineering sta. ere was

a substantial amount of turnover in my Malaysian engineering

workforce. I could not keep a stable engineering environment in

my Malaysian project teams.

I lost a couple of Malaysian engineers right in the middle of a

project due to salary increase disputes. I got them well trained at

the beginning of the project. ey were in the process of becoming

very qualied in their tasks and they were smart and hard workers.

ey learned somehow that their counterparts in the United States

got 10% increases in annual salary reviews and they got nothing.

ey conded in me that they were ready to leave our company

because of unfair annual salary increase and bonus distribution

practices in our Malaysian subsidiary. I pleaded with their super-

visor and with our Malaysian general manager to stop those two

Malaysian engineers from leaving our company. e Malaysian

managers attitude was that there were many unemployed engineers

out there and they could hire them at a much lower salary. Due

to the Malaysian managers stubbornness and short- sightedness, I

wasted all the training time for those two engineers and several of

my projects tasks were set back by two weeks.

Salary and bonus discontent among engineers is increasing in

developing countries. Engineers in these countries are less satis-

ed with their engineering careers and they are ready to jump ship

and/ or change careers in order to improve their lives.

At the other end of the global engineering workforce spec-

trum, there are countries like South Korea and Singapore where

engineering is well respected and well appreciated and therefore

well rewarded. In an internal project team, I had several engi-

neers from our South Korean subsidiary who were working for

me. ey also had unequal pay, about 50% in the 1990s, for equal

work as compared to their U.S. counterparts. eir supervisors

and our general manager in South Korea were more willing to

go along with my annual salary increases and bonus distributions

recommendations. ey valued an engineers training, qualica-

tions, and experience. As South Korea improved their economy at

lightning speed, their engineering salaries and bonuses climbed

up to about 70% in the 2000s as compared to their U.S. counter-

parts. I think a signicant portion of South Koreas economic

Project ManageMent case studIes

success was due to their well- satised, well- appreciated, and hard

working engineering workforce. I had similar good experiences

with Singaporean engineers on my project teams. ey were very

happy and very satised with their careers.

I believe that salary and compensation discussions in a global

team environment should be taboo. As global project managers,

we have to sensitize our team members not to discuss money mat-

ters with our colleagues from other countries.

LESSONS LEARNED FROM THIS PROJECT EVENT

In an international project team environment, work

motivation levels alter quite a bit from country to country.

You have to advise your U.S.-based engineers not to

discuss their compensation packages with engineers in

other countries.

Case1.10: Lessons Learned from Previous Projects

Historical knowledge of projects completed in a company is a

very valuable guide for a global project manager. In particu-

lar, lessons learned from historical projects can shed light and

show the right path to avoid making the same mistake over and

over again. As project managers, during execution of a global

project, we always run into issues with specications, schedules,

budgets, team members, company upper management, cus-

tomers, regulatory agencies, foreign governments, subcontrac-

tors, inspectors, suppliers, and so on. As we get ready to close

out a project, we should compile all the lessons learned from

that project along with actions taken and results achieved in a

report. We should release this report in document control. We

should also present pertinent sections of this report to our team

members, to our upper management, to our customers, and to

our subcontractors.

e lessons learned report for a completed project was a

requirement for a company that I worked for. Reviewing these

reports about a customers previous projects gave me a very

good understanding of what I should be prepared for in deal-

ing with this particular customer. In particular, my customers

unannounced audits of man- hours and materials charged to my

project surprised me a lot. My customers auditors came to our

company unannounced and reviewed our charge records for every

one of their previous projects. As a project manager I had never

27

case studIes In stakeholder ManageMent

experienced unannounced auditor visits before. We had had sev-

eral issues with this company with incorrect charges in the past.

So I started to check our charge records every two weeks and made

the necessary corrections with our accounting department. I was

audited unannounced twice by my customers auditors during the

execution of my project for man- hours and material charges. ey

found everything in order and our accounting department and I

received good pats on the back.

In another oshore oil platform equipment design project, pol-

lution control laws, ordinances, rules, and regulations were very

detailed and complicated. Pollution control involved several gov-

ernment agencies such as the U.S. Department of the Interior,

U.S. Geological Survey, U.S. Army Corps of Engineers, and

the U.S. Coast Guard. I reviewed my companys historical doc-

uments related to similar past projects and discussed pollution

control procedures with seasoned engineers who worked on previ-

ous similar projects. I formulated a very thorough plan to prevent

pollution during the execution of my project. I trained my team

members as to what to do in case of undesirable and uncontrolled

spills and leaks. Every member of my team was very diligent in

pollution prevention while performing his or her task.

Another useful lesson that I learned was in dealing with mate-

rial safety data sheets for chemicals that were used in one of my

projects. My customer paid lots of attention to material safety data

sheets for all chemicals used in my project. From historical infor-

mation, I prepared a list of laboratories certied by my customer

that could issue material safety data sheets. I put together a data

sheet form that was acceptable to my customers project manager.

In my project schedule, I included all dates for when I had to sub-

mit samples to certied laboratories and when material safety data

sheets were due to my customer.

Lessons learned information was crucial for a customers

design review process. What had surprised us during design

review meetings in the past? What kind of issues had we encoun-

tered during meetings? How did we deal with incomplete and

missing information? Did we have any specication clarication

issues? How did we deal with a customers instantaneous add-

ons to the project? One thing I learned was to take a time-out

from the meeting or call for a break, if an unanswerable question

or request popped up. en I huddled with my team in private

and we collectively decided on an answer in a calm environment

before facing my customer with an answer.

28

Project ManageMent case studIes

In another lessons learned case, I found out that a particu-

lar nal inspector always randomly checked torques of several

bolts on equipment being inspected. I asked my manufacturing

manager to go over and verify each bolts torque on every piece

of equipment that was ready for inspection before the inspector

arrived. In the past, this nal inspector also randomly checked

paint thickness on every surface of the equipment. Also, in the

past, there had been several issues with this nal inspector not

signing o our equipment, but at the end of my project we were

ready for him. We inspected every piece of our equipment to be

shipped just as he would have inspected it. We made a couple

of touch- ups and corrections as needed. e nal inspector was

very surprised not to nd any issues with our equipment during

his nal inspection. I was thankful for my companys lessons

learned documents.

LESSONS LEARNED FROM THIS PROJECT EVENT

Do not forget to release your Lessons Learned report

in your document control during the closure phase of

your project.

Present Lessons Learned from your project to your

team members, to your upper management, to your cus-

tomers, and to your subcontractors before interest in your

project fades away.

Case1.11: e Eect of an Outside Consulting Firm

on a Project

In most companies, upper management has a hard time mak-

ing decisions. Ocers of the company procrastinate a lot and

put o important decision making. As project managers, these

kinds of important decision delays can aect our projects and our

performances. We can only write our warning e- mails, prepare

our reports, and have urgent discussions with upper management

with little eect on their decision- making process.

In such a case, I was assigned by our president to prepare a fea-

sibility report to expand our production operations into Europe

and into Southeast Asia. I was given six months to prepare a

detailed report on expanding into certain countries like France

and South Korea. I prepared a long list of questions for their for-

eign investment representatives. I visited all those countries and

I learned in detail their investment incentives such as duty- free

29

case studIes In stakeholder ManageMent

zone rules and requirements, investment loan conditions, foreign

company taxation rules, labor and union laws, wages and salaries,

and so on. I also got lots of help from international subsidiaries

of an investment rm. I prepared a comparative feasibility study

that detailed investment amounts by year and estimated returns

on these investments. I outlined facility needs, equipment, and

personnel requirements. I also listed all risk areas in utilities, in

unions, in training, and so forth. I summarized my report in four

pages for my upper management. I gave the full report with its

summary to four executives in my company one week before the

nal delivery date.

Our president called a meeting with company executives about

expansion of our production operations and asked me to pres-

ent my feasibility report. All of the executives were focused on

amounts and returns on the companys investment. Overall my

presentation went well. ey all praised my report.

ree months passed and there was no word on expansion. I

asked several executives what was going on. ey all replied that

they were in the decision-making process with no denite date in

sight. One day I received a call from my boss informing me that

they had hired a consulting rm to perform a similar feasibility

study to mine. e president and the board of directors wanted a

second opinion before launching into a foreign expansion project.

I was disappointed at my upper managements decision but I had

to live with it.

Four representatives from the consulting rm came to our facili-

ties and settled into four oces for three months. Every one of them

interviewed me almost daily. ey asked me hundreds of questions

about our production equipment, about the countries I visited,

about labor and engineer training requirements in those countries,

and so on. I provided them with all the information they needed.

ey also received lots of input from their subsidiaries in France

and in South Korea. e consulting rm completed their feasibility

report in four months and presented it to my companys executives. I

was not invited to the presentation meeting, but I did receive a copy

of their report from my boss. e consulting rms conclusions were

very similar to mine. My company spent millions of dollars to get a

second opinion from the consulting rm on the foreign expansion

project. My companys executives and our board of directors needed

that assurance from the consulting rm before taking a big step

forward in the foreign expansion project. Finally, after a year and a

half, they made a decision to go ahead with the project.

30

Project ManageMent case studIes

During my career I have seen all types of decision makers

in company executives. Some were high- risk takers, while oth-

ers were very conservative. High- risk takers made fast decisions

which emerged from their gut feelings and from their experi-

ences. Conservative executives took their time to make a deci-

sion. ey consulted many people during the decision- making

process. ey would get several reports compiled about the sub-

ject. Some executives could not even make a decision by them-

selves and would opt for an executive group decision. In our

fast- moving and very competitive business environment, cautious

risk takers are the winners.

LESSONS LEARNED FROM THIS PROJECT EVENT

Some upper management people procrastinate a lot and

put o important decision making.

Some upper management people need extra assurance

from dierent and reliable sources before making impor-

tant decisions.

Case1.12: Japanese Customer Visit to Qualify

Our South Korean Plant for Volume Production

As an American magnetic recording head manufacturing com-

pany, we were successful in getting qualied as a component sup-

plier to a major Japanese disk drive manufacturer. One last hurdle

in this relationship was to get our South Korean magnetic record-

ing head manufacturing plants to be qualied by our Japanese

customer. In my previous visits to our South Korean plants, I

observed bitter antagonism toward the Japanese because of Japans

colonization of Korea during the rst half of the 20th century.

I was afraid that my engineering team in South Korea would not

be able to control themselves during the qualication process and

show their bitterness toward our Japanese customer.

In the beginning of the 20th century, Japan colonized Korea.

Japan established economic and military dominance in Korea.

Japanese rulers forced Koreans to adapt to Japanese cultural and

religious practices. Koreans were forced to change their names to

Japanese ones. Over 50% of arable land was turned over to the

Japanese owners and many Korean landowners became tenant

farmers overnight. All Korean newspapers were shut down. Korean

children were only allowed to have a primary school education.

case studIes In stakeholder ManageMent

All factories were owned by the Japanese. Japanese rulers created

a strict system of colonial mercantilism to exploit Korean raw

materials and Korean manpower for their WorldWarII eorts.

After the Japanese surrender in 1945, the Soviet Union and the

United States agreed to split the Korean peninsula at the 38th

parallel (the demilitarized zone). e southern region of the pen-

insula became a democratic republic called the Republic of Korea

and the northern region became a communist regime called the

Democratic Peoples Republic of Korea.

In order to ease the tensions between my Korean engineering

team and the visiting Japanese qualication team, I decided to go

to Korea rst for two weeks to prepare and to train my Korean

team for our Japanese customers qualication process both psy-

chologically and technically.

I had meetings with my Korean engineering team daily. I

told them that the historical relationship with Japan was bit-

ter. However, South Korea was trying to advance technologi-

cally and catch up to Japan in standard of living. I emphasized

South Koreas national ambitions and asked my team members to

restrain themselves from showing their antagonistic feelings dur-

ing the upcoming qualication. If our Japanese customer qualied

our South Korean plant as a sole source component supplier for

their automated disk drive assembly line that would be a great step

forward for the South Korean economy. All the team members

agreed and were upbeat about the qualication process.

We did three trial qualication runs. I acted as the Japanese

customer during the trial runs. I bombarded them with ques-

tions and inquiries about critical parameters, process controls,

and our historical capabilities at every manufacturing station.

We reviewed and polished all our statistical process controls from

receiving inspection, through every assembly process, to nal

shipment to customer. We reviewed our disposition procedures

for out- of- specication situations. We reviewed our operator

training and production line qualication methods. At the end of

two weeks, my Korean team was ready for our Japanese customer.

During the introductory meeting, I took the oor and praised

my Korean team and gave examples of their accomplishments in

process and in quality control. Our Japanese customer gave us a

list of items that they would like to investigate. We obliged them

in every item that they requested. ey toured our assembly line

during the day shift and also during the night shift. ey asked

32

Project ManageMent case studIes

specic questions of the operators about their tasks. e qualica-

tion process lasted for four days. ere were several minor glitches

here and there, but my team worked very hard to correct them and

found the right answers. My team was also very courteous during

lunches and dinners with our guests.

At the end of the fourth day, the head of the Japanese delega-

tion took the oor and praised our Korean operations. ey found

only one aw in our clean room monitoring control charts. ey

wanted the temperature, humidity, and particle count monitored

every half an hour instead of every two hours. We agreed to their

request. Our Japanese customer qualied our South Korean plant

as the sole source for their magnetic recording head assemblies.

One month after the qualication, we started shipping from

South Korea to Japan a high quantity of magnetic recording head

assemblies directly to their automated disk drive manufacturing

line in a kanban system.

After our Japanese customer left we had a team meeting. I

thanked every member of my South Korean team for their out-

standing eorts during the qualication process. at night I

invited them out to dinner to celebrate their psychological and

technical success. I do not remember how many bottles of soju

were consumed during dinner. Since I do not drink I could not

participate in their drinking ceremony from the same shot glass

that went around the table.

LESSONS LEARNED FROM THIS PROJECT EVENT

In a global project environment, learn the histories of the

countries you are dealing with.

Prepare your project team for sensitive issues between

countries that might negatively aect your project.

Always praise and recognize your project team after a

successful project event.

Case1.13: e Customer Placed a Permanent Observer

in Our Plant and in Our Subcontractors Plant

My company was chosen as the sole source custom component

supplier to a large U.S. computer manufacturer. I had a team of

engineers who worked only for the design and manufacturing of

this custom component. We designed and developed the custom

component in the United States and manufactured it in South

33

case studIes In stakeholder ManageMent

Korea. We also had several key subcontractors for this custom

component in Japan. Our customer was very diligent regard-

ing industrial espionage and protecting their intellectual prop-

erty. ey required us to apply very strict rules and regulations

to protect their customized design and product details. In a fast

developing and very competitive computer industry, intellectual

property protection was top priority.

During the development and qualication of the custom com-

ponent I had to relocate my project team to an isolated location

in our U.S. facilities. ey could not discuss the custom compo-

nent with anyone else outside my team. e custom components

test facility was also separated from other test laboratories. e

customer placed a resident engineer into my group to oversee all

our activities and to make sure that their intellectual properties

were fully protected. e custom component development and

qualication went very well for three months with several minor

glitches. Some engineers left several drawings on their desks at

night, which was not acceptable. All drawings had to go into the

vault at night. One engineer made a copy of a drawing without

getting my and the resident engineers permission. We were ready

for oshore manufacturing. Our facilities in South Korea and our

subcontractor in Japan had to be qualied for volume production

and these facilities and the people working on this project had to

be prepared for intellectual property protection.

Production areas for the custom component both at our sub-

contractor and at our facilities were separated by gray plastic

walls. All engineers and other personnel working on this project

were trained on intellectual property protection rules and guide-

lines. I traveled with the customers team both to Japan and to

South Korea to qualify them for intellectual property protection

procedures. Everything went smoothly during the qualifying

inspection and volume production started on time. e customer

assigned a resident engineer to our plant in South Korea. is

resident engineer also traveled to Japan to check on our subcon-

tractor every fortnight.

After a month into volume production, the resident engi-

neer got very sick from food poisoning in South Korea. He was

taken to a hospital in the city of Chungju. I called my teams

manager in South Korea and asked him to stay with the resident

engineer all the time in the hospital. I asked my teams manager

not to leave the sight of the resident engineer one minute until

34

Project ManageMent case studIes

he got well. e resident engineer did not speak any Korean.

Communication with the hospital personnel was a major issue.

It was my responsibility to take care of him. My teams man-

ager in South Korea stayed with him one week in the hospital.

Apparently, the resident engineer lost lots of uids during his

food poisoning ordeal. He had to gain back his strength and his

body uids before being released from the hospital. He was very

appreciative that we did not leave him alone in his struggle back

to health. Even during his hospital stay, he reviewed and signed

o on engineering change orders and on volume production out-

of- specication lot dispositions.

e resident engineer stayed in our manufacturing facility in

South Korea for a year without any other health issues. He did

not even take a day of vacation during his stay in South Korea. He

was very dedicated to his assignments. His supervisor and I went

to South Korea to visit him several times during his stay there.

His supervisor even gave the resident engineers annual review

to him in South Korea. His supervisor asked me to provide my

input too regarding the resident engineers performance in our

U.S. facilities, in our South Korean facilities, and in our subcon-

tractors facilities. I provided him with very positive input about

the resident engineers performance at our and at our subcontrac-

tors facilities.

e volume production of the custom component lasted for

three years. My customer sent two more resident engineers to

South Korea during this time. eir stay in South Korea went

without any incident. At the end of the project, my customer was

very appreciative of my team for taking good care of their resident

engineers during their stay in South Korea and for doing a superb

job in protecting their intellectual property.

LESSONS LEARNED FROM THIS PROJECT EVENT

Protecting your customers intellectual property during

the execution of a project can require very detailed and

careful planning.

Customers intellectual property protection is more dif-

cult in foreign and competitive countries.

Case1.14: Final Project Evaluation by the Customer

I was heading a data communication chip design project. We had

the nal design review. e chip design software was delivered

35

case studIes In stakeholder ManageMent

to the customer. e customer built it and beta tested it success-

fully. I could never close out the project because the nal proj-

ect evaluation by the customers project manager was missing. I

needed a report card from my customer that identied my teams

performance. My company and I wanted feedback that identi-

ed our good qualities, average qualities, and bad qualities during

the execution of the project so that we could improve continually.

Such a nal project evaluation report covered evaluation of all

team members, our design expertise, our test expertise, commu-

nication with the customer, on- time response, dealing with engi-

neering change notices, and meeting their specication, schedule,

and cost targets.

I nudged the customers project manager for three months

by e- mails and telephone calls after we delivered the nal chip

design software for the nal project evaluation report. He was

always apologetic that he did not have any time and that he had

been given a new assignment to head a new large project for his

company. I told him that I was onto a new project too, but I would

very much like to close out his project. He felt that the project

ended when we delivered the nal version of the chip design soft-

ware. He was not allocating any of his time for my nal proj-

ect evaluation report. So my projects nal evaluation report was

falling through the cracks. I did not want to go to his superi-

ors and antagonize the guy. One day I heard from his secretary

that he would be attending a chip design tools conference in San

Francisco in two weeks.

I went to my managers oce and explained to him the situa-

tion about the stalled nal evaluation report. I asked my manager

if I could attend the conference in San Francisco to evaluate the

advances in chip design tools for my company and also catch up

with our customers project manager to complete the nal evalu-

ation report on the spot. Since the project was completed three

months ago, all of my projects charge numbers were closed. I

was doing this extra work to complete the nal project evalu-

ation report on our overhead account. I told him what the cost

of my three- day trip to the conference would be. My manager

thought about my proposal for a couple of minutes. He said that

he could nance my trip to the conference through his groups

training account. I was very pleased to hear his approval of my

trip. Finally, I was going to get a chance to close out my old

project, which was hanging over my head like Damocles sword.

36

Project ManageMent case studIes

I went to the conference. I was able to catch up with my cus-

tomers project manager during the rst session. I told him about

my persistent mission to nalize the project evaluation report. I

assured him that I would not take more than half an hour of his

time and I would ask the evaluation questions and I would jot

down his answers. He only had to review the nal report, sign,

and date it. He nally agreed to get together with me for coee

the next morning. I was elated to see the light for the nal project

evaluation report at the end of the tunnel.

During the evening, I prepared all of the project evaluation

questions that I was going to ask him. In our company, we had a

standard nal project evaluation form. I expanded on it. e next

morning we met at Starbucks at the conference center. I treated

him to a coee of his choice. I went over every evaluation ques-

tion one by one, got the response of the customers project man-

ager, and jotted the summary of his response on the evaluation

form. e whole process took a little over 45 minutes. He reviewed

the summarized report, signed, and dated it. His evaluation of

the project was very favorable. He had several concerns about my

project team. He mentioned that my team was composed of too

many novice engineers and not enough seasoned ones. He rec-

ommended that our project teams should be more balanced in

experience for future projects. His second important criticism was

about my companys high overhead costs. My company was losing

its competitive edge with high overhead costs. He advised that we

should lower our overhead costs at least by 20%, if we wanted to

win other projects from his company. ese were two very crucial

inputs from my customer. I thanked him for his time and for his

honest evaluation of our project. I assured him that I would take

his recommendations to my companys president and correct them

to win his next contract in chip design.

When I got back, I made an appointment with the company

president and went over the nal project evaluation report. He

thanked me for working hard to obtain constructive input from

our customer. He was aware of our companys high overhead

costs. He assured me that steps were being taken to lower them.

He promised to distribute his manpower experience more evenly

for the future projects.

e nal project evaluation report by the customer can be hard

to get. Sometimes it can be a pain in the neck to obtain it for a

project manager. If it is done face- to- face with the customer, you

can get good and honest advice for improvement.

37

case studIes In stakeholder ManageMent

LESSONS LEARNED FROM THIS PROJECT EVENT

During the closure phase of your project, do not forget

to get the nal project evaluation report from your cus-

tomers project manager.

Final project evaluation reports always fall through

cracks as your customers project manager and you go on

to new assignments.

Do all you can to catch up with your customers project

manager in order to complete the nal project evalua-

tion report.

Input and comments from your customers project man-

ager are very important guidelines for your future projects.

Case1.15: Filtering Information

I was the project manager for supplying all the U.S. manufac-

tured wafer fabrication equipment for a Japanese high technol-

ogy company. One of the high- end pieces of equipment that my

customer was sourcing in the United States was the ion milling

machine. e subcontractor for ion milling machines was located

in Virginia. My customer ordered four ion milling machines

for their new wafer fabrication plant in Malaysia. I was heav-

ily involved in putting together specications and shipment and

delivery requirements for the ion milling machines.

I visited the ion milling machine subcontractor several times

during the course of the project with and without my Japanese

customers representatives joining me. e project was scheduled

to complete in 10months. I was on the phone ve days a week

with my subcontractors project manager discussing the status of

my project. I updated my Japanese customers project manager

weekly on the progress made on the construction of ion mill-

ing machines.

e ion milling machine subcontractor built the best ones

in the world at that time. While they were building my four

standard ion milling machines, they had a large order to build

20 advanced ion milling machines from a very important cus-

tomer. Everything they were doing for their important customer

in their plant was blocked inside temporary plastic walls so that

no one else could see the advanced ion milling machines that were

being built there. Whenever I chatted with their engineers about

their advanced product, their engineers were mum on the details.

ey only mentioned that these advanced ion milling machines

38

Project ManageMent case studIes

had a 10-nanometer accuracy of uniform material removal from

the surface of a 6-inch wafer.

I had to manage the communication with my Japanese cus-

tomer appropriately without getting them excited while keeping

their trust and respect in me and in our subcontractor at the high-

est level. I did not report to my Japanese customer every little

detail of the project. I gave them a weekly status summary of the

project and a weekly updated project schedule. ere were sev-

eral ups and downs every day regarding the ion milling machines

construction. Most of the down issues were solved within at most

two weeks. ese minute details were between me and my sub-

contractors project manager. Some delays crept into my proj-

ect due to the subcontractors priority to his large advanced ion

milling machines order. I immediately hopped on a plane from

California to Virginia and showed myself at the door of my sub-

contractor and solved the project delay issues and other nagging

issues face- to- face with him. We always found a way to catch up

to the schedule by authorizing some overtime or by nding an

outside machine shop that could build a component faster. I had

to keep my credibility with my customer intact. By monitoring

my subcontractor very closely and by not disturbing my customer,

we completed the project on time, but we ran 5% over budget due

to several overtime authorizations. My customer was very happy

with the results.

Another issue was with my customer. My customers project

manager insisted that we perform a long- term capability study on

all ion milling machines before they left the subcontractors facil-

ity. However, the contract specied a short- term capability study

requirement for all four machines before delivery. A long- term

capability study meant taking a lot more data while running the

machines. is would have delayed the shipments by at least two

weeks and cost my subcontractor an extra 160 man- hours of work.

I emphasized to my customers project manager what our contract

specied. I convinced him that the long- term capability studies

should be performed at his factory after receiving the ion milling

machines. After several discussions, he nally agreed with me. I

did not even mention this extra work request from our customer

to my subcontractor. My subcontractor was overstretched with

respect to manpower. I had to protect him from our customers

extra requirements.

Communicating ltered information is the backbone of a proj-

ects control structure. How much information to pass on and how

39

case studIes In stakeholder ManageMent

much you want to disturb the cart are crucial factors during the

life of a project. If every little detail regarding your project goes

up to your chief executive ocer or goes to your customer, you

are mismanaging your project. You have to lter out the ripples

in your communicated information. At the same time you have

to realize what information and when to inform your higher- ups

and/ or your customer without any delay.

A similar kind of information ltering goes both ways. If you

receive some negative information regarding your customer, do

not immediately spill it to your team members. Your customer

might be going bankrupt. ey might be shutting down your proj-

ect. ey might be changing project specications. First, absorb

the information yourself. Validate the information, understand its

details, and weigh eects of the information on your team mem-

bers, and then announce it as needed.

A similar kind of information ltering should happen inter-

nally. If you hear from your boss that a layo is going to happen

in two weeks, do not run and blabber to your team members about

the layo. First, understand the details of the layo. Does it aect

your team members? is kind of information ow can be very

demoralizing to a team. en announce the upcoming layo with

details in a team meeting at an appropriate time.

LESSONS LEARNED FROM THIS PROJECT EVENT

Do not get your customers and your subcontractors

involved in every little detail of your project.

Filter your information appropriately in order to not

inadvertently rock your projects boat.

Learn the details of a demoralizing fact before discussing

it with your project team members.

Case1.16: Holiday Conict with a Technical

Proposal Presentation

We prepared a very competitive proposal for a large corporation

in India. e proposal was for a pipeline communication system

design, build, and installation. One of the bidding requirements

was to make a technical presentation to the Indian companys

bid evaluation committee in India. We sent our engineering vice

president and a senior engineer to India to give our technical pre-

sentation. e Indian company conrmed the technical presen-

tation time, duration, date, and location by e- mail three weeks

40

Project ManageMent case studIes

before our team left the United States. Our technical presentation

team arrived in Mumbai a day earlier. e next day, they went to

the headquarters of the Indian company where the presentation

was supposed to take place. ere were only security guards at the

entrance to the company compound. e guards told our team

that the company was on holiday for three days for the Diwali

festival and that there was no one from the bid evaluation com-

mittee working at the company that day.

Our team had no choice but to wait for three days until the

holiday was over. Our presentation team called us and explained

the miscommunication regarding the technical presentation date.

We agreed with their decision to stay in Mumbai and resched-

ule the technical presentation with the Indian company. ey

toured Mumbai during the holidays and enjoyed the Diwali fes-

tival of lights and festivities. After three days, they called the

chairman of the bid evaluation committee. He was very apologetic

about the miscommunication regarding the technical presentation

date. He said that he would like to talk to all bid evaluation com-

mittee members and set a new time and date as early as possible.

He asked our team to call them back the next day.

e next day our team called the bid evaluation committee

chairman. He set up the meeting the following day at 2 p.m.

and also conrmed the new meeting time and date by e- mail.

Our team was able to give their technical presentation ve days

after their arrival in Mumbai. Our teams presentation was sched-

uled for an hour. Afterward, an hour was reserved for a question

and answer period. After the technical presentation meeting we

received feedback from our team that all went well. However, we

lost the bid to a French company with a lower cost basis. Our

company spent over $100,000 to prepare for the bid and perform

the required technical presentation. It was my mistake that I did

not reconrm the technical presentation time and date before

our team left the United States. In international meeting set-

ups, reconrmation is a must. ings change fast and mistakes

are made. A meeting set up a couple of weeks or months before

might not be valid anymore. Continual communication among

the involved parties and reconrmation of the times and dates of

meetings avoids mistakes and unnecessary headaches.

is is especially true in countries like India, as most reli-

gious holidays are according to the lunar calendar. eir dates

change every year according to our Gregorian calendar. India

has both national holidays and religious holidays. e national

41

case studIes In stakeholder ManageMent

holidays such as Republic Day, Independence Day, and Mahatma

Gandhis birthday are xed according to the Gregorian calendar.

However, the religious holidays such as Hindu holidays, Parsee

holidays, Islamic holidays, Sikh holidays, Buddhist holidays, and

Jain holidays might shift dates every year in the Gregorian cal-

endar. Also, depending upon the belief of the person(s) you are

going to visit in India, some might be on his or her religious holi-

day, but the rest of the organization might be at work. In some

countries, if a religious holiday comes on a Tuesday, Wednesday,

and ursday, the company you are dealing with or the entire

country might decide to take the whole week o. ey shut down

their operations during Monday and Friday too, due to inecien-

cies in the workplace and close down for a week. e whole coun-

try shuts down for a week.

For a global project manager, keeping track of all national

and religious holidays of countries that you are dealing with is a

requirement. You also have to know the religious beliefs of every

individual you are dealing with. If you slack on keeping track of

all national and religious holidays, an engineer you are dealing

with in India might believe in Judaism and take a couple of days

o during Hanukkah, the festival of lights, which might coincide

with your scheduled visiting days to India.

LESSONS LEARNED FROM THIS PROJECT EVENT

In a global project, know all the national and religious

holidays of countries you are dealing with and record

them in your project schedule.

In a global project, know all religious observances of the

people you are dealing with.

Case1.17: Customers Final Inspection Report

We completed on time the designing, manufacturing, and test-

ing of mooring equipment and spare parts for a new oil rig on

Sakhalin Island, Russia. e oil rig was being constructed in

South Korea. Our equipment and spare parts were scheduled to

ship to South Korea for installation onto the platform that was

being built there. e customers inspectors came to our facilities

for nal acceptance of all equipment and spare parts. e accep-

tance process took ve days. With some minor modications,

everything was accepted and was ready to be shipped. We pack-

aged all of the equipment and spare parts in waterproof crates

42

Project ManageMent case studIes

and shipped them using a land/ ocean route to South Korea. We

included the inspectors nal inspection report with the shipment.

e nal inspection report included the packing list of all the

equipment and spare parts. We had a very experienced freight for-

warder who insured the goods that were being shipped against all

risks of physical loss or damage for door- to- door transportation.

My customers project manager was very satised with our per-

formance. He released our milestone payment. My company got

a hefty contract milestone payment of 50% of the contract value.

Five weeks passed and I received a call from my customers

project manager that the shipment had arrived in Pusan, South

Korea, but they could not clear the cargo through South Korean

customs because the spare parts were missing from the nal

inspection reports packing list. I told my customers project man-

ager that I would investigate the issue and get back to him in an

hour. I went to our shipping department and found the packing

list that our shipping department prepared for that shipment. Lo

and behold, 10 spare part items were missing from the packing

list. My shipping department missed the spare parts from the

packing list. e customers inspectors missed inspecting the

spare parts. e bank that paid us our milestone payment missed

the spare parts in the packing list. Now all of the equipment, close

to 100 items, and 10 spare parts were sitting at South Korean

customs and could not be cleared.

I called my customers project manager and relayed the unfor-

tunate chain of events. We brainstormed the situation at hand

over the phone and tried to nd a solution to the problem. One

option was to ship the 10 spare parts that were not on the pack-

ing list back to the United States, get them inspected, and reship

them back to South Korea with a correct packing list. is option

would take about two months and would incur an extra cost of

about $20,000. With this option, all of the equipment compo-

nents could be cleared through customs in a timely fashion, but

not the spare parts. e second option was to send a revised pack-

ing list to my customers representative in South Korea. He could

then present the revised packing list to South Korean customs

and clear everything through customs. e only drawback with

this option was that the 10 spare parts were not going to see the

required nal inspection per the project contract. I assured him

that all those 10 spare parts were tested and inspected by our

quality assurance department before nal inspection took place. I

left the decision to my customers project manager. I told him that

43

case studIes In stakeholder ManageMent

I would go either way he chose to solve the issue at hand. He told

me that he would discuss the two options with his superiors and

get back to me the next day with a decision.

e next day, my customers project manager called and told

me that they had decided to go with option two. ey could not

live with a two- month delay in receiving the inspected spare parts.

I was to revise the packing list in a day and send him a copy, and

to his representative in South Korea the original by FedEx. He

released us from the nal inspection of spare parts by conrming

their decision in an e- mail.

As the project manager I should have checked all nal docu-

ments that went with the shipment. After this mishap, I made it

a task for myself to review all documents that were included in a

shipment for a customer. is was an honest mistake. My shipping

department, the customers inspectors, and my customers bank, all

missed the 10 spare parts from the packing list. Spare parts were

in the list of deliverables, loud and clear, in our projects contract.

LESSONS LEARNED FROM THIS PROJECT EVENT

e customers nal inspection report has to be scruti-

nized by you for accuracy.

Simple errors in a customers nal inspection report can

come back to bite you later in your project.

Case1.18: Pressure Put on a Team Member

by Upper Management

One of the mechanical design engineers on my project team was

working on a wheelchair access ramp design for a bus. His design,

manufacture, and test tasks were on the critical path of the proj-

ect. I met with him weekly to see if he had any showstopping

issues. I asked my other team members to help him in certain

auxiliary tasks such as sourcing double- acting air actuated cylin-

ders. He was determined to nish his design on time and he was

putting in extra hours in order not to fall behind schedule.

One of our vice presidents from the sales department was

going to his cubicle almost daily and asking him questions about

his design and trying to get a feeling for the status of the wheel-

chair access ramp design. is vice president won the bus con-

tract for our company. He felt as if the contract was his baby.

He wanted everything to be completed on time so that he could

satisfy our customer. He wanted to get more future contracts from

44

Project ManageMent case studIes

our customer. e vice president was spending about half an hour

with him at each visit. I was starting to get annoyed with his vis-

its; but more than me, my design engineer was getting annoyed

too. My design engineer was a nice guy and he did not complain

to me for about a month. During one of our weekly status meet-

ing, he nally spilled the beans and told me that he was sick and

tired of the vice presidents visits day in and day out. e vice

presidents visits to his cubicle were not constructive at all. He

was wasting my design engineers valuable time. He asked me to

straighten out the situation.

I went to my boss and explained the unfortunate events

between the sales vice president and my design engineer. We dis-

cussed how we should approach the vice president and ask him

to end his daily meetings with my design engineer. We decided

that I should go alone and talk to the vice president and explain to

him the criticality of my design engineers tasks. I was to ask him

politely without oending him to end his daily visits to my design

engineers cubicle. I was to also oer to the vice president that he

was more than welcome to visit my oce daily to get an update

regarding the status of the wheelchair access ramp design.

I made an appointment with him to discuss the criticality of

the wheelchair access ramp design on the overall project. e

meeting went well. He agreed that my design engineers time

was very valuable. We did not want my design engineers critical

tasks to fall behind and to cause a delay in the overall project. He

was very receptive to my suggestion of getting daily status updates

from me instead of visiting my design engineers cubicle.

I relayed the results of our meeting to my boss and to my

design engineer. My design engineer was relieved. As the project

progressed he needed constant support in order to stay on sched-

ule. He completed all the wheelchair access ramp design speci-

cations, calculations, and drawings successfully two weeks late. I

invited the sales vice president to the design review meeting. He

did not have any comments or suggestions during the meeting,

but he was nice enough to congratulate my design engineer for

his thorough job. I also thanked the sales vice president for his

overwhelming interest in our project and by coming daily to my

oce for the project updates. My project team caught up with the

project schedule by working overtime during the manufacturing

phase of the project.

In every project, almost all hands in a company swarm around

a critical project person with good intentions to get a feeling for

45

case studIes In stakeholder ManageMent

how things are going. ey waste his or her valuable time. If the

project person has an easygoing personality, he or she tries to

accommodate everyones inquiries and questions. Valuable time

can be wasted and the project schedule can unintentionally go

down the drain. You have to caution your team members to let you

know if there are unnecessary interferences with their work. As

a project manager, you have to protect your team members from

these unnecessary distractions.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to protect our team members

from pressure coming from outside our team environment.

Time wasted by your team members due to outside inter-

ference can easily delay your project.

Case1.19: Dictatorial Micromanagement

We had six program managers in the chip design section of my

company. My company hired a new director of program man-

agers from a well- established Silicon Valley company. He was a

well- known authority in data chip design. He had started his job

two months ago and started to enforce his style of management. I

reported directly to him.

My boss had a dictatorial character. Everything was supposed

to be done the way he saw it. He never listened to me or to my

team members. He attended some of my weekly team meetings.

He took over the whole show. My team members and I tried to

give our input to solve an issue. He listened to our input half-

heartedly. He countered with his own ideas and he demanded

that our approach to a solution should be his way. I discussed his

behavior with the other ve program managers. He behaved the

same with his dictatorial style of management to all of them.

Sometimes he went behind my back and talked to my engi-

neers. He changed their ways of approaching an issue without

informing me. I told him several times not to circumvent me and

not to give mixed signals to my team members. He said okay

okay to me and kept enforcing his own style of management.

My bosss behavior was demoralizing to my team. ey started

to hold themselves back and they started to not give any input

whenever he joined our meetings. is was totally opposite of

my management style. I promoted empowerment of my team

members and everyone else contributing to my project. I listened

46

Project ManageMent case studIes

to all input and chose the most logical approach. I treated my

people with respect and consideration. I told my team members

to hang in there and asked them to provide their suggestions

and input regarding our project to me. I told them that I would

deal with the director myself in protecting my teams suggestions

and input. I used to have a weekly one- on- one meeting with the

director. I defended my team members suggestions and input. He

started shouting and swearing and insisted that everything was to

be done his way.

I could not take his one- man- show behavior anymore. I made

an appointment with the vice president of human resources and

detailed my concerns to her. I told her that our people were the

most valuable asset of our company. I told her that my team

members, other program managers, and I were fed up with the

dictatorial behavior of our director. I emphasized that we could

lose some of our crucial assets, if the directors behavior did not

improve. She told me that she was aware of the situation. She

had received other complaints about the directors authoritarian

management style too. She asked me to sit tight and to keep the

director away from my team members as much as I could. She

promised me that there were going to be several big personnel

changes coming very soon.

e following week there was a layo at my company. My

company dismissed 10% of the workforce including the director

of program managers due to a slowdown in business. e dic-

tator was gone in three months. Everyone in the company was

very happy. My team members began to get motivated again.

I respected and encouraged their input. I continually tried to

develop my team members brainstorming and engineering skills

so that I could extract the highest possible performance from each

one of them. I always wanted to create a culture and environment

that supported and respected my people.

e company promoted a director of program managers from

within the company. e new directors management style was

very much like mine. We got along great. My team members per-

formed awlessly to complete my project on time and within bud-

get. I was lucky that three months of a distasteful ordeal with the

authoritarian director did not hamper my project.

During my 40-year engineering and management career, I

came across many dierent styles of managing people. e worst

management style belonged to this director who was micro-

managing everyone under him in an authoritarian fashion.

47

case studIes In stakeholder ManageMent

LESSONS LEARNED FROM THIS PROJECT EVENT

A dictatorial boss can overwhelm you and your project

team and cause damage to your project without realizing

the consequences.

You have to protect your project team from your authori-

tarian boss at all costs.

You have to take immediate steps to correct your bosss

unacceptable behavior.

Case1.20: Setting Up Two Automated

Assembly Modules in Malaysia

Labor costs were increasing fast in our Malaysian plant. Also,

computer component sizes were shrinking and their assembly

and alignment tolerances were getting tighter and tighter to the

order of 0.0001 inches or 2.5 micrometers. I was assigned to

develop an automated assembly module for our computer com-

ponent assembly processes and get two modules into operation

in Malaysia. I was assigned two full- time senior manufacturing

engineers from our U.S. plant to my team. Our rst task was to

search in the United States for an automation development house

and get the automated assembly module built to our specica-

tions. After a three- month search, we found an automation sub-

contractor in Boston whose cost proposal and whose technical

capabilities t our mission.

I made a half- hour presentation to my companys board of

directors about our options and their return on investment and

got the automation project approved. Our boards approval was a

requirement for projects over $2M dollars. is was the highest-

priced project for the company and it had to be completely installed

and in operation in Malaysia in nine months. All the automation

drawings had to be in both British and in metric units. All fas-

teners had to be in metric so that they could be easily sourced in

Malaysia. I sent two of my engineers to Boston and made them

live with the project at the subcontractors plant day in and day out.

I also had to nd three Malaysian engineers who were mechani-

cally savvy so that I could bring them for the automation module

qualication runs to Boston for three months. ey were going

to be trained in-depth for the operation and maintenance of the

automated assembly modules by the subcontractor. ese three

Malaysian engineers would ultimately be responsible for running

the automated assembly modules in our Malaysian plant.

48

Project ManageMent case studIes

I communicated with our Malaysian general manager and sent

him the requirements for the Malaysian engineers. ey found

nine candidates. I traveled to Malaysia to interview the nine can-

didates face to face. e Malaysian general manager and I agreed,

after interviewing all the nine candidates, to hire three of the can-

didates. ese Malaysian engineers were also responsible for writ-

ing the equipment operation and maintenance manuals in English

and in Bahasa Malay. I made sure that they had the correct entry

visas into the United States for three months. I arranged for an

apartment for them within walking distance to our subcontrac-

tors plant. ey traveled to Boston after six months into the proj-

ect when the module was getting ready for the qualication runs.

During those six months in Malaysia, they prepared the site for

two automated assembly modules. e site had to have tempera-

ture and humidity control and had to have a class 100 clean room

environment. e site oor had to be vibration- free and the power

supply had to have voltage regulators and the power supply had to

be uninterruptible. ey also had to source a precision machine

shop close to our plant in Malaysia for precision spare tools.

Everything was on schedule and within my cost prediction for

the rst six months of the project. When we started to assemble

and test the system we started to have clogging problems with

the automated epoxy dispensing unit. In our specications, we

required a periodic maintenance for half an hour at every eight

hours to the automated assembly modules, namely at the begin-

ning of every shift. However, the epoxy temperature control and

dispensing required the system to be cleaned and maintained every

hour. is was totally unacceptable because it reduced our through-

put from the assembly system by 25%. It took our subcontractor

and the project team another three months to nd an acceptable

solution to the epoxy dispensing units short operating cycle. With

better temperature control and with a modied epoxy dispensing

unit, the periodic maintenance interval was increased from one

hour to four hours. During this unfortunate event, the cost of the

project soared by 40% and I had to go in front of the board again

to explain the failing adhesive dispensing submodule and the pro-

posed solutions and to ask for a three- month extension and a 40%

cost increase for my project. at was a painful experience to face

the board members, but the company board realized that there

was a light at the end of the tunnel and shelving the project at this

juncture would have been more harmful for our company.

49

case studIes In stakeholder ManageMent

After a three- month delay, the qualication runs in Boston

started and went well. e Malaysian engineers learned the sys-

tem hands on and in great detail. However, we had to accept the

automated assembly modules with a four- hour periodic main-

tenance interval that resulted in a 6% throughput loss. I had to

again go in front of the company board to explain the nal status

of the automated assembly modules. I got their approval to accept

the system with 6% throughput loss, not to push our subcontrac-

tor to meet the system specications to the letter, and not to delay

the project further out.

We shipped two unassembled automated assembly modules by

air to Malaysia to gain time. We reassembled the two systems

in Malaysia and started to make qualication runs. Two engi-

neers from our subcontractor, two engineers from my team, three

Malaysian engineers, and myself got two automated assembly

modules ready for production in two weeks in Malaysia.

ere were some other unforeseen glitches in the Malaysian

operation of the two automation assembly modules. One glitch

was with the spare parts. In a three- shift operation a day and

six days a week, we were always short of spare parts. We had to

increase our spare parts supply by twofold in a hurry. Also, we had

to set up a two- day delivery system with Federal Express from the

United States from several of our automated assembly modules

component manufacturers.

Another issue in Malaysia was with one of the Malaysian engi-

neers. He had to leave the company for medical reasons. I had to

scramble and get one of the U.S.-based engineers on my team to

go to Malaysia and support them in the operation and mainte-

nance of the systems. He had to live in Malaysia for six months

until another Malaysian engineer was found and properly trained.

e Malaysian plants general manager was very helpful in nd-

ing a new Malaysian engineer.

Another nagging issue was the shortage of computer compo-

nents for assembly for a given customer. Some of the components

were delayed in customs or at the original manufacturer. Some

of the component lots were rejected at the receiving inspection

stage. Initially, two automated assembly modules were idle about

15% of the time in a given month. e Malaysian plant had to

increase the inventory of the computer components that had to be

assembled for a specic customer. After six months of operation

and a diligent component inventory control, the two automated

assembly modules idle time was reduced to 4%.

50

Project ManageMent case studIes

After operating the two automated assembly modules for one

month in production, the precision alignment pins started to wear

out. Computer component assembly locations started to shift. I

requested our subcontractor to come to Malaysia urgently. We put

our heads together and decided that we had to replace all of the

precision alignment pins with ones that were made out of harder

material. We updated all the aected drawings and were able to

source the new harder precision pins in Germany. is retrot

to the two systems took two weeks and it made the automated

assembly modules operation much more stable.

After we qualied the two automation assembly modules, we

had to invite our customers to our plant in Malaysia for produc-

tion qualication runs for their specic computer component

assemblies. One of our customers was Japanese and the other was

French. We rst brought the Japanese customers representatives

into our plant and showed them our new automation assembly

module. We made a shifts worth of assembly runs for them, about

1,000 assemblies. We measured the critical parameters of all the

assemblies and studied their means and spreads. e means were

very close to the customers specication nominal. e spreads

were about 50% narrower than the manual assembly control

charts. e Japanese customer accepted the new automation

assembly module without any reservations. e following week,

we performed a similar qualication process for our French cus-

tomer. e French customers qualication also went smoothly.

After 14 months of challenging problem- solving sessions,

board meetings, communications, and travel between our U.S.

plant in California, our subcontractor in Boston, and our plant in

Malaysia, my project team, our subcontractor, and the Malaysian

project team did a great job of developing and implementing the

two automation assembly modules in our Malaysian plant.

LESSONS LEARNED FROM THIS PROJECT EVENT

e diculties in setting up automated assembly lines in

developing countries.

As a project manager, details of a task are very crucial.

An issue can always pop up that you might have easily

overlooked.

Budget overruns are a part of life for a project manager.

How to deal with them in a timely fashion is a must.

51

case studIes In stakeholder ManageMent

It is sometimes not feasible to comply with every speci-

cation of your project. You have to go to your customer

and ask for deviations using justiable reasoning.

You have to learn the infrastructure and capabilities of

each one of your teams personnel in utmost detail in all

foreign countries that you are dealing with.

Case1.21: Project ClosureLessons Learned Meetings

I was in the process of closing out a two- year project in advanced

electric bus design and manufacturing. My nal project status

report was accepted by my customer. I presented the nal project

metrics to the domestic and international upper management of

my company. I received a favorable nal project evaluation report

from my customers project manager. Everything regarding the

projects closure was going smoothly. en, I was called to an

emergency re-ghting mission to South Korea. I had to travel

to South Korea immediately and ended up staying there for three

weeks in order to straighten out my companys urgent issue with a

casting subcontractor. e only thing that was left open from my

projects closure was the lessons learned meetings with my team

members, with my domestic and international upper management,

with my customers project manager, and with my subcontractors.

When I returned to the United States, I compiled a list of les-

sons learned items from my two- year project. I tried to get a meet-

ing going with my old team members, but everyone was assigned

to other project teams and it was dicult to come up with a com-

mon meeting time. Also, interest in such project closure meetings

faded away fast. Everyone involved had dierent pressing priori-

ties. Two of my team members were assigned to a project in Japan.

Finally, I was able to gather eight out of ten team members to a

luncheon meeting. Of course, I promised to buy lunch for every-

one. I presented my lessons learned list. We discussed what to

do in the future in order not to fall into similar situations. I later

did the same presentation to two engineers residing in Japan via

video conferencing. I gave a similar lessons learned presentation

to my team members in Germany via videoconferencing. en I

called a lessons learned meeting for my upper management team

to which only half of the upper managers attended. I also called

my customers project manager and my major subcontractors to

discuss pertinent portions of my lessons learned list. Finally, I

52

Project ManageMent case studIes

released the lessons learned list with constructive input from all

my contacts into document control so that all future project man-

agers could easily access it. It took me a good part of a week to

complete my nal duties for my completed project. I charged my

time to the company overhead account because all project num-

bers were already closed.

e nal lessons learned list covered issues related to team

personnel, project specications, my company, my customer, my

subcontractors, project schedule, and project budget. In all of the

issues discussed during our lessons learned meetings, two of them

stood out and they were related to the projects cost. One lessons

learned item was the price of the bus frames which were built by

our subcontractor in Germany. We had to pay an extra 20% in

U.S. dollars for those frames due to devaluation of the U.S. dol-

lar against the Euro. In an international project like that one, my

company should have analyzed the future value of the U.S. dollar

against the Euro and should have bought Euros at the beginning

of the project to cover the cost of all bus frames. In our future

global projects, our chief nancial ocer was very careful in deal-

ing with my companys liabilities in dierent foreign currencies.

After this lessons learned event, my company bought sucient

futures in dierent foreign currencies against the U.S. dollar that

were required for our global projects.

e second lessons learned cost issue was due to the price

increase in special high- strength steel purchases. During the

course of the project, the price of special high- strength steel

increased substantially due to increasing worldwide demand. Our

purchasing department bought the steel in three segments from

three dierent customer- approved sources due to our tight cash

ow. is strategy worked against us as the price of steel skyrock-

eted. We should have bought all of the required steel at the begin-

ning of the project or we should have bargained with one steel

supplier to deliver the required amount in three installments at the

same initial price. Again, our purchasing strategies were improved

and scrutinized very carefully after this lessons learned event.

Closing a project appropriately can be painful and time con-

suming. However, rewards of a properly closed project can be

invaluable. Lessons learned from a completed project can be one

of the most important items on a project closure to-do list. As

project managers, we have to nalize lessons learned meetings

at all costs even if the interest in the completed project is quickly

fading away.

53

case studIes In stakeholder ManageMent

LESSONS LEARNED FROM THIS PROJECT EVENT

Lessons learned from the execution of a project should

be documented and presented to everyone who played a

part in your project.

After a project winds down, it is dicult to get your old

team together for a meeting.

Case1.22: Penalties in a Project Contract

Penalties in a project contract can come with quite dierent word-

ing and meaning. As global project managers we have to fully

understand the meaning of these penalties. We need to bring our

lawyers into the picture if we have to clarify or modify certain

contract clauses. en we have to relay all of the information

related to a project contracts penalties in detail to our team mem-

bers and to our upper management. Liquidated damages are good

examples of a project contracts penalties.

In one of my project contracts, the liquidated damages were

worded as follows:

If Seller does not deliver goods in conditions stipulated and

in accordance with delivery times provided in this Contract,

Purchaser is entitled to recover reasonable liquidated damages per

each week of delay.

is was a vague penalty statement. What was the meaning of

reasonable? Who decided on the reasonable damage? I had to get

this statement modied before the start of the project. I got my

upper management and my legal department involved to clear up

this vagueness in the contract. After two weeks of negotiations

with the customer, the nal version of the contract for liquidated

damages read as follows:

If Seller does not deliver goods in conditions stipulated in this

contract and in accordance with delivery times provided in this

Contract, Purchaser will recover 4% of the total purchase price

per each week of delay as liquidated damages. A delivery delay

in goods caused by a force majeure impediment is excluded from

liquidated damages.

In another project contract, a penalty clause was stipulated as

follows:

Seller is obliged to deliver all goods according to packing, preser-

vation and marking instructions of Purchaser. If Seller does not

carry out these instructions, Purchaser is entitled to a price reduc-

tion of 5% of the total contract price.

54

Project ManageMent case studIes

I reviewed the entire contract in order to nd these instructions,

but there were none. I called my customers project manager and

discussed missing packing, preservation, and marking instruc-

tions. We agreed on all the details in such a way that the price

of the contract did not change. He sent me a written conrma-

tion of all packing, preservation, and marking instructions. I

was relieved to nalize a missing item from my projects contract

before it was too late.

In a chip design project contract, the following contract

statement was very restrictive to the progress of my project in a

timely fashion.

Purchaser shall have the right to request changes from this con-

tract agreement. Seller shall not proceed with any such change

until an ocial change order is received from the Purchaser.

is clause was impossible to implement. e chip design speci-

cations were very uid. My team members and my customers

engineers conferred daily for specication clarications and for

additions and deletions to specications. e project could not

progress if I waited for an ocial change order from my cus-

tomer for every specication change event. I discussed this show-

stopper clause with my customers project manager. We agreed to

modify this contract clause as follows:

Purchaser shall have the right to request changes from this contract

agreement. Seller shall not proceed with any such change until

an e- mail describing the change is received from the Purchasers

Project Manager. All changes approved by e- mails shall be col-

lected monthly into an ocial change order by the Purchaser.

In one of my oshore oil platform equipment delivery projects,

the contract stipulated the delivery time as the date the equipment

in question was installed and was operational on the platform. If

I missed that date I was penalized by a liquidated damage clause

in my contract. I had to watch like a hawk for any equipment

installation delays caused by my customer. Several times their

power lines were not ready. On one occasion they had to perform

extensive welding, which blockaded the area of our equipment

installation. I recorded all these delays caused by my customer

and immediately informed my customers project manager so that

I would not get penalized for events that were beyond my control.

Penalties in a projects contract can be ambiguous, too general,

vague, inconsistent, redundant, and conicting. As global project

55

case studIes In stakeholder ManageMent

managers, we have to catch these sinkholes before the execution

of our contracts and have them claried without any reservations.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to fully understand all

penalties written into our projects contract.

We have to get vaguely worded contract penalties well

dened by our customer and if necessary with the help of

our legal department.

We have to explain project penalties and their conse-

quences to our team members, to our upper management,

and to our subcontractors at the beginning of our projects.

57

2

Case studies in

sCope ManageMent

As project managers, we have to watch the scope of a project like

a hawk and we have to be the nal authority for the projects scope

changes. Changes and misinterpretations of a projects scope can

occur very easily behind our backs.

In a chip design project, the specications were written in a very

concise fashion and they were open to many interpretations. As the

design progressed, my team started to have numerous questions

about the specications that needed clarication. Also, my customer

in Germany wanted to add several enhancements to the chip design

along the way. Specications that are in a constant ux can be very

challenging to control as depicted in Case2.1.

During the manufacturing phase of a research safety vehicle proj-

ect, there was a sudden program manager change with our customer.

e new program manager was clueless about the history of the

program. He started to demand changes to the vehicle design that

were above and beyond the specication clarications and changes we

had agreed to with his predecessor. As project manager, I had to put

the brakes on and bring him back to reality in my project as detailed

in Case2.2.

In a xed price contract, the customers specications had quite a few

TBDs (to be determined items). For a project manager, TBDs required

a lot of attention and caused tremendous headaches between the cus-

tomers project manager and myself. I had to watch these TBDs like a

hawk. When a TBD specication was nalized by the customer, I had

to make sure that the claried specication was doable and that it did

not aect my projects cost and time constraints as shown in Case2.3.

In one project, I had dual customers and therefore two customers

project managers. To keep both customers project managers in sync

and happy took a lot of extra eort during the execution of my project.

58

Project ManageMent case studIes

I detail the issues I encountered with the dual customers project man-

agers in Case2.4.

We had to nish the manufacturing phase of a project destined

for Russia by the end of January so that we could test and ship the

heavy equipment mover system for installation and training during

the summer months there. Our customers project manager called me

and told me that several of their other subcontractors were delayed in

completing their tasks. ey also had some cash ow issues so they

wanted to delay our mover system to be installed during the following

summers window. A year delay to complete a project requires several

adjustments to tasks as shown in Case2.5.

I took over a project right in the middle of its design phase. My

customers project manager was accustomed to calling my teams

design engineers and ordering minor variations to the specications

on the telephone without my knowledge. Nothing was documented

and we were drifting away from the original project technical speci-

cations. Apparently, the previous project manager closed his eyes to

these minor specication variations and my customers project man-

ager became used to forcing these minor specication changes on my

design engineers as detailed in Case2.6.

I had several projects where minor scope changes occurred. I went

along with my customers requests without going through the mind-

boggling change approval cycle. My customers project manager followed

a similar process. is was a documented bartering process of minor

scope changes between my customer and me as detailed in Case2.7.

Software used in a project has to be scrutinized for compatibil-

ity very carefully. ere can be many unforeseen conicts and issues

between customers, subcontractors, and internal users of software. I

ran into several serious issues with software as detailed in Case2.8.

Case2.1: Specication Clarications

with a Customer in Germany

I had a nine- month project to develop the software for a mobile

phone wireless application connectivity chipset for a German cus-

tomer. I had six chip software design and test engineers working

on my team on a full- time basis. Our oces were in California

and my customers oces were in Munich, Germany. is nine-

hour dierence in the time zones brought to the surface several

59

case studIes In scoPe ManageMent

communication challenges, especially as the chipset specications

were written in a very concise fashion and they were open to many

interpretations. As the design progressed, my team started to have

numerous questions about the specications that needed clarica-

tions. Also, the customer wanted to add on several enhancements

to the chipset design along the way.

I was lucky that this custom chipset software development

project was not a xed price contract. It was a time and materi-

als agreement. I had to inform the customer weekly of how his

money was being spent on the project. ere were no punishing

scope changes and specication revisions. I only had to record

every specication clarication and every additional specica-

tion enhancement as the project moved on. is custom software

development project required precision and on-time communica-

tion methods with the customer. ese communication methods

had to eliminate any specication ambiguities in their uid state.

At the project kicko meeting with the customer, I oered to

have a daily one- hour telecommunication with my team and on

his end with him and the others that he wanted to bring into the

teleconference from Monday through Friday. e teleconference

time would be at 8a.m. Pacic standard time, which would make

it 5p.m. in Munich, Germany. He accepted my meeting proposal.

I also proposed that we both record the teleconference proceed-

ings so that we would not miss any specication clarications,

additions, or deletions. I also told the customers project manager

that I would review the meeting tape recordings daily and sum-

marize the contents and issue the meeting minutes by e- mail to

him for his approval within 24 hours. I would update the chip-

set design specications weekly, release the new revision to our

document control, and distribute them to the customers project

manager and to my team. e customers project manager was

very happy with my specication control procedures. We started

the project this way.

After the second week into the project, I started seeing delays

in my engineers performance. Specication clarications and

customers additions or deletions were not being handled on a

timely basis. is was such a dynamic project that my engineers

required instant clarications and solutions to specications. My

team and customers interface had to be in more real time. We

could not wait 24 hours to get a response from the customer for

specication clarications. e communication setup was bog-

ging down my engineers and hampering their progress.

60

Project ManageMent case studIes

I had a team meeting to discuss the specications and cus-

tomer interface issues. Two of my senior software engineers

oered to change their schedule and work a swing shift from

6p.m. to 3a.m. from Sunday night through ursday night. ey

were used to these kinds of odd work hours from university days.

ey thought they would be more productive by not being dis-

turbed by other colleagues in the oce. is setup would give my

team four hours of direct interface with Germany from 11p.m. to

3a.m. ese two software designers were responsible for the most

critical segments of the chipset. I told them that their proposal

would be a great solution for our teams progress. is new setup

would give us ve hours of real- time interface with the customer.

My condition was that they had to tape record every conversation

with the customer so that I could collect all the clarications and

changes regarding the chipset specications. Also, I would have a

meeting with these two engineers from 6p.m. to 7p.m., Sunday

through ursday, in order to review their progress, to discuss the

issues they were having, to give them updates as to what was hap-

pening during the day shift, and to bring them up to date from the

results of my morning call with our customer.

I told them we would propose our new interface setup to our

customers project manager in the morning. I also told them that

I would discuss new working hours with their supervisors and

with human resources so that there were no hidden kinks in the

new proposal. ere could have been company security issues.

ere could have been overtime payment requirements. ese

engineers were salaried engineers and there was no overtime work

adjustment to their salaries. e supervisors of the two engineers

and human resources found no drawbacks for them to work from

6p.m. to 3a.m., Sunday through ursday night, for the duration

of my project.

e next morning, during our teleconference with our cus-

tomer, we discussed the new working hours of my two senior

engineers and how this new setup would improve real- time com-

munication to clarify ambiguities in specications. e custom-

ers project manager was very receptive to our proposal. My two

engineers started to work in the swing shift and this new setup

increased our real- time communication with the customer to ve

hours a day. is new setup was very eective in getting quick

responses to questions regarding chipset design specications

and it lasted for six months. Also, these two software designers

worked very eciently without being disturbed.

61

case studIes In scoPe ManageMent

My team nished the chipset software design and test on

time. I generated a complete set of specications for the chipset

which was up to date. My customer appreciated the complete set

of specications tremendously. At the end of the project, I wrote

a resounding recommendation for the two software engineers

who had volunteered to work the swing shift. e beauty of this

solution was that the swing shift idea came from the engineers.

is was a win- winsituation for my project, for my company, and

above all for the customer.

LESSONS LEARNED FROM THIS PROJECT EVENT

In a global project environment, real- time communica-

tion between your team and your customer might require

unusual work schedules.

As project managers, we have to notify our project team

members supervisors and get their approval for chang-

ing work schedules.

Keeping track of all changing project specications and

their clarications during the execution of a global proj-

ect can be very time consuming.

Case2.2: A Change in the Customers Program Manager

in the Middle of a Project

I was the project manager for the research safety vehicle develop-

ment for the National Highway Trac Safety Administration, an

agency for the Department of Transportation. e design phase

of the project was completed. We started to manufacture proto-

type vehicles and got them ready for crash testing. During the

course of the design and development process, there were many

specication clarications and changes to the vehicle. All speci-

cation clarications and changes were document controlled in our

company. Every revised version of the specications was submit-

ted to our customer.

During the manufacturing phase of the project, there was a

sudden program manager change with our customer. e new

program manager was clueless about the history of the research

safety vehicle program. He started to demand changes to the vehi-

cle design that were above and beyond the specication clarica-

tions and changes we agreed upon with his predecessor. He wanted

specication changes in the vehicles ground clearance, the vehicles

maximum curb weight, the vehicles side impact crashworthiness,

62

Project ManageMent case studIes

and so on. e vehicle design had already been completed and it

was not possible to implement his new specication requests at this

stage of the project. When I refused to implement some of the

changes that he requested, things started to get tense between us. I

sensed a rising tension from his tone during our telephone confer-

ences. I had to do something urgently to bring this customers new

program manager to our level of understanding of vehicle speci-

cations and contract requirements.

I decided that I could not bring him up to date from 3,000miles

away in our research safety vehicle project, which had been going

on for three years. I kindly asked him to plan a trip to come to

our facilities in California and spend a week with us so that he

could meet my team members and could see our operations and

capabilities in person. My main purpose was to go over the history

of the project step by step with him. I wanted him to understand

all the specication clarications and changes that were made

during those three years. e customers new program man-

ager accepted my proposal, decided to leave his desk behind in

Washington, DC, and visit our facilities.

I sent him a proposed agenda for his visit. He accepted all of

my proposed agenda with some minor variations. e rst day was

dedicated to meeting my team members and our upper manage-

ment. On the second day, we concentrated on our manufacturing

facilities and our test facilities. On the third and fourth days, we

went through the history of the research safety vehicle project. We

went over every specication one by one. We reviewed all the spec-

ication clarications. We reviewed all the new specications that

were added on by my team or by his predecessor. en we reviewed

every contract modication and every monthly status report. He

was very impressed with our precise document control procedures.

On the fth day, we went over the master project schedule and

reviewed tasks that were on the critical path. He was brought up

to speed on every aspect of the project. He was very appreciative

of such a detailed project review. I was ecstatic too that he was

nally at the same level of understanding of the project as me and

my team.

By the afternoon of the fth day, we had covered everything we

could regarding the project and we deserved a break from work. I

took him to our city center for lunch and I played tour guide and

showed him the highlights of our city. During this interaction, I

learned a lot about the personal side of my customers new program

manager. He was also a tennis bu like me. Later, I invited him to

63

case studIes In scoPe ManageMent

play an hour of tennis with me. I provided him with all the tennis

gear. e customers new program manager left California with a

good understanding of the research safety project. He gained trust

in our project team and in our project processes. Above all, he

became a project contributing colleague and a good friend.

ese kinds of changes to critical personnel can happen in any

project. It is the project managers responsibility to bring the new

team member up to speed about the project.

LESSONS LEARNED FROM THIS PROJECT EVENT

Bringing your customers new project manager up to

speed might need patience and require careful planning

and execution.

Mutual trust and respect established between you and

your customers project manager along with a personal

touch are signs of a matured project manager.

Case2.3: TBD and Erroneous Specications for a Project

We were doing a mooring system project for an oshore oil rig in

the Gulf of Mexico. It was a xed price contract, but the speci-

cations were sprinkled with a lot of TBDs (to be determined)

items. As the project manager, the TBDs required a lot of atten-

tion and caused tremendous headaches between the customers

project manager and myself. I had to watch these TBDs like a

hawk. When a TBD specication was nalized by the customer,

I had to ensure that the claried specication was doable and that

it did not aect my projects cost and time constraints.

Out of a dozen TBD specications, one was for the smoothness

of a stainless steel surface. I had to negotiate this TBD specica-

tion rigorously with the customers project manager. I did not want

to accept a tight specication that would have required extra ne

machining of stainless steel surfaces of our system. We rst agreed

on the smoothness measurement technique and then the mea-

surement sampling location and measurement length for traces.

en we agreed on the maximum R

a

value, maximum value of the

arithmetic average of absolute values of vertical deviations of the

roughness prole from the mean line. I sent my customers project

manager an e- mail outlining the agreed upon smoothness speci-

cation in detail and asked him to send me his approval note for this

TBD specication. After I received his approval note, I initiated

an engineering change order for the project specications in our

64

Project ManageMent case studIes

document control system. I distributed the nal smoothness speci-

cation to all the engineers and manufacturing people who were

involved with the stainless steel surfaces. I also sent a copy of the

released project specication to my customers project manager.

One by one, we negotiated and agreed on all the TBD specica-

tions. One of these specications was the interface drawings that

were supposed to be delivered to us after four weeks from the start of

the project. It took them six weeks to deliver the interface drawings

to us. We were lucky to receive them in six weeks and fortunately,

they did not aect the progress of my project. So I did not raise any

ruckus with my customer about this crucial delay. I kept their delay

as an ace in my pocket to exchange it with a future project delay that

could have happened on our side.

We nished all our stress calculations and system components

designs on time. We as a team were ready for the mooring sys-

tem design review. We had a two- day meeting at our facilities.

During the meeting, the customers chief engineer told us that

the slots that were designed into the mooring system were good

for the chain passage, but they were not sized appropriately for the

passage of the chain connectors. My team and I were quite sur-

prised by this announcement by our customer, because the project

specications clearly identied the chain size and dimensions and

also identied that there would be no chain connectors in this

mooring system. I showed them their specications. My custom-

ers team was embarrassed to realize their slip in project speci-

cations. My customers project manager emphasized that we had

to redesign the mooring system for the chain connector passage.

e only solution was to evaluate the impact of this major

change to our project for manpower, cost, and schedule. I asked

my customers project manager to give me two days to analyze the

eects of this major change and to provide him with a written

revised proposal. He accepted my oer and they left our facilities

after throwing a major twist into the project. We had to redo all

of our stress calculations and change our design drawings. On top

of it all, I was not even sure if all the designers on my team were

available for the expanding project.

I had a meeting with my team to get their time estimates for the

customers new change order. I estimated the time and cost impact

of the engineering change order to the project. I met with the man-

agers of each member of my team regarding their availability for

the extended project. After I had all the facts, I collected my upper

management team for a meeting and showed them the impact of our

65

case studIes In scoPe ManageMent

customers change order. ey made some minor changes to my cost

estimates. I got the upper managements blessing for the change order.

en I wrote a formal response to my customers project manager for

their proposed change. e project was delayed by two months and

this major slip in my customers specications cost them 20% extra.

My customers project manager discussed my schedule and cost

impact on the project to their change order with his upper man-

agement. ey had no negotiation leverage but to accept my pro-

posal. e surprising change order was a major slip on their part.

My team nished the project two weeks earlier than promised. My

teams eorts to nish the project two weeks early received excel-

lent reviews from my customers project manager.

LESSONS LEARNED FROM THIS PROJECT EVENT

At the start of a project, there can be several TBD speci-

cations in your customers documents. As project man-

agers, we have to have them claried as soon as possible.

Sometimes a customers specications can be in error or

missing, which might change the course of your project.

Any major project specication changes have to be ana-

lyzed very carefully and with the utmost detail by you

and then presented to your upper management for their

approval. Your presentation should cover change order

eects on your team members, on the project schedule,

and on the project cost. en, the change order should be

introduced to your customer.

Case2.4: Dual Customer Project Managers for a Project

I was heading an electric bus design and manufacturing project for

the municipal transit district of a large metropolitan city. It was a

two- year project. My team had to design, build, and test 15 elec-

tric buses for operation in the citys downtown area as a free people

mover. e 40-passenger buses had to have a range of 50miles in

a stop- and- go downtown environment before changing their bat-

teries with a fully charged set. is was a dream and a leading-edge

project in the 1980s. e project was sponsored by the Department

of Transportation. e interesting part of the project was that I

had two bosses for the project. One was the project manager from

the Department of Transportation who sponsored the project and

the other was the project manager from the citys municipal transit

district who was going to utilize the electric buses.

66

Project ManageMent case studIes

We also had to deliver the buses to the citys municipal transit

district and had to train their personnel for operation and main-

tenance of the buses. As a project manager, my duties were almost

doubled. I had to communicate ins and outs of the project to both

project managers. I had to keep both of them up to date regard-

ing the project. Both project managers had to be present at all the

critical meetings. Critical meetings had to be set up by consid-

ering both project managers schedules. Whenever there was an

engineering change order, both project managers had to sign it

o. I had to keep track of all the correspondence with both project

managers. ese routine tasks were ne and dandy, but when the

two project managers had conicting ideas and demands about

the project, things got out of hand. I acted as an ombudsman and

tried to resolve the conicting issues by having telephone con-

versations between the three of us. If telephone dialogue did not

work out, I had to bring all three of us into a meeting room.

One of the conicts came from the minimum ground clear-

ance specication. e initial minimum ground clearance speci-

cation was 9 inches. All the design was done per this specication.

During the design review meeting, the municipal transport dis-

trict project manager requested this minimum ground clearance

to be increased to 12 inches. I explained to them that at this stage

of the project it would be dicult to change this specication and

I explained the reasons. I told them if they insisted on increasing

the minimum ground clearance of the buses, we had to redesign

several subcomponents. is would delay the project by at least

two months and it would also have a cost increase impact. e

Department of Transportation project manager insisted that we

stay with the original specication, but the municipal transport

district project manager did not budge from his request. I saw

that we were not going to resolve this conict during the meet-

ing. I requested a recess. I gathered the two project managers

into a smaller conference room away from my project team. We

discussed the pros and cons of increasing the minimum ground

clearance specication in detail. I made the municipal transport

district project manager agree to the fact that the citys downtown

route was very at with no dips or bumps. I also listed all the

changes that had to be implemented in order to comply with

his request. e Department of Transportation project manager

allowed me to do all the talking and convincing. I asked both of

them to sleep on this conicting specication and to make a deci-

sion by tomorrows design review meeting.

67

case studIes In scoPe ManageMent

e next morning at the beginning of our design review meet-

ing, both project managers announced that they agreed to stay

with the original minimum ground clearance specication. is

was quite a relief to me and to my project team.

Another conict between the two project managers surfaced

toward the end of the project about the driving cycles that were to

be used to test buses for a range specication of 50miles. We pro-

posed to load a vehicle with fully charged batteries with sandbags to

simulate 40 passengers and run it on an airport runway mimicking

a citys downtown stop- and- go environment. e municipal trans-

port district project manager bought into our proposal. He asked us

to repeat the test three times with dierent buses in order to get an

accurate understanding of the electric buses range. is time, the

Department of Transportation project manager had issues with my

range test proposal. He wanted us to ship two completed buses to

the city and run those two buses there for a week while transport-

ing people, using its air conditioning, and operating its wheelchair

ramps. He wanted a real life test in the citys downtown driving

environment before accepting our buses. ese proposed range tests

were risky because of the uncontrolled environment. I had a tele-

conference with both project managers to discuss the range test pro-

cess. After an hour of negotiating they both agreed that we would

perform the controlled range tests as I proposed. en after they

accepted the buses, we would ship two buses to the city to be tested

for range in the actual downtown environment. is agreement was

a win- win agreement for both sides. We got what we wanted because

my priority was the acceptance of the buses. e Department of

Transportation project manager got what he wanted, too.

Both range tests were performed without a hitch. At the simu-

lated range test, we got close to 60miles of range. At the citys

downtown range tests, we got higher ranges because the buses

were not always fully loaded.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, you can have more than one boss

on your projects customer end.

Conicts can arise between your multiple bosses at the

customers end that can negatively aect the progress of

your project.

You might have to bring your multiple bosses together to

discuss and to negotiate a just solution to the issue at hand.

68

Project ManageMent case studIes

Case2.5: A Customer Delays Installation and Training

I was heading a two- year heavy equipment mover system proj-

ect for Russia to be installed at a Siberian location. e project

had four phases, which were design, manufacturing, testing

and installation, and training. e design phase was completed

in eight months on time and within budget. e critical design

review was held in our facilities in the United States and it went

very smoothly. We were in the nine- month manufacturing phase

of the mover system. We had to nish the manufacturing phase by

the end of January so that we could test and ship the mover system

to Russia for installation and training during the summer months

there. e customer gave us a four- month window for the instal-

lation and training phase in Siberia, namely, the months of May,

June, July, and August.

We worked hard to complete manufacturing by the end of

January. I had to authorize some overtime work due to several inef-

ciencies during the Christmas break. We were almost about to

complete our manufacturing operations and the customer came

to us with surprising news. Our customers project manager called

me and told me that several of their other subcontractors were

delayed in completing their tasks. ey also had some cash ow

issues so they wanted to delay our mover system to be installed

during the following summers window. I told him that I would

discuss this sudden shift of events with my upper management

and would get back to him with my response in two days.

First, I collected my team for a meeting and discussed the

implications of the installation and training delay for a year.

Everyone on my team concurred that we should test the mover

system in our facilities during February and March without delay

and we should have our customer come to our facilities to accept

the mover system. After the mover system was accepted we should

crate the system for surface shipment. en, we should nd a stor-

age space that was clean and that was temperature and humid-

ity controlled to store the mover system for a year. We should

also charge the mover system transfer and storage expenses to

our customer.

en I had a meeting with my upper management team to

inform them of my customers delay and to discuss my teams

counterproposal to this delay. Upper management was very recep-

tive to our proposal. A one- year delay in completing the project

would have a minimal eect on our cash ow. All my team mem-

bers would be allocated to other projects by the end of March.

69

case studIes In scoPe ManageMent

Four of my engineers would be reassigned to my project the fol-

lowing May for installation and training in Siberia. We decided

not to apply the penalty clause of the project agreement for their

delaying the project. My upper management gave me the green

light to make our counterproposal to our customer. During these

internal negotiations with my upper management, I asked two

of my engineers who had some slack time to investigate the

expenses for a storage facility. We needed about 2,000 square feet

of space for a year. ey found a couple of alternative storage spots

close to our facility. e mover system transfer and storage costs

for a year were estimated to be between $40k and $50k.

e next day, I called our customers project manager in

London and gave him the details of our counterproposal. He also

wanted to delay the acceptance tests, but I stood my ground in

order not to delay the acceptance tests. I told him that we were not

applying any penalty clauses of our agreement for their delay. And

that we were doing extra work to nd a storage space to store the

mover system under very secure and favorable environmental con-

ditions for a year for just $40k. He said he had to go back to his

people and get their input for my counterproposal. I did not hear

from him for two days. During this time, I put our counterpro-

posal in an item- by- item written format and e- mailed it to him. I

called him back to see what was going on. He asked for another

week before he could make a decision on our counterproposal.

During this time, we started testing the completed subsystems

of the mover system. I allocated two months of testing and nal

acceptance for the completed mover system.

LESSONS LEARNED FROM THIS PROJECT EVENT

Completion of your project can be delayed by your

customer.

Always get your project team involved for major changes

and decisions to your project.

Always get your upper managements approval for major

changes and decisions to your project.

Stand your ground with your customers during negotia-

tions if the issue at hand is caused by them.

Case2.6: Project Scope Changes

I was brought in as the project manager of an advanced vehicle

development project during the detailed design phase. e previous

70

Project ManageMent case studIes

project manager had to resign from our company due to health rea-

sons. My customer was the U.S. Department of Transportation. I

had a team of six automotive design engineers working on my team.

When I came into the project, the rst thing I did was to learn the

advanced vehicle specications and the deliverables timeline. en I

learned the responsibilities and capabilities of every team member.

I went to Washington, DC from California to meet with my cus-

tomers project manager and to generate a close rapport with him.

According to the original schedule, we were about two weeks

late and the project was running over budget by 6% when I took

over. One thing that bothered me was that my customers project

manager was accustomed to phoning my teams design engineers

and ordering minor variations to the specications without my

knowledge. Nothing was documented and we were drifting away

from the original project technical specications. Apparently, the

previous project manager closed his eyes to these minor speci-

cation variations and my customers project manager got used to

forcing these minor specication changes on my design engineers.

e rst thing I did was to have an emergency team meeting.

I went over all pending redlines that were not released through

document control. e original specications were still at revi-

sion A. I asked my team members not to accept any changes to the

specications without my knowledge. If a specication change

was requested by the customer over the telephone, it did not

matter how minor the change request was, it had to go through

me. We all agreed to the new strict specication change rules. I

revised the specications to revision B and sent it to my customers

project manager for his approval.

en I asked my customers project manager to travel to our

plant so that we could nalize the revised technical specications.

I sat with him for three days face- to- face to go over each redline

and got his nal approval for revision B to the contracts technical

specications. I told him that we were falling behind in the project

due to the minor changes that were piling up. I asked him politely

to go through all the changes with me whether they were minor

or not. I told him he could talk to the individual design engineers

as many times as he wished, but if there was a change looming on

the horizon, he had to go through me. I emphasized that if the

change was urgent, I could redline the technical specications,

sign it, and release it to the responsible design engineer that same

day. en I could have the technical specications go through

71

case studIes In scoPe ManageMent

an ocial revision after piling up a couple of minor changes. If

a change were going to aect the project schedule and cost, then

I would provide him with my new schedule and cost estimates. I

then could get the change approved and implemented only after

his written concurrence with me regarding the new project sched-

ule and project cost. He agreed with me on all my scope change

procedures.

I kept the project technical specications current. I made

sure that changes went through our document control with

top priority. I always kept my design engineers on top of the

technical specications. I reviewed all the changes during our

weekly team meetings. When the project design phase was

completed after nine months, the technical specications were

at revision K.

Similar technical specication control rules apply between your

subcontractors and your company. Your customer should not be

able to go to your subcontractor directly and ask for a scope change.

Technical specications make up one of the critical legs of a

project structure. e other three critical legs of the project struc-

ture are the schedule, the cost, and the team. If one of those legs is

out of sync, the project will start to wobble, lose control, and sink.

As project managers, we will denitely fail. Keeping the scope

changes of a project under tight control without causing your cus-

tomer to become frustrated and angry is a must.

LESSONS LEARNED FROM THIS PROJECT EVENT

Taking on a project in the middle of execution is very

courageous and risky.

You have to absorb and evaluate all aspects of your new

project very fast.

You have to initiate changes to project activities that you

see as inappropriate.

It is always quite challenging to be able to change old

established habits in a project environment.

Case2.7: Bartering Minor Scope Changes

In a project, scope changes are a fact of life. Every time there is

a scope change initiated by your customer, by yourself, and/ or by

your subcontractors, you do not have the luxury of going through

several approval signatures and specication revisions. As a project

72

Project ManageMent case studIes

manager, you have to assess if a scope change aects your projects

cost, schedule, and team members. For minor eects, you do not

have to rattle the apple cart and go through a tedious approval cycle

and specication revisions. Many times, minor scope changes can

be agreed upon between two project managers. You can receive an

e- mail from your customers project manager for his approval of a

minor change you proposed or vice versa. You have to store these

e- mails in case a conict arises in the future.

I had several projects where minor scope changes occurred. I

went along with my customers requests without going through

the mind- boggling change approval cycle. My customers proj-

ect manager followed a similar process. I applied similar rules to

my subcontractors. I had to be practical. I bartered minor scope

changes with my customers and with my subcontractors. For

some picky customers project managers, I collected all minor

scope changes during the course of the project and revised all

contract specications at the closure of the project.

One example of bartering minor scope changes occurred dur-

ing the design and construction of the equipment of an oshore

oil platform. e control panel window size was specied as 10

by 16 with no tolerances. In the nal design, our control panel

window size came out to 9.5 by 15. I asked my customers project

manager for a deviation. He accepted and conrmed the new con-

trol panel window size by e- mail. He told me that he was going to

ask me for a minor change too. e customer specication asked

for a -inch thick tempered glass cover for the equipment gauge

panel. e customers engineers wanted to change from glass

material to Lexan polycarbonate with a UV-resistant exterior sur-

face. Also, Lexan oered 250 the impact resistance of tempered

glass at half the weight. I told him that I would investigate his

change oer and get back to him in two days. We had already

bought the tempered glass for the project. I called the glass vendor

and discussed the material change in our design. He said that he

would accept the return of the glass and only charge us a restock-

ing fee, which was a small amount. I then called the Lexan vendor

and got pricing and delivery information for the amount needed

for the project. e delivery time was acceptable and the pricing

was 6% higher. All these changes caused by the new material were

minor and acceptable from my point of view. I called my custom-

ers project manager and explained in detail the material change

process. I bartered his scope change and sent him an acceptance

e- mail. We did not go through a formal specication revision at

73

case studIes In scoPe ManageMent

that time. We did the update on all project specications at the

end of the project.

In another project for an advanced electric bus design and

construction, plastic hanging passenger straps and their plastic

fasteners came from the vendor in a cobalt blue color. e cus-

tomers specication asked for a gray color. I did not have time

to reject the straps and their fasteners. Lead time was an issue.

I called my customers project manager and explained the color

dierence and what it would take to change them. I had done

some minor specication changes for him in the past without a

fuss. So he owed me one. He accepted the new color and con-

rmed it by e- mail.

ese kinds of minor scope changes frequently occur especially

in software design and development. e customers project man-

ager requests several minor software specication changes almost

every day. My team members will also ask me to ask our customer

for some minor changes in software specications daily. A gentle-

mans understanding between two project managers is a must for

the project to ow smoothly and not to have to wait through sev-

eral approval signature cycles and document control procedures

for specication revisions. As the project manager, the bottom

line is to document these bartered minor specication changes in

order to avoid any conicts downstream.

LESSONS LEARNED FROM THIS PROJECT EVENT

Approval of project scope and specication changes can

be very tedious and time consuming both at your com-

pany and at your customers company.

Minor scope and specication changes can be accom-

plished in writing between you and your customers proj-

ect manager without going through the formal scope

change process.

Case2.8: Keeping Up with Software Revisions

During the execution of a project, team members use several

dierent types of software. We have to deal with internally and

externally developed software. We have to deal with customers

and subcontractors software. We have to make sure that the soft-

ware is compatible and at the same revision levels. I have come

across several issues with software during my project management

career. I will cover four such cases in this section.

74

Project ManageMent case studIes

We had an internally developed magnetic recording head y-

ing height calculator software. All of the design engineers on my

team used this software. e developer of the software was a well-

known scientist who worked in the companys research and devel-

opment group. He was good at what he developed, but he was

not meticulous in document controlling his softwares revisions

and updating his softwares user manual. My teams design engi-

neers were using dierent versions of the software and they were

making errors. I had to take this sloppy situation under control. I

went to the scientists oce and politely explained several issues

we had with his software. He accepted that his revision release

process was not perfect. He told me that he was a sloppy, but good

scientist and not a disciplined revision controller. It was going to

be hard to change his sloppy behavior at his level. So I oered

to release new versions of his software and user manual on docu-

ment control myself and to inform all users. I wanted everyone to

be on the same page when they used his ying height calculator

software. He agreed with my proposal. I took over releasing new

versions and user manual updates. All user errors diminished.

My design engineers had no issues using our internally developed

ying height calculator software.

I was heading a team in an oil platform subsystem design, man-

ufacturing, and installation project for the Russian Federation.

I used MS Projects latest revision as my project management

software. I presented our projects schedule and critical tasks to

my customer during the customer kicko meeting. Everything

was ne and dandy. My customers project manager asked me to

send him by e- mail an updated project schedule with percentage

completed task estimates every Monday. e problem was that

they could not open my MS Project le and review my updated

project schedule. My customers company used dierent proj-

ect management software, which was not compatible with MS

Project. I oered to send him my weekly updates in a PDF format.

He accepted my solution. Every week after updating my projects

schedule, I had to convert it to the PDF format and e- mail to my

customer that way.

In another project software case, a subcontractor was design-

ing and manufacturing some trolleys for a transport system on an

oil platform. My design engineers were using the most current

release of AutoCad to design the transport system. My trolley

subcontractor was using an old version of AutoCad. By the way,

75

case studIes In scoPe ManageMent

AutoCad had 28 revisions from its rst release in 1982 through

2014. e subcontractor sent us his AutoCad drawing les for

trolleys so that my design engineer could interface them into the

system drawings and verify that there were no issues. Several

callouts and dimensions on the trolley drawings were transferred

erroneously. My design engineer had to check each and every call-

out and dimension for the trolleys and correct several of them so

that our system drawings were intact. Backward compatibility of

software releases should be checked very thoroughly at all costs.

ere can be some hidden surprises in dierent software releases.

In an integrated circuit design case, my teams design engi-

neers used Verilog, a hardware description language software. My

engineers were trained at school and at work to use Verilog soft-

ware to describe functionalities of the circuit. One of my German

customers required us to use VHDL software for the integrated

circuit design for them. ey put this requirement into their tech-

nical specications. I discussed this design software choice issue

with my customers project manager. He insisted that internally,

his company only used VHDL software. at was the reason they

put this requirement into their specications. So as their subcon-

tractor, my designers had to use the VHDL software. He did not

budge at all in using the Verilog software. Our sales group missed

this critical point when they signed the contract with our cus-

tomer. Most experienced ASIC (application specic integrated

circuit) designers could use both kinds of software, but my teams

design engineers were fresh out of school and they were only

trained in using the Verilog software. I had to scramble and get

a training program going for the VHDL software. I had my six

design engineers trained in VHDL software in a crash course in

two weeks. ey designed all parts of the circuit for my German

customer in VHDL language. ey were slow at the beginning

of the project, but they became more ecient as the project pro-

gressed. At the end of the project, all my design engineers were

very thankful to me for making them learn the VHDL software.

ey became ecient in both kinds of software, which was good

for them and for my company.

e software used in a project has to be scrutinized very care-

fully. ere can be many unforeseen conicts and issues between

customers, subcontractors, and internal users. Errors generated by

using dierent software and dierent software releases can sink a

projects schedule and cost performance.

76

Project ManageMent case studIes

LESSONS LEARNED FROM THIS PROJECT EVENT

Software used during the execution of your project by

your team members, by your customers, and by your

subcontractors has to be compatible and has to be at the

same revision levels.

Internally developed software has to be released through

your document control and the softwares revision levels

have to be the same across your company.

77

3

Case studies in

knowledge ManageMent

Knowledge management is the foundation of your project. Depth

of knowledge in your team members to your subcontractors can sail

smoothly or sink a project.

My subcontractor was designing and constructing trolleys with a

10-ton load capacity for one of my projects. Contract specications

called for a bronze coating over the trolley wheels for a nonspark

operation with very tight tolerances. My subcontractor insisted that

a bronze coating with such tight tolerances was not manufacturable.

He had to educate me on bronze coating techniques. He had to show

me what was doable and what the limits of the bronze coating process

were. I was a bridge between my subcontractor and my customer in

order to get tight specications relaxed. Details of this case are pro-

vided in Case3.1.

My project management experience spanned several dierent

technology- based companies. Leading-edge technical knowledge is

the basis of an engineering project. I made sure that my engineers

were trained and excelled in state of the art technological advances.

When we bid for a project contract, we sold our technical knowledge

and expertise in that particular eld. I had to orchestrate to have an

excellent collective technical knowledge internally and through our

partners and consultants as depicted in Case3.2.

As project managers, we have to make sure that all our team play-

ers are ready and up to par for presentations in front of the customers,

regulatory agencies, inspectors, and upper management. Many factors

can spoil a presentation as shown in Case3.3.

As project managers, we should always encourage our project team

members to record their new ideas and ndings in engineering books

and have them signed and dated by a colleague so that their new

ideas and ndings can be veried and patented for the companys

78

Project ManageMent case studIes

and their benet. An interesting patent application is described in

Case3.4.

e not invented here syndrome can happen at an individual

level or at a company level. Some company ocers sometimes refuse

to change company designs or procedures by better and proven ones

available from the outside. is organizational level of not invented

here syndrome can degrade a companys performance and aect your

projects performance as shown in Case3.5.

As project managers, we have to encourage our team members to

attend technical conferences and shows as long as they are within our

companys guidelines. However, we have to establish with our team

members as to who is going where at the beginning of the project. It is

our responsibility to balance our projects responsibilities with techni-

cal conferences and shows as detailed in Case3.6.

Methods of interpretation for a callout on a drawing can be quite

dierent even from person to person in a global project as depicted in

Case3.7. Inviting the nal user of the design drawings to the design

review meeting is a must. As project managers, it is our responsibility

to bridge the gap between the designer and the user.

Paying attention to details and checking out all possible conse-

quences of a task is the rst amendment in the laws of global engi-

neering project management. In one of my global projects, I made a

mistake in believing a departed project manager and my teams engi-

neers regarding the equivalence of U.S. and European certication

standards as detailed in Case3.8.

Some project managers are closed- minded. ey are intolerant and

unreceptive to others new ideas. eir actions discourage team mem-

bers. Team members stop contributing for the good of the project.

Even some out- of- line suggestions can have value. As project manag-

ers, we should listen to and weigh all options before deciding on a

course of action in a task as depicted in Case3.9.

As a global team, your team members should be knowledgeable

of all pertinent project specications and requirements. ey have to

trickle down as required to all the people involved in your global proj-

ect as depicted in Case3.10. In a global project, a personalized trickle

down project management is not possible. In such cases, you have to

rely on your oshore managers.

79

case studIes In knowledge ManageMent

Intellectual property guidelines have to be sorted out at the begin-

ning of a project. Dos and donts have to be advised to all team mem-

bers. As project managers, we are totally responsible for honoring

the intellectual property rules of a project. My several challenging

encounters to protect intellectual property are given in Case3.11.

Case3.1: Respecifying Bronze Coating ickness on Wheels

In project management, you are constantly destined to negoti-

ate contract specications with your customer and with your sub-

contractors. You start the project with claried and agreed upon

specications during the bidding phase of the project. Most of

these bidding phase deals might be done by the sales group of your

company. When you get into the execution phase of the project

you might realize that some of the specications are not doable.

You have to inform you customers contract manager immediately

and come to terms with him or her.

I had several heated negotiations with my customers project

manager about specications during the design, construction, and

installation of an oshore oil platform system. e design was

for a Class 1 hazardous environment in which ammable gases

or vapors could be present in the air in sucient quantities to be

explosive or ignitable. According to the contract specications, all

moving part surfaces had to be nonsparking.

One of my subcontractors was designing and constructing trol-

leys with a 10-ton load capacity. Contract specications called

for a 0.010 0.001 thick bronze coating over the wheels for a

nonspark operation. My subcontractor called me one morning

and told me that his man, a sub- subcontractor, said that doing the

bronze coating would not control the 0.001 thickness tolerance

all the way around the wheel, especially at the radius between the

bottom of the wheel and the sides of the wheel. He said that he

talked with several other bronze coating people and received the

same response. e best bronze thickness tolerance they could do

around the radius was 0.005. He asked me to authorize a speci-

cation deviation for bronze coating tolerance over the radius of the

wheels. I told him that I would contact my customer immediately

and get back to him with a written specication deviation in a day.

I called my customers project manager and explained the situ-

ation. He had to discuss the bronze coating tolerance issue with

his engineer. I received a response from him in the afternoon that

80

Project ManageMent case studIes

they could not relax the tolerance around the radius because of

the Class 1 hazardous environment. His response was not accept-

able. I had to pursue this specication relaxation so that my sub-

contractor could get the trolley wheels built. Wheel radius was

a noncontact area and it did not touch the rails at all for spark

generation. I asked him if I could discuss the tolerance relaxation

issue directly with his engineer. He gave me permission to do so.

I called the mechanical engineer who put together the trolley

specications. He was a novice engineer right out of college. He

was very adamant about the bronze coating tolerance specica-

tions. I told him that no manufacturer in the United States could

comply with his tight specications around the radius of the trol-

ley wheels. I assured him and showed him on our assembly draw-

ings that there was no contact at the surface of the radius with the

rails where I was requesting the relaxation of the bronze coating

tolerance. I proposed to perform a 100% inspection for bronze

coating thickness and for pinholes in coating around the radius.

He felt better after I threw in the 100% inspection requirement

and agreed to relax the specication. He informed my customers

project manager about his change of mind after the discussion

with me and after my proposed 100% inspection requirement.

I received an e- mail conrming the bronze coating thickness

relaxation around the radius to be 0.010 0.005 with the 100%

inspection requirement in the radius region. I forwarded to my

subcontractor the relaxed specication. He was happy for the

specication relaxation, but not happy about the added inspec-

tion. He told me that the 100% inspection was going to cost him

four hours of extra inspection time for every trolley. I convinced

him that you win some and you lose some in these specication

negotiations. In this case, we won a more signicant victory. e

added burden of four hours of inspection per trolley was minor as

compared to the bronze coating thickness relaxation in a hazard-

ous environment.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we are the conduit connecting our

subcontractors and our customers.

You can learn a lot from your subcontractor about his

special area of expertise.

You have to evaluate your subcontractors change requests

in a timely fashion and help them to progress smoothly

in their portions of the project.

81

case studIes In knowledge ManageMent

Case3.2: Technical Training Needs

My project management experience spanned several dierent

technology- based companies. Leading-edge knowledge was the

basis of our strength. I had to make sure that my engineers were

trained and excelled in state of the art technological advances. When

we bid for a project contract, we sold our knowledge and expertise in

that particular eld. I had to orchestrate collective technical knowl-

edge internally and through our partners and consultants.

I was managing a project for an oil company in the Arctic

region where the temperature plummeted down to 50C. We

had to perform our stress analyses of structures for 100-year seis-

mic events at very low temperatures. I had four mechanical design

engineers on my project team. Two of them needed to come up

to speed in the latest developments in very low temperature stress

analysis. I asked these two engineers to search and come up with

a training plan for their upcoming tasks.

One of the design engineers came back to me with an exten-

sive proposal. He wanted to take two classes and attend two con-

ferences during the rst three months of the project. He wanted

to take a course online entitled, Fracture Toughness of Materials

Crack Tip Displacement eory at Very Low Temperatures.

Another course he wanted to take at a local university was entitled,

Alternating Stress Fatigue Analysis at Very Low Temperature.

He wanted to attend two conferences. One was the Oshore

Technology Conference and the other was the Mechanics of Time-

Dependent Materials Conference. ese courses and conferences

were very good ones for our technology base, but that he would have

to spend 20% of his time during the rst six months of the project

on training. Also, our companys overhead budget allowed for only

one course and one conference expense per engineer every year.

I went to his cubicle and discussed his training proposal. I told

him that I was very much in favor of getting training in leading-

edge technologies. I also emphasized that my projects sched-

ule and our companys education budget could not handle two

courses and two conferences in the next six months. I asked him

to prioritize his choices and take one course this year and the sec-

ond course next year and to make similar choices in attending

conferences. He agreed with me and decided on his course

and conference choices for the rst year. I took his choices to his

supervisor and to human resources for their approval. Everything

worked out so that my project was not delayed and one of my

mechanical design engineers was trained appropriately.

82

Project ManageMent case studIes

e second mechanical design engineer on my team had a dif-

ferent view on technology training. Online courses that he chose

were in game theory and in statistical process controls. He also

wanted to attend the International Conference on Ocean, Oshore

and Arctic Engineering in Oslo, Norway. I discussed his course

and conference choices with him. His main interests were in

mathematics. His game theory course choice did not apply to our

technology base at all. His statistical process control choice applied

only to our volume production products. His choice of a conference

in Oslo, Norway, was going to be way over the allocated budget.

I encouraged him to take courses more in line with our technol-

ogy base. I also encouraged him to nd an appropriate conference

closer to home. He did more searching and came back to me with

an online course in dynamic nite element analysis at very low tem-

peratures. He switched his conference to an international pipeline

conference in Houston, Texas. Both of his choices were approved

by his supervisor and by our human resources department.

Orchestrating the technical knowledge base of a company is one

of the most important and challenging tasks of a project manager.

Learning gives impetus and constant drive to your team members.

You have to have that ame for learning desire always lit in your

team. Broad- based technological ndings come out of collabora-

tive eorts between your team members, your company depart-

ments, your consultants, your subcontractors, and your customers.

Including the needed courses and conferences into your project

schedule for every team member should be one of your top priorities.

LESSONS LEARNED FROM THIS PROJECT EVENT

Keeping your local and international team members up

to speed with advancing technology should be top prior-

ity for an engineering project manager.

Necessary training courses and conferences should be

included in your projects schedule and budget.

Case3.3: Abysmal Performance at Design Review

I had an excellent group of ve software design engineers in a

one- year project to upgrade a data communication chip. My

customer was U.S. based. e project was moving smoothly on

schedule and within budget. I was updating my customers proj-

ect manager by telephone weekly and was sending him a weekly

document controlled progress report.

83

case studIes In knowledge ManageMent

We were scheduled to have our rst design review meeting in

two weeks at our facilities. My customers project manager, their

engineering vice president, and their two senior engineers were

going to attend the design review meeting. I arranged for our

internal design review meeting one week before the one with the

customer. First, I gave an overall status of the project. en each

of my software design engineers summarized their portions of the

project. After each presentation, I opened the oor for questions

and answers. Some engineers needed some polishing in critical

areas, especially related to complying with the customers speci-

cations. Overall, we were ready for the big day facing the cus-

tomer the following week.

e design review meeting started with initial introductions

and with small talk regarding the data communications industry.

My customers engineering vice president emphasized the impor-

tance of the chip we were designing for his company and how it

t into their future product plan. en I presented the overall

status of the project. I detailed the schedule and cost performance

indices for each task group. Afterward, my two software design

engineers presented the status of their tasks. ere were several

discussions regarding the specications and their clarications.

Everything was going according to my plan and my customer

seemed very relaxed and happy about the progress of the project.

Afterward we had a lunch break. Lunch was brought into the

conference room. After a quick bite to eat, everyone rushed to

check their e- mails and respond to their voice mails. I reserved

two oces for my customers people so that they could work in

privacy during their breaks in our facilities.

After lunch, the third software design engineer from my team

began his presentation. He started to deviate from his prepared

PowerPoint presentation and then stumbled over several speci-

cation clarication questions. I tried to intervene and correct the

situation. My software design engineer seemed to be in another

world. I was worried. I immediately asked for a recess. I took the

software design engineer to my oce to nd out what was hap-

pening to him. He started crying. He told me that he had a ght

at home with his wife. She was going to leave him. He could not

sleep all night. He was devastated. I told him that he should have

informed me before the meeting as to what was going on with

him. I could have canceled his presentation. He told me that he

had thought he could still perform well under his highly stressed

condition. He was very sorry that he botched his presentation in

84

Project ManageMent case studIes

front of the customer. I told him to go home, to get some rest, and

to straighten himself out. I told him that I would take care of the

customer and would explain his situation to them.

We reconvened in the conference room after a half an hour

break. I explained to my customer that my software design engi-

neer had a family issue and he was highly stressed out. He could

not continue his presentation. I also told them that my software

design engineer was good and reliable. I oered to visit their

facilities with my software design engineer and he could give his

portion of the presentation as soon as he straightened out his fam-

ily issues. ey agreed to my proposal and they wished a speedy

recovery to my software design engineer. e rest of the design

review meeting went well. ey said that they would release the

partial project payment to my company after we had completed

the design review at their facilities. I informed upper management

and our human resources of what had happened, but I assured

them that everything was under control and my software design

engineer was an excellent talent for our company.

Two weeks after the eventful design review meeting, my software

design engineer settled down. He straightened out his family issues

and he was back to normal. He again apologized to me and to all the

team members during our weekly team meeting. I arranged for the

continuation of our design review meeting at our customers place.

He made a good presentation there and our customer was very sat-

ised with his much- improved performance. I fully supported my

software design engineer during his unfortunate ordeal. e only

setback was the two weeks of delay for our partial payment.

After this episode, I made sure beforehand that all my team

players were up to par for presentations in front of the customers,

regulatory agencies, inspectors, upper management, and so on.

LESSONS LEARNED FROM THIS PROJECT EVENT

A project manager has to prepare his or her team mem-

bers meticulously for project design review meetings

with customers.

If something goes haywire during a project design

review meeting with your customer, immediately request

a recess to correct the issue at hand.

Right before design review meetings, make sure that all

your team members are in top- notch condition to give

their presentations.

85

case studIes In knowledge ManageMent

Case3.4: Patent Rights

In the computer disk drive industry, the cost of the drives

decreased every year while the areal density of the information

that was recorded on a magnetic disk increased exponentially.

We had to keep ahead of our competition. ere was no breath-

ing room to pause or relax for a moment. I was heading a team

of magnetic design engineers to improve the performance of our

magnetic recording heads. My team came up with several ideas

to advance the magnetic recording process. One such idea was to

reshape the magnetic head slider so that it could y closer to the

magnetic disk and also it could be shaped so that magnetic ux

losses in the slider body could be minimized. is idea came from

one of my senior physicists.

I always cautioned my engineers to write down their nd-

ings in their engineering books and have them signed and dated

by a colleague. When the patent application time came for an

improved design, being detailed in your engineering write- ups,

and signatures and dates was very important. e improved mag-

netic head design idea had to be veried. Two engineers on my

team and the senior physicist got a couple of thousand magnetic

heads made to the new design and got them tested thoroughly

for a month. We saw statistically signicant improvements in the

magnetic head performance. We were elated and I immediately

called our companys patent lawyer for a patent application.

We kept the information about our improved magnetic head

design within our team and the patent lawyer until the patent

was ocially applied for to the U.S. patent oce. We wanted to

protect our intellectual property overseas too, especially in the

disk drive manufacturing centers such as Japan, Malaysia, and

Singapore. We also applied for a patent in those countries.

e senior physicist and the two engineers sat down with the

patent lawyer for a week and detailed the present invention. At the

same time they detailed the prior art in the magnetic recording eld.

ey put together 11 drawings to describe the preferred embodi-

ment. ey summarized the improved test results of the new inven-

tion as compared to current day magnetic recording heads. en

they formulated the claims, all 43 of them. Claims were the most

important portion of the patent application. It had a layer- by- layer

structure starting with the basic claim and then expanding the basic

claim to cover all possible variations to the basic claim.

Our patent lawyer went through a couple of revisions before

nalizing the patent application. He called me after a week and

86

Project ManageMent case studIes

told me that he was ready to submit the patent application, but the

senior physicist wanted to have his name as the only inventor on

the patent application. I was very surprised at this development

because the two engineers on my team and the physicist worked

together for a month to verify the proposed invention. en they

all wrote portions of the patent as a team with our patent lawyer.

e invention was the senior physicists idea, but without experi-

mental verication his idea was worthless.

I called the senior physicist to my oce and expressed to him

how proud I was of their new invention. I told him that our com-

pany was going to benet a lot from the improved magnetic record-

ing head. Once the patent application process was completed, we

were going to announce the improved magnetic recording head to

our customers and at industry shows and conferences. I told him

that all this would not have been possible if all three of them did

not work diligently for a month as a team and veried his idea. He

argued with me that the improved magnetic recording head was

his idea. I emphasized that ideas are not patentable, but inventions

were. In order for his idea to be an invention we had to go through

a tedious test process. We had to show that his idea resulted in a

substantial magnetic head performance.

My senior physicist nally agreed to my logic and agreed to

include the other two engineers names on the inventors list.

e patent assignee was our company. After the patent appli-

cation, we announced our advanced magnetic recording head

to the world. Within a year, it became the main component in

several disk drives. My senior physicist and my two engineers

were given company appreciation plaques at a banquet for their

patent. ey were also handsomely rewarded during the annual

bonus distributions.

I have always encouraged my project team members to record

their new ideas and ndings in engineering books and to have

them signed and dated by a colleague so that their new ideas

and ndings could be veried and patented for the companys

and their benet.

LESSONS LEARNED FROM THIS PROJECT EVENT

All contributors should share names on a patentable

invention.

As project managers, we have to encourage and guide

our team members to apply for patents.

87

case studIes In knowledge ManageMent

Patents increase the value of your company and give your

team members pride and an extra spark to create fresh

and leading-edge inventions.

Processing patent applications in foreign countries can

take a long time and they can be expensive. You have

to choose countries for patent application very carefully.

Case3.5: Not Invented Here Factor

I had on my team a senior mechanical designer who was an expert

in vehicle structural design. He designed vehicle structures dur-

ing his engineering career for 20years. He always resisted ideas or

input from his teammates and from external sources. He had an

extreme case of not invented here syndrome. When we were devel-

oping a light vehicle frame for our project, he never considered using

advanced technology materials in his designs such as plastics, alu-

minum, high- strength steels, and so forth, as suggested by others.

I had extensive discussions with him regarding advances in

vehicles. I encouraged him regularly to interact with a wider vehi-

cle design community, to read related journals and to go to per-

tinent conferences. He had high self- esteem and self- condence.

He was a good engineer, but he had an attitude that if he did not

invent or design a vehicles structural component it would be infe-

rior to what he would have come up with. His was a very coun-

terproductive behavior. Vehicle and materials technology were

advancing with lightning speed. If he looked around and listened

to his colleagues he did not have to reinvent the wheel.

I had to address his not invented here factor and remedy it. His

behavior was causing our vehicle design to be inferior to our com-

petitors designs. I could not rotate him to other tasks on my team.

He was the only player in his eld in our company. I could not re

him because he was a successful engineer. He was very good at what

he produced. I had to remove him from his enclosed pedestal and

make him consider all feasible design options. I started challenging

him with fresh design perspectives and asked him to look into them

during our weekly one- on- one meetings. I forced him to go to per-

tinent technical conferences. I asked several well- known vehicle

structure design consultants to attend our design review meetings.

He started to listen to our consultants reviews. at was encourag-

ing, but I had to bring him into a new way of global thinking.

en I went a step further to remedy his syndrome and asked a

vehicle structure design consultant to generate an independent design

88

Project ManageMent case studIes

within the given parameters in order to create a design competition.

is design competition idea increased my projects budget by 5%. I

explained my design and personnel issues to my management and

received their approval to go ahead with a second design.

During the nal design review meeting with our customer,

I had both designs presented. Our customer preferred our con-

sultants design to my senior mechanical designers design. e

consultants design was more on par with the advanced vehicle

structural design concepts. e consultants vehicle structural

design used more plastics and it was lighter in weight, but a lit-

tle more expensive to manufacture than the senior mechanical

engineers design. is design competition and his designs defeat

really opened my senior mechanical design engineers eyes.

My senior mechanical design engineer came to my oce the

next day and discussed his status in our company. He was very

humbled. He was afraid that he was going to be red since he

lost the design competition. I assured him that his notions were

erroneous. I praised him as an engineer, but I reiterated that he

had to open his eyes to the outside world, soften his perception of

superiority, and utilize advances made by others. He thanked me

for initiating the design competition. He said that he learned a lot

from the consultants design. He was apologetic for his counter-

productive behavior in the past.

e not invented here syndrome can happen at an individual

level or at a company level. Some company ocers sometimes refuse

to change company designs or procedures by better and proven ones

available from the outside. is organizational level not invented

here syndrome can degrade a companys performance. Correcting

such cases might require signicant organizational restructuring.

LESSONS LEARNED FROM THIS PROJECT EVENT

It takes quite an eort to open the minds of some sea-

soned and specialized engineers.

As project managers, we have to be open- minded and

prevent not invented here syndrome among our team

members and even within our company structure.

Case3.6: A Technical Conference Conicts

with a Projects Progress

Technical conferences and shows are a part of an engineers work-

ing life. He or she has to attend all pertinent events that would

89

case studIes In knowledge ManageMent

help to stay in touch and to compete in his or her eld of exper-

tise. I always encouraged my team members to go to technical

conferences and shows as long as they were planned well ahead

of time and they were accounted for in the projects schedule. All

companies that I worked for had well- dened rules, procedures,

and budgets for attending technical conferences and shows. If you

were making a presentation at a session, you always got priority to

attend. If you already attended a certain conference or a show the

year before, management would give priority to someone else in

your eld the following year. If you had a critical deadline or an

event at the company, you had to forgo the week at the conference

or at the show. Sometimes there were company cash ow issues,

which restricted travel expenses and the number of attendees to

technical conferences and shows. I remember going to one confer-

ence on my own dime.

During my career, I came across several surprising occurrences

to my team members regarding technical conferences and shows.

All these surprising occurrences aected the progress of my proj-

ect at that time. In one such case, four out of eight engineers

working for me on a yearlong project came to my oce one day

with smiling faces and informed me that they had gotten approval

from their managers to attend the Comdex show the following

week, a computer exposition show that occurred annually in Las

Vegas. I was dumbfounded. I told them that they should have

rst consulted me before approaching their managers. My project

was in a crunch time. All they thought about was a fun week at

Comdex in Las Vegas. ey forgot all about their responsibilities

to my project. I did not want to put my weight down, cancel their

attendance to Comdex, and disappoint them. We had to nd a

solution together. I went over each engineers tasks. If three of the

engineers worked 60 hours per week for two weeks after the show,

they could catch up to the projects schedule and would not cause

any harm. So three of the engineers were okay to go, but one test

engineer had to perform crucial training for two Malaysian engi-

neers during the week of the show. e Malaysian engineers were

already at our plant and they were scheduled to y back to their

country immediately after the training. I had another test engi-

neer on my team. I decided to bring him into our meeting too to

see if he could help us out of the bind we were in. We went over the

training tasks one by one. e other test engineer agreed to take

over the following weeks training tasks. He agreed to work an

extra 20 hours the following week so that his teammate could

90

Project ManageMent case studIes

attend Comdex. at was good camaraderie in a project environ-

ment. I agreed to let four engineers attend Comdex the following

week. I advised them to approach such a technical conference or

show requests in the future in a timely fashion by considering all

of their project responsibilities.

Another surprise came from an urgent replacement presenter

at the IEEE (Institute of Electrical and Electronics Engineers)

annual conference of industrial electronics in Europe. A physi-

cist at our company became ill and could not y on an airplane

to Europe. My upper management decided to send a replace-

ment. e upper management decided to send one of my team

members without consulting me or my team member. e vice

president of engineering called me and my team member to his

oce and explained the need for the replacement presenter at

the upcoming conference in three days. According to my upper

management, my team member was the best- qualied replace-

ment presenter in our company. What could I say? What could

my team member say? We could not object to such an emergency

request. I told the vice president that I was going to sit down with

my team member and nd a way to get him to go to the confer-

ence in Europe in three days without aecting his duties on my

project. I had to take over my team members project responsi-

bilities for the next 10days. I heard that he did a great job as

the replacement presenter at the conference in Europe and my

project had a minor setback.

A strange case happened regarding a Consumer Electronics

Show (CES). Apparently, a project team member of mine was a

regular attendee at this annual show. He thought that one week

every year at CES was a given to him by our company. He did not

even bother to inform me about his CES attendance at the begin-

ning of the project. I scheduled a critical design review meeting

with our customer, which unfortunately coincided with the CES

week. He came to my oce a couple of weeks before the show and

told me that he made his arrangements to attend the CES. I was

quite surprised. I told him that we were going to have a critical

design review during that week with our customer and he had to

be present at that meeting. I insisted that everything was set up

with our customer and he could not go to the CES. He had to

cancel all arrangements that he had made for the show. He was

very upset, left my oce, and went to his supervisor to complain.

His supervisor called me to discuss the conict. After I explained

the details of the case, his supervisor agreed with me that critical

91

case studIes In knowledge ManageMent

design review took priority and canceled his engineers trip to

CES. It was an unfortunate coincidence, but if he had declared

his plans to me at the beginning of the project, then I could have

scheduled the critical design review accordingly.

As project managers, we have to encourage our team mem-

bers to attend technical conferences and shows as long as they are

within our companys guidelines. However, we have to establish

with our team members who is going where at the beginning of

the project. It is our responsibility to balance our projects respon-

sibilities with technical conferences and shows.

LESSONS LEARNED FROM THIS PROJECT EVENT

Every team members schedule for attending technical

conferences and shows should be on our project schedule

from the start.

We, as project managers, have to balance fairly an engi-

neers wish to attend a technical conference and/ or a

show with his or her project responsibilities.

Case3.7: Redimensioning of Design Drawings

Generating design drawings for a project can be very tricky some-

times. If the construction of the parts will be done in Europe,

it is advisable to use ISO 128-21 standards. If the construction

of parts will be done in the United States, it is advisable to use

ASME 14.5 standards. If you study both standards, they look

similar, but there are many subtle dierences. A machinist in

Europe can misinterpret concentricity, symmetry, and so on, call-

outs on a drawing that is dimensioned according to ASME 14.5

standards, since they are trained and use drawings constructed

according to ISO 128-21.

In one of my projects we were designing several large and thick

steel plates with precision holes and slots to be used on an oil plat-

form. My engineers were trained in geometric dimensioning and

tolerancing per ASME 14.5 standards. We completed the design

drawings for the steel plates and our purchasing department solic-

ited bids domestically and internationally to build 20 steel plates.

Our purchasing department found the best deal with a French

company and subcontracted them to build the steel plates. In the

past, this French company had a good track record with our com-

pany for building complicated steel structures.

92

Project ManageMent case studIes

Our purchasing agent and I started to have weekly teleconfer-

ences with the French subcontractor. During the rst call, they

asked us to update our drawings to relocate the datum refer-

ence planes, since their large milling machines could not locate

the precision holes and slots from the ones on the drawings.

We immediately updated four drawings, released them through

document control, and e- mailed them in four days. e French

subcontractor started to machine the rst article. During our tele-

conferences, they assured me that there were no other issues with

dimensioning and tolerancing of our drawings.

Two weeks passed and they were ready for the rst article

acceptance. I sent one of my quality engineers to France for the

rst article acceptance. During the rst article acceptance mea-

surements, my quality engineer discovered that the symmetry of

the holes was out of tolerance for what was called out on the draw-

ings. e French machinist misunderstood the symmetry toler-

ancing in the ASME Y14.5 standard. My quality engineer had to

reject the rst article. Luckily, I had a design engineer on my team

who was also trained in ISO 128-21 standards. I asked him to

update all four drawings again. is time he made sure that all

the dimensions and tolerances were called out per ISO 128-21.

I e- mailed the new revised drawings to France. ey rebuilt

the rst article. I sent my quality engineer to France again. e

French subcontractor passed the rst article dimensional inspec-

tion with ying colors the second time around. Finally, we got

our French subcontractor to build correctly our 20 large and thick

steel plates with precision holes and slots. e plates were delayed

three weeks for delivery. Fortunately, completion of the plates was

not on the critical path of the whole project.

In a global industry, as the project manager, you have to be

cognizant of the standards and procedures that are used in that

particular country. is applies to dimensioning and tolerances,

to certications, to material origins, to machines used for certain

processes, quality control practices, and so on. You would be sur-

prised to nd vast dierences from country to country.

What I should have done was to have the French machinist

review all four drawings for every dimension and tolerance during

a teleconference. I had to make sure that he was on the same page

as my design engineer. en I should have asked our purchasing

department to reword the contract.

93

case studIes In knowledge ManageMent

Methods of interpretation for a callout on a drawing can be

quite dierent even from person to person in a global project.

Inviting the nal user of the design drawings to the design review

meeting is a must. As a project manager, it was my responsibility

to bridge the gap between the designer and the user.

LESSONS LEARNED FROM THIS PROJECT EVENT

Your design drawings and user manuals have to be user-

friendly in a global project environment. Users in foreign

countries have to be able to understand and be able to

interpret them easily.

Always invite nal users of your design drawings and

user manuals to your design review meetings.

Case3.8: Component Certication

I took on a project in the middle of the design phase because the

original project manager was leaving the company. e project

was to design and build control consoles for a hazardous envi-

ronment with combustible gases and vapors. Our customer was

in Europe. e departing project manager and I had ve days

of overlapping period so that he could bring me up to date on

all signicant aspects of the project. e departing project man-

ager introduced me to every member of my new team. ere were

ve engineers in the group. ey were all experienced in their

specialties. e departing project manager, our customers project

manager, and I had a two- hour videoconference in order to make

a seamless transfer of responsibilities. e departing project engi-

neer went over all the critical specications with me. He briefed

me on the schedule, cost structure, and status. Everything seemed

to be in order and progressing smoothly.

All electrical components, enclosures, and assemblies had to be

certied for a Class 1 and Division 1 hazardous area environment.

Electrical control enclosures were going to be used outdoors. ey

had to be protected against corrosion, windblown dust and rain,

splashing water, and ice formation. e departing project manager

assured me that as long as the control enclosures were NEMA 4X

(U.S. National Electrical Manufacturers Association) certied,

we did not have to get recertication according to the European

standards, namely IP56 (ingress protection rating in Europe).

94

Project ManageMent case studIes

My team completed the design on time. We bought components

that were certied both in the United States and in Europe for a

Class 1 and Division 1 hazardous area environment. e European

certication standards were written by IEC, Electrotechnical

Commission International. e only issue arose in the electrical

control enclosures. One of the assemblers notied me that the con-

trol enclosures were only NEMA 4X certied. I called the control

enclosures manufacturer and talked to them about the European

IP56 certication of their product. ey told me not to worry

because both NEMA 4X and IP56 certications were equivalent.

I received the same response from my teams engineers.

My last stop was our customers project manager. I called

him and asked him the same certication question about elec-

trical control enclosures. He cautioned me that both hazardous

area standards were very similar, but our contract called for cer-

tication of all electrical components, enclosures, and assemblies

according to European Union IP56 standards. He would not

budge on the electrical control enclosures certication. We had to

return all 15 control enclosures back to their manufacturer with

a minimum of cost penalty. I mobilized our purchasing depart-

ment and my teams engineers to source 15 control enclosures

that complied with our design and that were certied in Europe.

Delivery time was also an issue. We had to have these control

enclosures in three weeks time in order to meet our schedule. I

asked our customers project manager for his suggested sources

too. He could not be of much help.

After a week of frantic searching, we nally found a small elec-

trical control enclosure manufacturer in Germany who was will-

ing to build and test for us 15 control enclosures according to our

design and to the European hazardous area standard IP56. is

was quite a relief to me and to my team. I had to pay extra for

transportation to get them airfreighted to the United States on

a priority basis. In the end, we were delayed a week in delivering

of our product, which complied completely with the European

hazardous area standards including assemblies. I had to send a

400-page binder of compliance certicates to our customer along

with our deliverables.

It was my mistake to believe the departed project manager and

my engineers regarding the equivalence of U.S. and European

certication standards. I should have emphasized that all compo-

nents and enclosures were to be checked for IP56 standard certi-

cates at receiving inspection. ere were some minor dierences,

95

case studIes In knowledge ManageMent

but the bottom line was my customers specication, which

required that all electrical components, enclosures, and assem-

blies had to be certied for a Class 1 and Division 1 hazardous

area environment according to the IP56 standard.

LESSONS LEARNED FROM THIS PROJECT EVENT

Taking on a project in the middle of execution can be very

tricky. You have to have a long enough transition period

so that the project management transfer is seamless.

Certication standards in other countries can have slight

dierences from the ones we have in the United States.

Case3.9: A Practical Solution to Fluid Flow Simulation

I was a senior scientist on a team that designed and built a rotary

combustion engine for passenger vehicles. Our team was strug-

gling to optimize the design of engine housing coolant ow

deectors. ese ow deectors gave direction and increased tur-

bulent energy of the engines water coolant and thereby increased

convection heat transfer capability from combustion chambers.

ese ow deectors had to prevent any stagnant ow regions,

had to prevent cavitation, and had to prevent bubble formation on

housing walls. Optimized ow deectors decreased engine hous-

ing wall temperatures and therefore thermal stresses in the cast

housing material.

We had several team meetings regarding the ow deectors

optimization approach. Our teams project manager wanted to use

an advanced uid ow simulation program that was going to be

run for optimization by an expert consultant. en we were going

to verify the consultants uid ow simulation program results in

a laboratory at a nearby university by building a clear plexiglass

model of the engine housing with optimized ow deectors. is

approach was going to take three months and was going to be

expensive for the project.

I proposed a simpler solution for the optimization. I told my

team that we could build an engine housing model with several

dierent ow deectors from clear plexiglass and test them visu-

ally by running water at dierent ow rates through them. We

could watch and take pictures to see if there were any stagnant

ow regions. We could modify the ow deectors easily and rerun

the ow experiments until we found the optimum ow deec-

tor design by trial and error. My trial and error experimental

96

Project ManageMent case studIes

approach was going to take about one month and be one-quarter

of the cost of the simulation program optimization eorts.

Our teams project manager insisted on using the simulation

program optimization. He was determined in that approach from

the beginning of the project. I discussed with him several times my

trial and error experimental approach in the laboratory. He never

listened to my quicker, cheaper, and simpler optimization sugges-

tion. He was the leader of our team. We had to go along with his

choice. e program manager contracted an expert consultant in

uid ow simulations. e consultants simulation optimization

took three months. en we had to build a model of the engine

housing with optimized ow deectors and test it. Simulation

optimization verication eorts took another two weeks. e

results were very discouraging. ere were two areas in the engine

housing where the water ow stagnated. However, ow simula-

tions showed normal turbulent ow in those two stagnant regions.

We wasted three and a half months and a lot of the projects funds

without success. We had to start the optimization process over

again. is time, the project manager came to me and confessed

that he should have listened to my proposal in the rst place.

e project was delayed for no good reason. Our project man-

ager was grilled by our upper management too. Upper manage-

ment got the gist of my practical proposal for a ow deectors

design optimization and got after our project manager for refus-

ing to go along with my proposal. ey were denitely stressful

times in our project.

We went back to optimizing the ow deectors design using

the trial and error experimental method that I had outlined for

the team. We had the engine housing model already. We only had

to change deector shapes and positions. After two weeks and

14 trials, we narrowed the deectors design to their optimized

shapes and positions in the engine housing. At our team meet-

ing, the project manager again thanked me for being practical and

achieving such a quick solution to a dicult problem.

Listening to others and evaluating all of the input are the most

important virtues of a good project manager. Some project man-

agers are very closed- minded. ey are intolerant and unrecep-

tive of others new ideas. eir actions discourage team members.

Team members stop contributing for the good of the project. Even

some out- of- line suggestions can have value. As project manag-

ers, we should listen to and weigh all options before deciding on

a course of action.

97

case studIes In knowledge ManageMent

LESSONS LEARNED FROM THIS PROJECT EVENT

Some project managers are not good listeners and they

want things done their way.

As project team members, we should not get discour-

aged when a project manager shoots down our ideas. We

should be empowered by our projects goals and keep

providing constructive input to our team.

Case3.10: Traceability of Heat Lot Numbers

I was the project manager for a two- year project involving compo-

nent design, manufacturing, and installation for a new oil platform

destined for the Gulf of Mexico. e project technical specica-

tions and requirements were compiled into a 400-page handbook.

e handbook contained the scope of the project, component

performance criteria, classication, certication and regulation

requirements, operational life requirements, fatigue life require-

ments, operation criteria, installation criteria, environmental cri-

teria, transit conditions, corrosion protection and coating criteria,

marking and tagging criteria, quality plan requirements, inspec-

tion requirements, testing requirements, design drawing and

design calculations requirements, project management, reporting

and scheduling requirements, dimensioning, weights and center

of gravity requirements, shipping requirements, ship yard com-

missioning and preservation manual requirements, installation,

operation and maintenance manual requirements, and certica-

tion data book requirements.

As the project manager, I had to absorb every word in that

handbook and distribute the projects technical specications and

requirements to every pertinent team member. Some specica-

tions and requirements were hidden in the layers of the handbook.

For example, testing requirements were further broken up into

functional tests, load tests, nondestructive tests, mechanical tests,

electrical tests, and environmental tests.

As a team, we were able to deal with all of the specications

and requirements except one, namely, traceability of some raw

materials to their origins. e project requirements required

complete traceability of raw materials for steel plates, forgings,

castings, fasteners, pins, and shafts from their original heat lots

to nished products. We had to stamp the heat lot number and

the vendor designation on the part. If we could not use stamp-

ing due to component size or due to an available surface, we had

98

Project ManageMent case studIes

to tag the part with the traceability information. I warned our

manufacturing manager about this traceability requirement at

the beginning of the project. However, this project requirement

information did not trickle down to our machinists. e machin-

ists worked on the special steel to manufacture the required com-

ponents for two months. After machining, all original heat lot

information for the special steel pieces were lost. We could not tell

which nished component came from which special steel heat lot.

We purchased the special steel for the project from two dierent

customer- approved steel vendors and according to our receiving

inspection records they were produced in ve dierent heat lots.

I called an urgent meeting with our manufacturing manager,

receiving inspection manager, stockroom manager, and our six

machinists. We brainstormed the issue at hand. e stockroom

manager and our six machinists were very helpful. ey came up

with a good idea for how to trace the special steel back to its origi-

nal heat lot. When a machinist requested a piece of the special steel

from our stockroom, the stockroom personnel recorded the date,

the heat lot information, vendor information, and the machinist

who received it. By going back to these stockroom records, with

the help of our machinists, we were able to determine where the

original material came from for every nished component. e

machinists had to remember when they built each part during the

last two months. By using the elimination method, we were able

to pin down every nished components heat lot number and ven-

dor. Every machinist stamped or tagged his own nished com-

ponent. e manufacturing manager was very apologetic about

missing a simple requirement for my project.

After this episode, I made sure that every project requirement

detail was understood and complied with by the people who did

the work. I discussed the project requirement with their manag-

ers, but more importantly with every one of them who did the

work individually. is kind of personalized trickle down project

management was not possible in a global project. In such cases,

I used written e-mails and also I had to verbally remind the o-

shore managers several times to make sure that their people knew

and complied with the applicable project requirements.

LESSONS LEARNED FROM THIS PROJECT EVENT

A projects technical specication and requirements can

be very complicated and tedious to understand. Some

technical specications and requirements can appear in

99

case studIes In knowledge ManageMent

several dierent customer documents and they can con-

tradict each other.

Every pertinent technical specication and requirement

has to trickle down to its user on our team.

As project managers, it is our responsibility to make sure

that every technical specication and requirement is

complied with during the execution of our projects.

Case3.11: Protecting Intellectual Property

During the execution of a project intellectual property guidelines

can be very complicated for a project manager to comprehend and

to apply. Before the project begins, the project manager has to

make sure that he understands all intricacies governing intellec-

tual property under his projects umbrella. If he needs clarica-

tions about intellectual property rules he immediately should seek

help from his companys lawyers and from his customers project

manager. Patents, copyrights, trademarks, and secrecy rules gov-

erning his project should be crystal clear to a project manager

before the execution of the project starts.

In an advanced automobile design project, my company had to

defend at our cost, indemnify, and hold harmless our customer and

my company against a liability suit that a component manufacturer

opened against us. e lawsuit was for infringement of a patent that

my team members and I had overlooked for using a component in

contention for our design without the component manufacturers

permission and royalty payment. My company lost the case. at

was an expensive lesson I experienced during my career. After that

experience I was very careful to check all patents and pros and cons

before using someone elses intellectual property in my projects.

In another intellectual property case, an engineer on my team

wanted to apply for a patent. His new idea and design were a result

of technical input from our customer. I told him that he could

not apply for that patent because his invention was mainly based

on technical information received from our customer. erefore,

according to our contract his invention was the property of our

customer. I had to promptly notify my customers project manager

about his invention. After several discussions with my customers

project manager and his companys lawyers, we agreed to le a

joint patent for the new invention as long as my company paid for

the patent application expenses. My engineer, my customer, and

my company were all satised with the nal resolution.

100

Project ManageMent case studIes

In another intellectual property case, my company had to share

my project teams inventions with my subcontractors company.

is subcontractor was crucial for our design. Before signing a

contract with us, the subcontractor requested that we share all

inventions that would result from our joint design. My companys

lawyers, my subcontractors lawyer, and I had several meetings on

this issue. We were doing a substantial portion of the design. We

negotiated that any inventions resulting from our design would

be applied for jointly. However, royalties coming in from such

patents would be split 80/20, namely, we were going to get a major

share of all the royalties. We signed the contract. Four patents

resulted from our joint design eorts. Both parties were satised

with the shared intellectual property rights.

Protecting a customers intellectual property can require

extensive planning and can be very time consuming in some proj-

ects. In such a project, I had to form a team which was totally

separated from my companys other duties. Everyone on my team

was 100% dedicated to that secretive and advanced technology

project. Even our oces were relocated to a remote corner of the

company. Coded locks were put on the entrances to our oces.

Only my team members and I could enter that remote area. All

design drawings and personally assigned laptop computers were

kept in a vault. Drawing copies were made only by receiving writ-

ten permission from the customers representative. I had to make

sure that all drawings and laptop computers were safely in the

vault before I left for the evening. We were sworn not to discuss

technical details of that project with anyone outside of our team.

e manufacturing side of that project was another nightmare.

Whole manufacturing and test areas were isolated by opaque

plastic walls. No one was allowed to enter those restricted areas

except the operators and the engineers who worked for that secret

project. We were constantly monitored by our customers repre-

sentatives. We had some minor security breaches during the two-

year project. My team members and I were very happy when the

project was completed. e whole project environment was like a

high-security prison. However, it was a very lucrative project for

my company. We were able to protect our customers intellectual

property with very detailed planning and control.

Intellectual property guidelines have to be sorted out at the

beginning of a project. All of the team members should be advised

about the dos and donts. As project managers, we are totally

responsible for honoring the intellectual property rules of a project.

101

case studIes In knowledge ManageMent

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we are responsible for protecting

the intellectual property of our company, our customers,

and our subcontractors.

At the beginning of a project, all intellectual property

protection rules pertaining to our project have to be

explained to our team members.

Protecting intellectual property in a global project envi-

ronment requires very tight controls

103

4

Case studies in

sChedule ManageMent

Schedule performance management of a global project is very time

consuming for a project manager. Unexpected delays at your subcon-

tractors, at your suppliers, and in information ow can devastate your

projects progress.

I got devastating news from our subcontractor that his special steel

supplier in Germany delayed their delivery another four months due

to a large order from China. e whole steel factory capacity was ded-

icated to China for several months and our subcontractors small order

was pushed out another four months, which impacted my projects

schedule very unfavorably. I had to scramble to straighten out this

issue in Case4.1.

A French subcontractor in one of my projects informed me with

regret that his machinists voted to strike and they did not accept my

subcontractors terms for the new contract. An uncertain delay in

the subcontractors delivery schedule surfaced. I had to scramble to

nd another resource to replace my subcontractor in the middle of my

project as detailed in Case4.2.

Managing a monster- size project schedule for a large project can

be very tedious and time consuming. A project manager should break

down the monster project schedule le into manageable major task

groups and subcontractor groups. en he or she should create a mas-

ter project schedule that includes the results of major task groups,

all critical document delivery dates to the customer, all internal and

customer design review meetings, and the customers acceptance test

dates and payment milestones. I present a large such challenging proj-

ect in Case4.3.

Global projects such as the one detailed in Case4.4 put a lot of

excessive strain on a project manager. Precise time management in dif-

104

Project ManageMent case studIes

ferent time zones is the only way to smooth out and eectively monitor

the progress of your project.

Critical path tasks need more attention and more detailed scru-

tinizing during the execution of a global project. Case4.5 details

changes and their impact on a critical path task that heavily impacted

several of my global projects.

Estimating task completion percentages periodically can be very

tricky in a global project as shown in Case4.6. As global engineering

project managers, it is our responsibility to determine task completion

percentages as accurately as possible. Our schedule and cost perfor-

mance can give false implications about the health of our projects to

us and to our upper management.

Case4.1: Material Delays in a Hydraulic

Cylinder Manufacturer

I was assigned to a yearlong project to build automated heavy

equipment movement systems for a Norwegian customer. Final

testing and acceptance of the systems were to be in California.

en the systems were to be surface shipped to Malaysia for

installation and usage. I had several critical subcontractors in the

project. ese subcontractors were controlled by our purchasing

agents on a part- time basis and these purchasing agents reported

to me for the project on a dotted line. A Dutch subcontractor

had six months to complete 20 high- pressure hydraulic cylinders

for the project and surface ship them to California. is Dutch

subcontractor also had a good track record with our company for

on-time and quality product delivery.

I let our purchasing agent control this subcontractor by calling

them every two weeks and getting updates on the progress of the

project. At the end of the second month, we learned that the spe-

cial steel provider from Germany for the casings of the hydraulic

cylinders would delay their delivery by a month. Our subcontrac-

tor assured us that even with this material delay he would com-

plete the project on time. We accepted the one- month delay for

the special steel delivery and the fabrication start-up. Our subcon-

tractor had all other components and materials in house to start

the fabrication.

Another month passed. We got devastating news from our

subcontractor that their special steel supplier in Germany delayed

the delivery another four months due to a large order from China.

105

case studIes In schedule ManageMent

e whole steel factory capacity was dedicated to China for several

months and our subcontractors small order was pushed out another

four months. is push out of raw material was totally unaccept-

able. After several telephone conversations with our subcontrac-

tor, the best he could do was to deliver the completed and tested

hydraulic cylinders by airfreight three months late to our facilities

in California. is would delay the delivery of assembled, tested,

customer- accepted, and airfreighted systems to our customer in

Malaysia by two months. A two- month delay in the project would

cause heavy liquidated damages and a black eye to my company.

I raised the emergency ag immediately. I called an emergency

upper management meeting to discuss the grim situation and to

take the necessary steps to remedy the issue. I also invited the pres-

ident of our subcontractor to join the meeting by teleconferencing.

I depended totally on this subcontractor who had an excel-

lent track record and I did not put in more rigorous controls to

monitor their progress and to understand in detail the risks they

were taking. I prepared for the emergency upper management/

subcontractor meeting the next day. I put together several options

to remedy the issue. I prepared a risk analysis and cost benet

analysis for each option.

e rst order of business was to take full control of the

situation and not depend on the subcontractor. I was given full

responsibility to establish such control over this subcontractor.

e company provided the purchasing agent in charge of the sub-

contractor to report to me on a full- time basis. I also requested a

full- time quality engineer by name. I sent him to the Netherlands

after getting the Dutch subcontractors permission to monitor the

subcontractor on location.

One option was to nd another hydraulic cylinder manufacturer

who had the special steel material in stock and cancel the contract

with the Dutch subcontractor. is option was dropped during the

meeting because the hydraulic cylinder design was already com-

pleted by the Dutch subcontractor and it was approved by us, by

our customer, and by the regulatory agency. To start everything

from scratch after three months into the project was not acceptable.

Another option was to nd the special steel at a distributor at

a premium price and airfreight it to California for manufactur-

ing and testing per the Dutch contractors design drawings. is

option was also dropped since it was going to strain our manu-

facturing department and this new load on our manufacturing

would delay other projects.

106

Project ManageMent case studIes

Another option was to go to the German steel mill with our

subcontractor and negotiate for overtime work and extra funding

for faster delivery. is option was also dropped since our special

steel order was a small dent in their total steel production scheme.

Our subcontractor had dealt with them face to face many times

and the German steel producer would not budge.

A good option that everyone agreed upon was to search the

world for this special steel during the next week to see if we could

nd it at a premium price. e steel had to be manufactured in a

customer- qualied country. e steel had to have material test cer-

ticates for the regulatory agency. We agreed that we would share

the premium price for the purchase of this special steel with our

subcontractor and also share airfreight costs to the Netherlands

with them. My company assigned me three full- time purchasing

agents to search for this material all over the world.

After the emergency meeting, I called my customer in Norway

and explained the unfortunate delays in the special steel delivery.

I outlined the steps that we are taking along with our subcontrac-

tor to remedy the issue. Our customer was very upbeat with our

proactive steps. e project manager at my customer informed me

rst verbally and then in writing that they would accept a month

delay in the delivery of the completed systems in Malaysia with-

out applying any liquidated damages to my company. is was

great news for my company.

It took us three days to nd the special steel with all the

required test certicates at a secondhand supplier in Houston,

Texas, at a premium price. We split the extra cost of the material

with our subcontractor and we airfreighted 30 tons of mate-

rial to the Netherlands. My quality engineer on-site, the Dutch

subcontractor, and I worked on a modied fabrication, test, and

acceptance schedule for the hydraulic cylinders. e Dutch sub-

contractor worked very diligently and overtime, when necessary,

with my quality engineer watching over every step of the way.

ey completed the hydraulic cylinders one month late per the

new schedule and airfreighted them to California for nal assem-

bly and testing. We were exactly a month late in the project when

the completed systems were ready for customer acceptance. When

my customer came to our facilities to accept the nal systems,

they informed us that the overall project had been delayed so we

did not have to airfreight the completed assemblies to Malaysia.

I wished I knew about this project delay a little earlier. However,

we completed the systems one month late and they were accepted

107

case studIes In schedule ManageMent

by our customer without a hitch. Acceptance sign o was a big

milestone payday for my company.

As the project manager, I learned a lot from this special steel

sourcing asco by our subcontractor. Even if my subcontractor

was a very dependable one, I should have implanted my own engi-

neer at their site and gotten daily updates on this critical item. I

should have asked my subcontractor to line up a backup source for

the special steel if the German one failed to deliver. Also, I should

have required our purchasing department to include late penalty

clauses for critical milestones such as the special steel delivery

date to our subcontractors contract.

On the positive side, the issue was solved by working very

closely with the subcontractor. I helped them all I could to remedy

the issue. My company was generous enough to share the extra

costs for the material and shipping. One thing I did not allow

was for my company to squeeze the subcontractor into a corner

and beat him up to get the job done. Subcontractors are crucial

parts of the project team. Working together and helping them in

all aspects of their portion of the project is a must for a healthy

project conclusion.

LESSONS LEARNED FROM THIS PROJECT EVENT

Follow your subcontractors progress very closely.

Always implant your people at your crucial subcontrac-

tors to monitor on- site progress of your project.

If your purchased items are a small sh in a big pond, per-

sistently make sure that your items are not pushed aside.

Always consider several feasible options in order to get

out of a bind in a project.

Case4.2: Union Strike in France

I was managing a project to build an oil platform mooring system

for a new rig in the Gulf of Mexico. ere were several design

engineers, subcontractors, and consultants on my team. One of

the subcontractors was in France. ey were assigned to build

high- pressure hydraulic cylinders per our specications. e proj-

ect started on time and the rst couple of months went without

any incidents. In the beginning of the third month, I received a

telephone call from my subcontractors project manager in France.

He told me that his machinists might go on strike in the next

couple of weeks. ere was a slowdown in their work pace during

108

Project ManageMent case studIes

contract negotiations. He assured me that his management was

negotiating with the machinists union and they would settle their

dierences before their contract deadline.

I started to get worried. I informed my upper management

about the potential strike in France. We had no choice but to wait

for the results of their negotiations. A couple of days passed and I

received no update from my counterpart at the French subcontrac-

tor. Finally, I called him and explained my concerns about delaying

the hydraulic cylinders for my project. He again assured me that

they were at the nal details of the contract negotiations. He was

going to let me know the results in 24 hours. e next day came and

I anxiously waited for his phone call. e telephone nally rang at

9a.m. and my counterpart at the French subcontractor informed

me with regret that the machinists voted to strike and they did not

accept the companys terms for the new contract. He again assured

me that this would be a short- term strike and work slowdown and

the strike would not aect the delivery of my hydraulic cylinders.

I immediately had an emergency meeting with my upper man-

agement and our purchasing department director. During the

meeting, I proposed a couple of options to get out of the French

strike dilemma. Before the meeting I discussed the level of com-

pletion of our hydraulic cylinders with my subcontractors proj-

ect manager. All components, assemblies, and machining were

about 40% complete when the strike started. One option was to

ship everything to our plant in the United States and to complete

them there. Our president assured me that we would not have the

capacity to complete the job on time. en we decided to look for

other high- pressure hydraulic cylinder builders around the world

that had enough capacity to complete our job in a timely fashion. I

was going to lose another week or two while negotiating and sign-

ing a contract with a new subcontractor. Also, partially completed

cylinder shipments from France to our new subcontractor would

have taken at least a week with an expedited shipment. We gave

our purchasing director top priority to nd a new subcontractor to

complete the hydraulic cylinders for my project.

e purchasing director started to contact all the other hydrau-

lic cylinder manufacturers that we had dealt with in the past.

Luckily, he found one in the Netherlands that had enough capac-

ity to complete our job on time. ey negotiated the terms of the

contract by teleconferencing and signed the contract online. I

informed my customers project manager of what was going on

with the hydraulic cylinders project. He agreed with my approach

109

case studIes In schedule ManageMent

and he even suggested several hydraulic manufacturers to our

purchasing director. We called our subcontractor in France too

and told them what we were trying to do. ey agreed with us

too, since they could not propose any other viable option to us.

We paid 40% of our contract to our subcontractor in France. ey

agreed to truck the partially completed hydraulic cylinders to our

new Dutch subcontractor on their own nickel.

Two trucks had to be loaded at the French subcontractors

plant at night in order not to interfere with the strikers during

the day. With a two-week delay, the partially completed hydraulic

cylinders arrived at our new Dutch subcontractors facilities. e

Dutch subcontractor completed, tested, and shipped the hydraulic

cylinders to us on time. e French subcontractors strike lasted

10weeks. If I had stayed with the French subcontractor, my proj-

ects entire schedule would have been destroyed. I would have had

a very dissatised and angry customer even if the contract with

our customer covered us as harmless for unforeseen strike events.

ese kinds of unforeseen events can occur on any project. As

the project manager, it is my responsibility to nd other routes to

bypass these blockades. Extra eorts made to move the project

along smoothly make my customer and my upper management

very happy and raise their condence in me.

LESSONS LEARNED FROM THIS PROJECT EVENT

Labor unions are very strong and labor strikes are very

common in some countries.

Changing subcontractors in the middle of a project can

be very risky and requires very detailed and accurate

planning.

Sometimes, as project managers, we have to make

bold moves in order to get our projects going in the

right direction.

Case4.3: A Scheduling Challenge

I was assigned to manage a data communication chip design and

test project with a team of 16 engineers and two international

subcontractors. e project duration was a year. Initially, I put

together a project schedule in a week that included all domestic

and international resources, all dependencies between tasks, all

critical document delivery dates to the customer, all internal and

customer design review meetings, the customers acceptance test

110

Project ManageMent case studIes

dates, and payment milestones. I also included all the pertinent

holidays and forecasted special events for each team member. e

whole project schedule ended up being a 570-line monster le on

MS Project. I did not have anyone helping me on scheduling. e

schedule was a very dynamic document. I had to update it daily

and I had to present it to my team, to my upper management, and

to my customer on a weekly basis. e schedule updates, estimat-

ing work- performed percentages, and nding errors in the sched-

ule took a tremendous amount of my time. I was falling behind in

managing my teams people and my subcontractors.

Work scheduled and work performed were critical inputs to my

earned value analysis for my project. I had to be fairly accurate in

my work- performed estimates. ese work- performed estimates

went directly into my projects schedule performance indices and

cost performance indices. My management judged my projects

progress and health with these indices.

I had to do my scheduling in a more ecient and a more accu-

rate way. I decided to break down the monster schedule le into

12 major task groups and two subcontractor groups. Each major

task groups schedule had about 40 tasks. en I created a mas-

ter schedule that included the results of major task groups, all

critical document delivery dates to the customer, all internal and

customer design review meetings, the customers acceptance test

dates, and payment milestones. I only presented the master sched-

ule to my team, to my upper management, and to my customer.

If they had questions about the progress being made in a major

task group or at the subcontractor, I also presented that particu-

lar schedule to them.

is breakdown of the total schedule helped me a lot in manag-

ing the updates to schedules and reduced my time to almost half

in dealing with my scheduling responsibilities. It was much easier

to update smaller schedules and to nd errors in them. During

the review meetings, my team, my upper management, and my

customer appreciated dealing with the master schedule. Schedule

review times in the meetings got shorter. On average, we were

spending an hour going over the monster schedule. With the mas-

ter schedule, the schedule review times averaged about 20 minutes.

Creating the initial schedule took about a week. I had to dis-

cuss and nalize each tasks duration, order, and dependencies

with its owner. Each team member had to buy in to what he or she

was committing to accomplish in a given time. Everyone on the

team had a dierent work pace and work experience. It was crucial

111

case studIes In schedule ManageMent

to understand the work performance rate of every one of my team

members. I had to do the same thing with my two international

subcontractors by teleconferencing. I included an 85% work pro-

duction eciency factor to the schedule. I had to include extensive

training time for ve of my novice team members. I tried to keep

each tasks duration between one and three weeks so that the task

progress estimates could be predicted with accuracy. I included

all the observed holidays for my domestic and international team

members. For each team member, I included his or her personal

time- o days during the project duration. Gathering all this data

to input into MS Project was painstaking. It was worth the entire

week I spent to gather all the pertinent data for scheduling.

For a large project like this data communication chip design

and test project, I should have asked for a scheduler from my man-

agement to help me. Such a person was not in my project budget.

He or she would have had to charge the company overhead or

erode my projects margin. In hindsight, gathering all the sched-

uling data from my team members and from my international

subcontractors gave me a good insight on everyones capabilities

and work performance rates.

LESSONS LEARNED FROM THIS PROJECT EVENT

A well- prepared project schedule is a shining light on the

health of your project.

A large project schedule can be very cumbersome to

update daily by a project manager.

A large project schedule can be easily broken down into

smaller ones and a master one.

Work production eciencies should also be included

into necessary tasks with care.

Case4.4: Task Management between Dierent Times Zones

I had a challenging project management responsibility for a global

project that spanned ve dierent time zones. e chip design

project lasted for 18months and covered the software design and

verication phase, the chip prototype construction phase, and the

volume production start-up phase. My customer was in Munich,

Germany. I had four chip design engineers working for me in

California. My engineers were assigned to design major segments

of the chip and also test the functionality of the whole design. A

segment of the chip was being designed by a subcontractor at the

112

Project ManageMent case studIes

Research Triangle, North Carolina. A second segment of the chip

was being designed by an Indian design company in Bangalore.

e prototypes of this high- performance chip were scheduled to be

built at a specialty foundry in Tokyo, Japan. Volume production was

destined for a semiconductor fabrication plant in Penang, Malaysia.

Time management in this global project environment was a

very strenuous task for me. e project started in June during day-

light savings time. My daily workday schedule was as follows:

Call customer in Munich: 78a.m. California time and

45p.m. Munich time.

Meetings with team members in California: 8a.m. to 12 noon.

Call subcontractor at Research Triangle, North Carolina:

12p.m. California time and 45p.m. North Carolina

time.

Time for other project tasks such as scheduling, earned

value analysis, and so on: 24p.m.

Call foundry in Tokyo: 45 p.m. California time and

89a.m. the next day Tokyo time.

Call volume production plant in Penang: 56 p.m.

California time and 89a.m. the next day Penang time.

Call subcontractor in Bangalore from home: 910p.m.

California time and 9:3010:30 a.m. the next day

Bangalore time.

Before the phone calls, we e- mailed the topics we wanted to

discuss during the call to each other, so that we could bring in

the right participants for the phone call. I directed the phone calls

with the agenda generated from the e- mails. I recorded the min-

utes of the phone calls and the action items with the responsible

people and delivery dates. I released the minutes of every phone

call through our document control and had them distributed to

the appropriate people.

ere was another issue hanging over my head. Some of the

countries that I was dealing with did not use daylight savings

time. Only the United States and the European Union (EU)

used daylight savings time, but they started and ended day-

light savings time on dierent dates. e United States started

daylight savings time on the last Sunday in March, but the EU

started it on the second Sunday in March. So during that two-

week gap, I had to call my customer at 89a.m., which corre-

sponded to my customers 45p.m. e United States ended

113

case studIes In schedule ManageMent

daylight savings time on the rst Sunday in November, but the

EU ended it on the last Sunday in October. So during that one-

week gap, I had to call my customer at 67a.m., which corre-

sponded to my customers 45p.m.

When daylight savings time ended in the United States, my

daily schedule was as follows:

Call customer in Munich: 78a.m. California time and

45p.m. Munich time.

Meetings with team members in California: 8a.m. to 12 noon.

Call subcontractor at Research Triangle, North Carolina:

12p.m. California time and 45p.m. North Carolina

time.

Time for other project tasks such as scheduling, earned

value analysis, and so on: 23p.m.

Call foundry in Tokyo: 34 p.m. California time and

89a.m. the next day Tokyo time.

Call volume production plant in Penang: 45 p.m.

California time and 89a.m. the next day Penang time.

Time for other project tasks: 56p.m.

Call subcontractor in Bangalore from home: 89 p.m.

California time and 9:3010:30 a.m. the next day

Bangalore time.

Global projects such as this one put a lot of excessive strain

on the project manager. ere are numerous bumps on the way

before you reach the nish line. Precise time management is the

only way to smooth out and to monitor eectively the progress of

your project. e object of my time scheduling was not to disturb

the call schedules of my customers and my team members around

the world. As a conscientious project manager, I took the daily

call scheduling bumps on myself and I smoothed out everyones

call schedules related to my project.

LESSONS LEARNED FROM THIS PROJECT EVENT

Time management for communications in a global engi-

neering project has to be precise. Communication time

rules have to be established at the beginning of your project.

Engagement slots assigned to dierent global teams

should not interfere with each other.

Daylight savings time can cause confusion to and alter

your communication schedules.

114

Project ManageMent case studIes

Case4.5: Dealing with Critical Path Tasks

Critical path tasks on a global project can be very challenging for

a project manager. Tasks that lie on the critical path of a proj-

ect cannot be delayed without sacricing the projects schedule

performance and any delays in them most likely would ruin your

projects cost performance. A global project manager has to dou-

bly focus on critical path tasks. Several noncritical tasks can slip

during execution of a project and can become critical.

In a rotary engine design and development project that I was

heavily involved in, seals used between combustion chambers

became a major issue. After our initial design and prototype build,

structural integrity of the seals degraded fast. We had to perform

a thorough failure analysis, redesign the seals, and retest them. At

the beginning of the project, the seal design tasks had a handsome

slack time for an iterative development process so that it was not

on the projects critical path. After the third design iteration, seal

design tasks moved up to the critical path. e project manager

had to beef up the seal design team with several expert consultants

and had daily meetings on it in order to achieve the nal design.

We nally achieved the life expectancy out of the seals after the

fth design iteration. It delayed the project by a month and had

a 30% cost overrun for the seal design portion of the project.

Sometimes at the beginning, a technologically leading-edge com-

ponents design looks simple and straightforward, but by the end

it comes back to bite your project. When I look back on the seal

design task history, other project approaches come to mind. If we

had had the two expert consultants at the beginning of the task,

we might have achieved our goal with a couple of design iterations

within the allocated time and even within the allocated budget.

In another critical path task case, my projects chip soft-

ware design team always got tangled with the customers continual

design modications. e customers change approval process was

very bureaucratic and therefore it sometimes took a month to see

the nal approved change. Luckily, the project was managed on a

time and material basis. So these delays did not hurt my company

nancially, but they aected the duration of several critical path

tasks and the completion date of the project. Also, my team mem-

bers eciency dropped substantially while waiting for approved

design modications. I discussed this issue several times with my

customers project manager. He insisted on waiting for the nal

approved design modications before doing anything. I could not

115

case studIes In schedule ManageMent

move my team members to other projects during these lull times.

Our projects productivity dropped, but we still charged our time

to the customer. A yearlong project lasted almost a year and a half.

In an electric bus design project, the batteries we purchased

for the buses were leading state of the art critical items, but they

were not on the critical path of the project. I had to call my battery

supplier daily along with my purchasing agent in order to ensure

that there were no issues in the manufacturing and delivery of

my batteries.

More often than not, a critical path task can be assigned to a

subteam in a faraway location in the United States or in another

country. Managing such a critical path task can be very challeng-

ing. In such a case, I had to plant one of my engineers with a

subteam in France for six months for the construction of several

advanced hydraulic components for my project. On top of that, we

had to teleconference twice a week to assure them that the critical

task was moving along smoothly. We were able to tackle all the

issues in a timely fashion and the critical task was completed suc-

cessfully on time.

In another critical task case, during setting up and quali-

cation of a new wafer factory, my senior sputtering equipment

engineer jumped ship and moved to our competitor. I had to

scramble to nd a replacement, which was not easy at all. At the

time, sputtering equipment engineers were on demand. rough

our human resources department and my contacts, we did a

very detailed search without nding any feasible replacement.

I decided to groom one of my novice engineers for this critical

task. I also decided to get help from the equipment supplier. We

agreed that one of their seasoned engineers would come to our

factory and qualify the new sputtering equipment and at the same

time train my new engineer. is was an expensive option, but I

had to go along with it in order to complete my project without

any delay.

LESSONS LEARNED FROM THIS PROJECT EVENT

During the execution of a global project, several non-

critical tasks can easily slip back and become critical.

Critical tasks have to be completed satisfactorily on time

even if you experience cost overruns to nalize them.

If you have a critical task that is being performed in a

foreign country, you better have a constant and reliable

observer at that location.

116

Project ManageMent case studIes

Case4.6: Estimating Task Completion Percentages

As global project managers we have one of the most dicult and

periodically required duties of estimating completion percentages

for every task. Our projects schedule and cost performance indi-

ces depend on the accuracy of our estimates. We present these

performance indices to our upper management and to our cus-

tomer at least monthly. ese performance indices also show us

the health condition of our project. We can see the tasks that we

are having issues with. In some tasks we are behind schedule and

in a few others we are ahead of schedule. In some tasks we are over

budget and in a few others we are under budget.

If possible, I always sat down monthly with the responsible task

owner(s) and decided together on completion percentage(s) of his

or her task(s). Task completion estimates became more blurred for

task owners in other global locations and for our subcontractors. On

many occasions, I had to travel to the site of the task owner in order to

get more reliable task completion estimates. I have found throughout

my project management career that most task owners overestimate

their task completion percentage in order to present a rosy picture. If

you peel back layers of his or her task and go into minute details then

a more reliable task completion percentage picture emerges.

I had the most diculty getting good task completion esti-

mates from my software design engineers. e software design

task was one issue, but testing the software and revising it and

documenting it was another. For the most part, the software

designer and the tester worked as a pair. When they told me that

they were 90% complete, I could never believe them. e remain-

ing 10% took forever to complete. I asked them to break down

the software structure into manageable substructures or modules.

We reviewed the status of each module. If I sensed any trouble in

the progress of the software design process, I had to take immedi-

ate drastic action. Several times I had to call in experienced senior

software design engineers to take over remaining tasks in order to

complete the project on time even if I ran over budget.

Another area of dicult task completion percentage estimates

was in design engineering calculations. I had separate task dura-

tion estimates in my project plan for design calculations and for

checking these calculations. In most cases, the checker found sev-

eral mistakes or missing items in the design calculations. en

calculations went back to the designer. e designer updated

his calculations per the checkers recommendations and ndings.

Calculations went back to the checker again for rechecking. is

117

case studIes In schedule ManageMent

iterative cycle sometimes lasted four or ve times, especially in

complicated and detailed calculations with new in- house gener-

ated software. I always ran behind schedule and over budget in

extensive design engineering calculations.

Task completion percentages were also signicantly aected by

our customers review of the design drawings. Most of the time,

the customer was delayed in his or her review and approval of

drawings. When we received the delayed review and comments

back, there were always some minor tweaks to the design draw-

ings, which did not change the scope of the project specications.

My designers had to update drawings and resubmit them for

approval. is cycle was out of my control. I could not push my

customers with the same intensity as I pushed my team members

to get something done. Task completion estimates always tanked

when a customers action was involved.

Subcontractors always posed a problem in task completion

estimates. If a subcontractor was falling behind schedule, I did

not hear about it in a timely fashion so that we could formulate

corrective actions together without any delay. More often than

not, I had to implant engineers or purchasing agents into my sub-

contractors facility in order to be able to follow with ease of mind

what was going on with my projects tasks.

Most unreliable task completion estimates came from my

global subteams. According to my subteam leader, especially in

developing countries, everything was going hunky- dory. When

I visited them or sent one of my U.S.-based engineers to check

on them, I always received dierent perceptions about task com-

pletions. My subteams in developing countries needed continual

monitoring and hand- holding in order for me to be assured that

their tasks were on time and within budget.

LESSONS LEARNED FROM THIS PROJECT EVENT

Watch out for overestimated task completion estimates

by your team members.

You can run into surprising misunderstandings with task

completion estimates for tasks being performed in for-

eign countries.

Software design engineers and mechanical product

design engineers tend to always overestimate their task

completions.

You have to watch your customers and your subcon-

tractors like a hawk when it is time for task completion

estimates.

119

5

Case studies in

resourCe ManageMent

Resource management in a global environment gets very tricky and

requires continual monitoring. In particular, a global projects bud-

get management can be a constant struggle. Listening to experts

and evaluating input from experienced people outside of your proj-

ect team always helps to avoid pitfalls during the execution of your

global project.

I had a challenging experience with my companys information

technology department in one of my long- term projects. Computer

and information technology was advancing at a mind- boggling speed

at the turn of the century. A computers operating system, processor,

memory, and hard drive capacity became obsolete in six months. I

took it upon myself to improve our information technology depart-

ment in order to save my project in Case5.1.

After two months into a high volume production project, our sub-

contractor in Japan announced that they were shutting down their

operations which produced a critical component for our assembly

in three months. is was quite a shock to me and to my company.

Case5.2 describes the actions that I took to remedy this issue.

While working with leading-edge technology small- sized sub-

contractors during a project, lots of unforeseen issues can pop up.

oroughly understanding the capabilities of the personnel, equip-

ment, and processes being used in these companies can cut down on

undesirable issues as shown in Case5.3.

In dealing with international project teams from dierent coun-

tries, there is always a dierence in adrenaline rush and excitement

for meetings and project tasks. I experienced an adrenaline rush and

excitement toward project meetings and tasks at the higher end of the

spectrum from team members in countries such as Japan and Germany

and at the lower end of the spectrum from team members in countries

120

Project ManageMent case studIes

such as Malaysia, Mexico, and countries in the Mediterranean region.

I detail my encounters in dierent countries in Case5.4.

During the execution of a project, always keep the pressure on your

team members, but do not overdo it and burn them out. In this day

and age, continuous connectivity to our team members can be very

hazardous and stressful, if it is not handled with care. Such events are

detailed in Case5.5.

Listening is the greatest virtue of a project manager. When I ran

into trouble while executing a task, I listened to all ideas that would

cure the issue at hand. Such a nagging problem is detailed in Case5.6.

After trying a new interface system for over a month in our wafer fab-

rication lines, we saw signicant increases in wafer yields. Also, wafer

throughputs improved. Holdups for a shutdown process decreased

signicantly. I made this new process engineering shift interface

meeting a standard for our wafer factory.

If a task in a project reaches a re- ghting mode, your decision-

making process to cure the issue accelerates very fast. You are in an

urgent rescue mode. After being in a re- ghting mode for two weeks

to troubleshoot a control panel via telephone conversations in a remote

location in Norway with a novice engineer, I had to take drastic action

as detailed in Case5.7.

In some cases, we have to rescue our subcontractors from a bind. I

tasked two engineers on my team to improve a critical Japanese suppli-

ers falling yields. As a project manager, it was my responsibility to help

my subcontractor in any way that I could. As a result of this urgent

six- week long rescue mission, our products nal test yields improved

immensely and they were steady. ese details are given in Case5.8.

Listening to all of the input regarding your projects tasks and

ltering them down to useful ones is an art in itself. Such input is

detailed in Case5.9.

Some tasks in our global projects require us to deal with foreign

government agencies. Bureaucracy in a foreign government can hurt

your project in many ways. You have to go along with experts to solve

your problems with bureaucrats even if it costs your project an arm

and a leg as detailed in Case5.10.

As global project managers, we have to be on top of all ancillary

tasks such as shipping rules and regulations of our nished products.

If we leave these ancillary tasks alone, they might harm our project

121

case studIes In resource ManageMent

tremendously in one way or another. In Case5.11, I missed details of

the insurance coverage for my projects nished products shipment.

At the bidding phase of a project, we might have to partner with

other companies in order to strengthen our position. At the beginning

of a project, all project partners look eager and willing to win the bid.

Many unforeseen issues might surface with our project partners dur-

ing the execution phase of the project. As project managers, it is our

responsibility to remedy these project partner issues as fast as we can

without damaging the cost and schedule performance of our project.

An example is given in Case5.12.

Sometimes cost performance of a task might be hit by unexpected

increases in material costs. I had a project to design, build, and test

20 high- load capacity and high- pressure hydraulic cylinders for a cus-

tomer in Brazil. I had to scramble to get my cost performance under

control as detailed in Case5.13.

Monitoring schedule and cost performance of a global project very

closely at regular intervals is a must for a project manager. You have

to bring your companys other departments in sync with your projects

dynamic environment. e challenge is to be able to collect all sched-

ule and cost performance data in a timely fashion from your foreign

project partners as shown in Case5.14.

Case5.1: Dependence on Other Departments

During the execution of a project, a project manager depends on

performances of other departments in the company. e purchas-

ing department is the key player in purchased components for

the project and in establishing contracts for subcontractors and

consultants joining the project team. e accounting department

has to execute correctly and in a timely fashion the projects pay-

ables and receivables and charges to project charge numbers. e

drafting department has to prepare and release drawings, manu-

facturing process instructions, and quality assurance instructions

according to promised schedules. e sales department has to

coordinate with the project manager closely for a projects con-

tract extension and for related competitive bids to a project. Every

department in your company contributes to your project in one

way or another during the execution phase.

I had a challenging experience with my companys informa-

tion technology (IT) department in one of my long- term projects.

122

Project ManageMent case studIes

Computer and information technology were advancing at a mind-

boggling speed at the turn of the century. A computers operat-

ing system, processor, memory, and hard drive capacity became

obsolete in six months. You had to improve your computers per-

formance at most in a year in order to keep up with the changing

world. In parallel to improved computer performance, software

that was used in my projects was going through revisions to uti-

lize enhances in hardware performance. I had an IT department

in my company, as the saying goes, that always liked to squeeze

the lemon to the last drop. ey dragged their feet in upgrading

my teams hardware, software, and communication tools. is

type of mentality aected the performance of my engineers who

always wanted to be in sync with leading-edge technology. When

I made an upgrade request, it took them two to four weeks to

respond. I had several meetings with the head of our IT depart-

ment regarding timely upgrades to our IT tools. I told him how

demoralizing the situation was for my engineers. I told him that

if our IT tools were not at the leading edge of technology then

our company could not stay at the leading edge for long. He kept

complaining about his budgetary and personnel issues. He did

not change his style of service a bit to my requests. After two

months of frustration, I went up the ladder to his boss. I called a

meeting with the IT manager and his boss. I went over all hard-

ware, software, and communication, especially videoconferenc-

ing, issues. I sensed during the meeting that the IT manager was

being protected by his boss. Changes were not going to happen as

swiftly as I liked. eir vision was to reduce the IT departments

budget and use all IT tools that we had as long as possible.

en I went and discussed the IT department issues with other

department heads. All department heads had similar complaints

to mine, but their complaints were not as urgent as mine. I con-

vinced all department heads that something had to be done fast

to change the existing IT department mission. Two of the other

department heads and myself agreed to take our case a notch

higher to the president of the company. I called a meeting with

our president and also invited the IT department managers boss

to the meeting.

e meeting with the president, the IT department managers

boss, two department heads, and I lasted over two hours. I pre-

sented all my teams IT department issues that I encountered dur-

ing the execution of my project. e other two department heads

presented their issues too. e IT department managers boss

123

case studIes In resource ManageMent

was continually in a protective mood. At the end of the meet-

ing, our president promised to take constructive action immedi-

ately to improve the situation. A week passed and I got the news

that our IT department head had resigned or been let go. ere

was also reshuing of responsibilities in upper management.

e IT department started to report directly to the president. e

company searched and hired a new vice president of IT from a

well- known computer technology company. After six months of

continual struggle, my engineers and I started to see a bright light

at the end of the IT tunnel.

e execution of a project can be bogged down and sometimes

a project manager can experience long delays and cost overruns to

his projects tasks due to poor performance by other departments

in a company. Taking immediate action to correct issues at hand

with other departments is a must. e whole company has to run

smoothly and eciently on all cylinders in order to complete a

project successfully.

LESSONS LEARNED FROM THIS PROJECT EVENT

e IT department is a very crucial segment of your

company in this day and age.

Getting consensus with department heads to solve an

issue gathers momentum and helps you to achieve your

goal in a timely fashion.

All departments in your company have to function well

in order for your project to succeed.

Case5.2: Subcontractor Announcement

of Shutting Down Operations

We were qualied and were running a high volume production

of computer subassemblies for a U.S. computer manufacturer. A

critical component for our computer subassemblies was being sup-

plied by a sole source Japanese subcontractor. After two months

into the high volume production, our subcontractor in Japan

announced that they were shutting down their operations that

produced the critical component in three months. is was quite

a shock to me and to my company. At that time, I was head-

ing the engineering team for volume production of computer

subassemblies. I immediately had several telephone conversa-

tions with our subcontractor to understand the reasoning behind

their unexpected shutdown. Apparently, the critical component

124

Project ManageMent case studIes

manufacturing was not protable enough for them and the new

president of the company decided to end this divisions operations.

My company proposed several options to keep them going until

high volume production of computer subassemblies for our U.S.

computer manufacturer continued. To qualify a new subcontrac-

tor for this critical component would be a tremendous undertak-

ing at this stage of the game. My company oered to help them

nancially or even buy their division out to no avail.

I told our president that we should not inform our U.S. cus-

tomer until we had a detailed solid plan to qualify alternate

sources for this critical component. Our president agreed with me

and assigned me to prepare the qualication plan in three work-

ing days. After the internal review of the qualication plan, we

were going to go to our customer and present it in person.

I had three alternate subcontractor choices for this critical

component. One was in the Bay Area. e second one was again

in Japan, and the third one was in Malaysia. I immediately went

to our purchasing director and asked him to nd out in two days

their available production capacities for this critical component

and their pricing. ese were the two most important inputs to

start our qualication plan. It turned out that the sum of any

two of the subcontractors production capacities could satisfy our

needs. We ranked these three subcontractors with the purchas-

ing manager using several critical criteria such as quality control,

product reliability, stability of the subcontractor, pricing, and

capacity. e subcontractors in the Bay Area and in Japan came in

on top. We decided to prepare qualication plans with these two

subcontractors and present them to our customer.

I called our customers project manager immediately and

explained the unfortunate upcoming snag to our volume produc-

tion. I detailed our course of action with two new subcontractors.

I also detailed the qualication plans that we would be pursuing

in the next three months. I emphasized their involvement in the

qualication process. Our customer had to evaluate 200 computer

subassemblies, 100 from each new subcontractor, with new criti-

cal components in two weeks. Our customers project manager

agreed to do his part on time so that we would not disrupt the

volume production process.

I sent two engineering teams, one to each potential subcon-

tractor, for a detailed qualication process. Major areas of concern

were operator training, product change control, quality control,

and incoming material control. It took the teams one week to

125

case studIes In resource ManageMent

evaluate these two potential subcontractors. Both teams had

very promising reports about these two new subcontractors. We

decided to bring both subcontractors on board on equal footing.

We did not want to rely heavily on one of them. Both subcontrac-

tors provided us with qualication components with measured

critical parameters in four weeks. en we built computer sub-

assemblies for qualication using these new critical components

in ve weeks.

I hand carried the qualication lots to our customer. ey

tested 200 computer subassemblies in their computers while

I watched over their shoulders. Fortunately, there were no sur-

prises. Our customers project manager gave us the green light to

use the new critical component in our computer subassemblies as

promised in two weeks.

is surprising change to our product came without adequate

warning. I had to adapt to this change fast. I had to also con-

vince my customer about the steps I was taking to deal with this

change. We were lucky that there were other alternate solutions

to this problem. My mistake was originally to go with a single

source for the critical component. I should have qualied at least

two subcontractors for this critical component at the beginning of

the volume production process.

LESSONS LEARNED FROM THIS PROJECT EVENT

A surprising event can occur unexpectedly at a reliable

subcontractor.

Prepare a detailed and complete alternate plan before

approaching your customer with a way out of the

showstopper.

Always qualify multiple sources for critical components

of your project.

Case5.3: Subcontracting to Small Leading-Edge

Technology Companies

Subcontracting to small leading-edge technology companies can

be very tricky and time consuming during the execution of a

global project. Continual monitoring of such companies is a must

in order to assure that they are always up to a high level of opera-

tional standards and their personnel turnover does not hamper

your projects progress.

126

Project ManageMent case studIes

I was leading a team of engineers to supply high-volume mag-

netic recording sensors to our customers around the globe. Our

supply chain originated in our wafer fabrications in California

and branched into higher assemblies in South Korea, Malaysia,

Singapore, and Puerto Rico. Surfaces of our read- write sensors

had to be free of any contaminants before being installed into

disk drives. Our nal operations were performed in class-10 clean

room environments. We were supplying thousands of sensors a

week to dierent customers. Our major sensor lot rejection cause

by customers was contamination. Several lots per week were put

on hold or rejected by our customers for sensor surface contami-

nation. I had a subteam whose mission was to identify surface

contaminants, track down their sources, and eliminate them from

occurring again.

For U.S. customers, we brought contaminated sensors to our

material evaluation laboratories in California. We did failure

analysis using advanced state of the art auger spectroscopy, energy

dispersive x- ray spectroscopy, and atomic force microscopy. We

had well- trained technicians in all three shifts. We were able to

get surface analysis reports in a day to respond with our correc-

tive actions to our customers. Fast turnaround in corrective action

was a must in just- in- time supplier chain requirements from our

customers. I had to set up failure analysis laboratories for our cus-

tomer centers in Singapore, Japan, and Europe.

My team and I searched and sourced three leading-edge technol-

ogy contamination evaluation laboratories in each location. I sent

my engineers to these laboratories for qualication. We explained

our failure analysis requirements for surface contaminants on our

sensors. We checked their operations, nancial stability, measure-

ment costs, type of equipment they had for measurements, equip-

ment downtime, equipment repair structure, equipment spare

parts situation, their technicians measurement training and expe-

rience, sample preparation techniques, measurement prioritization

and turnaround time, failure analysis reporting time table, and so

on. After a thorough comparative analysis, we chose one labora-

tory at each location to be our failure analysis center.

My team and I had to check on these three leading-edge tech-

nology laboratories periodically. We had to make sure that they

were upgrading their equipment to the most advanced ones that

provided accurate elemental and chemical compositions of con-

taminants on the surfaces of our sensors. We had to make sure

that they were not losing their experienced technicians. We had

127

case studIes In resource ManageMent

some issues with lost sensors and miscommunication. We were

constantly discussing how to improve and how to expedite our

failure analyses within our partnership.

Several times while the failure analysis was going on, I had to

send one of my engineers and a couple of inspectors to my cus-

tomers facilities to sort our sensors. We had to separate good sen-

sors from contaminated ones under high- powered microscopes in

a Class-10 clean room environment so that my customers auto-

mated assembly lines would not slow down or come to a halt due

to the lack of our sensors.

In a just- in- time high- volume relationship with our customers,

I had to form such a global failure analysis group with leading-

edge technology small laboratories. It took my team and me six

months to form our failure analysis network, but in the end it

worked out very successfully for many years to come. Our cus-

tomers were very satised with our response time and corrective

actions to contamination issues in our magnetic recording sensors.

LESSONS LEARNED FROM THIS PROJECT EVENT

To qualify small leading-edge technology companies for

your project will require extensive scrutinizing and will

take more time.

To set up a global network for a crucial project task is

always a challenge for a project manager.

Case5.4: Latitude versus Attitude

When dealing with international project teams from dierent

countries, there was always a dierence in adrenaline rush and

excitement toward meetings and project tasks. I experienced

adrenaline rush and excitement toward project meetings and tasks

at the higher end of the spectrum from team members in coun-

tries such as Japan and Germany and at the lower end of the spec-

trum from team members in countries such as Malaysia, Mexico,

and countries in the Mediterranean region.

I dealt with team members from Malaysia, Mexico, and

Southern Turkey who often claimed that they never committed

to completing a given task on a mutually determined completion

time. eir behavior was inconsistent and uncooperative, and they

ignored my multiple requests and task deadlines. ey had to be

micromanaged and pushed to complete a task with quality. ey

had a lackadaisical work behavior. Of course this behavior was not

128

Project ManageMent case studIes

true for all team members from those regions, but most of them

had lower concentration and negative behavior. I attributed this

kind of behavior to the warm and humid climate in those coun-

tries and to their traditional work ethics.

In colder climates such as in Japan and Germany, people devel-

oped survival intelligence, they became practical, aggressive, and

competitive. Science and technology mushroomed from these

kinds of behaviors in the Western world.

For example, during my projects in Malaysia, I had issues with

my team members coming to meetings late and not being pre-

pared. Some team members walked into the conference room 10

or 15 minutes late. Some of them did not have a clue as to what

they had to present or what to contribute at that meeting. ey

obviously did not read their meeting invitation e- mail in detail.

I constantly reminded my team members that meetings were not

for kicking back and for being in another world. Everyone had

to be on their toes and contribute during a meeting even if it was

not their turn to present their part. I joked with the latecomers to

the meetings that I was going to charge a U.S. dollar per minute

that they were late to the meeting so that we could all go out and

have a feisty lunch every week. I kindly asked the latecomers to

be on time to the meetings with no success. en I went to their

supervisors and asked them kindly to correct the situation by talk-

ing to their people. e supervisors discussions with their people

helped the situation a little, but it was dicult to get rid of bad

habits. en I went up to the general manager of the company

and asked him to issue a stern memorandum for timely attendance

and well preparedness to all meetings. e stern memorandum

did the trick and all my team members got the message. After two

months of determination, my team meetings got into a productive

and a precise rhythm.

I also had issues with promised action item completion times

in countries such as Malaysia, Mexico, and countries in the

Mediterranean region. If I were given an action item completion

time by a Japanese engineer, the task was done before or right at

the promised completion time. If a Japanese engineer had prob-

lems with completing his task, he came and asked me for help or

for an extension to complete the promised action item. However,

in Mexico if an engineer promised me an action item completion

time, he came with his results a day to a week late. In these warm

regions of the world, the only way to keep my team members on

their toes was to micromanage them. I had to talk to them daily

129

case studIes In resource ManageMent

or even hourly to push them and to monitor their progress in a

given task.

Most of my team members in these warmer regions of the world

also had a relaxed behavior toward our customers and our subcon-

tractors. I emphasized that when a customer or a subcontractor

visited our plant we had to be well prepared and had to be sharp.

I want to emphasize that these lackadaisical behaviors surfaced

in the majority of my team members and not in all of them. It is

very dicult to change human behaviors in other countries. You

have to be exible, adjust, and learn how to deal with the situation

at hand. Jimmy Buetts song lyrics describe project team mem-

bers behavior in dierent countries well. With these changes in

latitudes, changes in attitudes, nothing remains quite the same.

LESSONS LEARNED FROM THIS PROJECT EVENT

In a global project environment, work habits and atti-

tudes vary vastly from country to country.

Changing well- ingrained habits in your global team

members can take lots of patience and continual guid-

ance on your part to correct.

Case5.5: Stress from 24/7 Connectivity

Internet and cell phone connections are getting faster, cheaper,

and more reliable every day. ese wireless connections are

achieved from anywhere on Earth, even ying at 35,000 feet

above the ground or while vacationing on a remote Tahitian

island. Continual advances in e- mailing, tweeting, cell phoning,

text messaging, ease of data transfer, videoconferencing, and wire-

less networking make the life of a global project manager much

easier. Anyone on your project team can instantly work with their

les, programs, and networks from anywhere on Earth just as if

they were at their own desks. A global project manager has to lay

down ground rules for 24/7 communication with all team mem-

bers, including subcontractors and customers around the world, at

kicko meetings of a project.

During the execution phase of a global project, a team member

can get inundated by e- mails, cell phone calls, text messages, and

so forth. ese 24/7 communications can occur during lunchtime,

dinner time, sleep time, or even during weekends, holidays, and

vacations. A conscientious team member will try to respond to all

messages in a timely fashion while sacricing his or her personal

130

Project ManageMent case studIes

life. ese kinds of 24/7 connections can cause overload and burn

out team members and the project manager fast. A 24/7-con-

nected environment will bring good things to a global project, but

the global project manager has to orchestrate and apply a fair bal-

ance between continuous connectivity and the private life of every

team member so that stress levels stay at normal levels during the

execution of a global project.

A good engineering friend of mine was working on an interna-

tional companys restructuring project team. He was a very con-

scientious worker. He checked his e- mails every half an hour from

the time he woke up until he went to bed. He always answered

his cell phone. One Saturday night we agreed to go out to dinner

together. He made a reservation at a good Italian restaurant, which

was very hard to get into. He brought his girlfriend. I brought

my wife. We were about to sit at our reserved table and his cell

phone rang. He answered his phone and ran out of the restaurant

to talk to the caller. We sat down at our table and waited for my

friend to return. After ve minutes he returned with a very sul-

len face. He told us that the call came from his project manager.

His project manager urgently wanted a couple of graphs from him

during the next hour. My friend told his project manager that

he was at dinner with us, but his project manager insisted on his

untimely demand. My friend had to excuse himself from dinner

and go home to his laptop. I learned later that his project manager

was a workaholic and was very rigid with his untimely demands.

He sometimes called my friend at midnight and during weekends

with excessive requests. My friend worked on that project team

for a month and then gave his notice to leave the company. He was

totally stressed out from 24/7 connectivity to his team and from

an unreasonably demanding project manager. My friend immedi-

ately started his own company and became quite successful. In a

way he was thankful for his previous project managers unaccept-

able behavior.

Interactive design and development by teams around the globe

are also an integral part of a global project. I was the project

manager of a chip design team in California that was constantly

interfacing with our German counterparts. Eight hours of time

dierence between the two design locations made me structure

feasible meeting and interaction times in order to reduce work

stress on both parties. I even allowed two of my design engineers

to work the night shift in California for two months in order to

have real- time interaction with their German counterparts. e

131

case studIes In resource ManageMent

proposal to work the night shift in real time with the Germans

during the design of the chips software was suggested by my engi-

neers. Real- time interaction between two design parties reduced

time and error in completing their design tasks.

A project manager colleague of mine was working with a sub-

team in India to manufacture computer components. A twelve

and a half hour time dierence between India and California

required him to take several steps to reduce work- related stress

from continuous connectivity. He set up videoconferencing from

7:30p.m. to 9p.m. California time on every Monday. He asked

his California team members not to call their Indian teammates

from 6:30a.m. to 7:30p.m. California time during the work week

and during weekends. He also listed all Indian holidays when

communication was to be stopped. e project manager had to

establish these communication rules for his project during the

kicko phase of his project.

LESSONS LEARNED FROM THIS PROJECT EVENT

Stress levels of your global team members can increase

exponentially in a 24/7-connected environment.

24/7-communication rules between your global team

members, your global customers, and your global sub-

contractors have to be laid out by you at the kicko meet-

ings of a project.

Case5.6: Engineering Interface

among Wafer Fabrication Shifts

Wafer fabrication engineering requires detailed recording and cor-

recting for out- of- specication conditions, scrap reasons, equip-

ment malfunctions, corrective actions, and variations in control

charts. Our wafer factory was working in three shifts for seven

days. Wafer fabrications process engineering hours were 7a.m. to

3p.m. for the day shift, 3p.m. to 11p.m. for the swing shift, and

11p.m. to 7a.m. for the night shift. I had six process engineers

in each shift. One was a principal process engineer for deposition

processes and the backup for ion milling processes. e second one

was a principal engineer for ion milling processes and the backup

for deposition processes. e third one was a principal process

engineer for photolithography and the backup for plate and etch-

ing processes. e fourth process engineer was the principal for

plate and etch processes and the backup for photolithography. e

132

Project ManageMent case studIes

fth process engineer was the principal for wafer testing and the

backup for clean room environment. My sixth process engineer

was the principal for the clean room environment and the backup

for wafer testing. All the important events that happened during a

shift were recorded in six dierent logbooks, one for every process

center, and critical action items were being sent to the next shifts

engineers by using six dierent e- mail folders, again one for every

process center.

e system was working okay, but it was not perfect. Several

items, some of them critical, were falling through the cracks.

ere were misinterpretations of messages written in logbooks

and in e- mail folders. I was getting several telephone calls a

night from the swing shift and the night shift engineers ask-

ing me to explain some of the comments written about a pro-

cess or about malfunctioning equipment. Even I could not help

explain some of the condensed phrases. Comments like sput-

tering equipment 1 is acting and photolithography curing

plates had temperature problems were causing us to do exten-

sive detective work to nd the particular malfunction. We had

to improve our wafer yields continually and the process engi-

neering communication system between shifts was hampering

our progress. I had several meetings with my engineers from

every shift and we discussed in detail how to improve our com-

munication procedures between shifts. We decided to record

more precise and detailed information regarding every issue

during a shift. All of my engineers complied very well, but still

it was not a good communication system between the shifts.

We had over 200 operations and equipment in six process

centers in the wafer factory. is kind of very dynamic and con-

tinuous process environment did not allow any mistakes or any

shortcuts to overcome the issues that popped up. All of the sput-

tering engineers had to be on the same page on all shifts. All of

the photolithography engineers had to be on the same page, even

on the same line, on all shifts.

During one of my process engineering meetings, one of the

engineers proposed a good idea to extend our shift hours by half

an hour and have a face to face between the shift engineers. I

talked to every engineer and got their consent to extend their

work hour by half an hour. I also talked with human resources

to make sure that we were not violating any overtime regula-

tions. Salaried engineers did not get paid for overtime in this

133

case studIes In resource ManageMent

company. Everyone agreed to the new schedule and to the shift

interaction meeting.

Wafer fabrications process engineering new hours were 7a.m.

to 3:30p.m. for the day shift, 3p.m. to 11:30p.m. for the swing

shift, and 11p.m. to 7:30a.m. for the night shift. We started to

have process engineering shift interface meetings from 7 a.m. to

7:30a.m. for the night shift and day shift engineers, from 3 p.m.

to 3:30p.m. for the day shift and swing shift engineers, and from

11 p.m. to 11:30p.m. for the swing shift and night shift engi-

neers. I attended all three meetings every day. I took the meeting

notes and distributed action items list to the appropriate people.

Sometimes we could not complete all current issues in a half an

hour meeting. Some meetings extended to an hour.

After trying this new interface system for over a month, we

saw signicant increases in wafer yields. Also, wafer throughputs

improved. Holdups for a shutdown process decreased signi-

cantly. I made this new process engineering shift interface meet-

ing a standard for our wafer factory. I also covered the extra time

that engineers were spending in these shift interface meetings in

their annual bonus awards. My boss and the company president

agreed to award extra bonuses for my process engineers for their

voluntary agreement to spend extra time for shift interface meet-

ings, which caused our wafer yields to improve continually.

LESSONS LEARNED FROM THIS PROJECT EVENT

24/7-production operations require face- to- face interac-

tion between shift engineers and operators.

Depending on only written communications between

production shifts can cause misinterpretations.

Written communication plus face- to- face interaction

between production shifts reduces the possibility of errors.

Case5.7: Fire Fighting during the Installation

of a System on an Oshore Oil Platform

I was the project manager of a large project to design, build, and

install an automated positioning system on a new oshore oil

platform. e design and construction of the system were com-

pleted in the United States. e system components were shipped

to Norway for installation. I had to send an application enginee

134

Project ManageMent case studIes

to Norway to see the installation of the positioning system on the

new oil platform and train the responsible people from our cus-

tomers team for its operation and maintenance.

I had a young and very inquisitive engineer on my team who

was trained for six months during the construction and testing

of the system in our facilities. He knew all the intricate details of

the automated system. He was also well versed in troubleshoot-

ing the system components. I decided to send him to Norway for

three months to oversee the installation of the system and to train

the customers team members. I discussed his mission with him.

He was very excited and elated that he was going to represent our

company by himself in such a detailed project. I told him that we

were going to have a daily telephone conference ve times a week.

I promised him that I would bring in other design specialists to

the telephone conference calls if there were any issues during

the installation. I asked him to keep an engineering notebook to

record all the daily tasks, mishaps, issues, and all important facts

regarding the system installation. I also cautioned him to carry

along a complete toolbox to be used during the system installation

and some cold weather clothing.

e rst month in Norway went well. e engineer did a great

job during the installation of our automated positioning system.

We had a telephone conference call at 8a.m. California time and

5p.m. Norway time during every working day. ere were some

minor issues such as interference with another equipment, which

was solved by removing a quarter of an inch from the side anges

of our equipment. Several bolting patterns with the oil rig oor

did not match. We had to slot our bolting holes to match theirs.

Installation was completed in a month and test runs were starting.

My engineer was freezing in Norway in the month of February,

but he was upbeat and ready to start the test runs.

e control panel of the system started to have problems during

the test runs. Watertight pressure switches were not sometimes

switching at their set points. My engineer on location tried to nd

the cause of this intermittent malfunction without any success.

I immediately collected the available brains in our plant and an

application engineer from the pressure switch manufacturer and

brainstormed the control panel problem in Norway. We provided

several suggestions to our engineer over the telephone for him

to try. Nothing seemed to work to correct this malfunction. We

tried all the re- ghting ideas for two weeks without any success.

135

case studIes In resource ManageMent

I had another option. ere was a very experienced consultant

in electro- mechanical system design. My company used his ser-

vices from time to time in the design of our control panels. I tried

to reach him by telephone and by e- mail. I learned from his fam-

ily that he was on a sailing vacation in Tahiti for a month. I asked

his family as to how I could touch base with him. Apparently,

he called his family at least twice a week when he was on land.

I asked his family to help me to touch base with him on a cru-

cial issue. I asked them to ask the consultant to call me as soon

as possible.

After two days, I received a call from the consultant from Bora

Bora in Tahiti. I explained the situation and told him that we were

in a bind. I asked him if he could cut his vacation short and y

from Tahiti to Norway and help my resident engineer solve our

control panel issue. I proposed an incentive to help him make up

his mind. I told him that I would pay him his regular hourly rate

even during his travel time and reimburse him for business class

airline fares. He agreed to my proposal and promised me that he

would be on the rst ight out of Tahiti to Europe.

After troubleshooting the control panel together with my nov-

ice engineer in a very methodical way, the consultant found the

problem that was causing our control panel to malfunction. e

power that was feeding the control panel was sometimes below

the allowable lower limit and was causing the pressure switches to

not function properly.

Being in a re-ghting mode for two weeks to troubleshoot the

control panel by telephone conversations in a remote location in

Norway with a novice engineer did not work out well. My hind-

sight told me that I should have sent my novice engineer to this

important oshore assignment in a foreign country along with an

experienced engineer as a team. In the end, my customer was not

happy because it took us three weeks to troubleshoot the control

panel malfunction. We were lucky that we were not penalized

for this delay because the new oil platform had other functional

issues. My solution to our problem was an expensive one. I was

over budget and my management was not thrilled about it.

I thanked my consultant for saving our butt by cutting his

vacation short. I showed my gratitude to him with a bonus pay-

ment. I did not forget to praise my novice engineer for performing

a very detailed and a courageous job by himself working the rst

time on an oil platform. He also received an outstanding perfor-

mance review from our customers project manager.

136

Project ManageMent case studIes

LESSONS LEARNED FROM THIS PROJECT EVENT

In a project, sometimes it takes very unusual and expen-

sive decisions to solve a nagging problem.

A novice engineer and an experienced engineer work-

ing as a team on a complicated project task can be more

ecient and more eective.

Case5.8: Engineers Sent to Japan

to Improve Manufacturing Yields

A Japanese supplier was providing ceramic magnetic recording

heads for our head stack assemblies for a U.S. disk drive manufac-

turer. Each head stack assembly was being tested for performance

and the yields were low. We formed a team of six engineers, two

from design, two from quality, and two from manufacturing, to

improve the yields of our head stack assemblies. I was heading

the yield improvement team. We investigated every process in our

plant. We tracked every suppliers component lots to nal testing.

We realized that our nal test yields were varying from 30% to

70% depending on the ceramic magnetic recording head lots we

received from Japan. ere were wide swings in performance of

ceramic performance heads from lot to lot.

I called the chief engineer at our Japanese supplier and dis-

cussed our surprising conclusion for low product yields with him.

He promised he would investigate his processes and report his

ndings to me in a week. A week passed and I did not hear any-

thing from him. I called him again to emphasize the yield issue.

He nally spilled the dire situation he was in. He told me that he

was down to one manufacturing engineer. He lost two of them

recently. He could not investigate and control all the processes for

our ceramic magnetic recording heads. I proposed to help him by

sending two of my seasoned manufacturing engineers from my

team to Japan for four weeks. I asked his company to pay for travel

expenses for my two engineers. He accepted my oer. Two of my

teams senior manufacturing engineers, one a lapping expert and

the other a grinding expert, were o to Japan.

We had a mission- dening meeting before the two engineers

left. I wanted a daily update via e- mail from them detailing their

investigation steps, their design- of- experiments, and their nd-

ings. We were also going to have a telephone conference call twice

a week on Mondays and ursdays at 5p.m. Pacic standard

time, namely, 9a.m. on Tuesdays and Fridays in Japan.

137

case studIes In resource ManageMent

My two engineers started to go over each manufacturing step of

ceramic magnetic recording heads at our Japanese supplier. Some

of the inconsistencies in their processes and in dierent shifts

were corrected. ese did not make any dierence in our over-

all yields. I asked them to conduct several design- of- experiments

involving lapping and grinding processes and especially speeds

and send me products from these experiments by specifying all

variables for a given lot. We built these special ceramic magnetic

recording head lots to nal assemblies and tested them to see the

changes in nal test yields.

e Japanese manufacturing personnel were helping my engi-

neers day and night. ey were doing up to 10 dierent experi-

ments at once. We could not nish all the designed experiments

in four weeks. We had to extend their stay in Japan another four

weeks. At the end of the sixth week, we received several special

lots with slower lapping and grinding speeds. Our nal test yields

with these slower speed lots shot up to 90%. e stresses induced

on the ceramic slider body were much lower and therefore the

stresses induced on the magnetic sensor were much reduced. I

gave my engineers and the Japanese chief engineer the exciting

good news. I asked them to send me ve more conrmation lots

with slower lapping and grinding speeds. All these special lots

too went through nal testing with ying colors. We had a very

steady 90% nal test yield.

Apparently, the Japanese manufacturing engineers increased

lapping and grinding speeds to jack up the throughput due to

increased demand from us. I emphasized to the Japanese chief

engineer not to change anything in their processes without my

approval. He agreed to it. He was very apologetic about the whole

chaos that was created by his novice engineers.

After all the 24/7 work that my manufacturing engineers per-

formed in Japan, I asked them to relax and spend a couple of days at

their leisure before heading back. e Japanese chief engineer took

them to a close by ash- spewing volcano and to some hot springs

(onsen) near the volcano. My teams two manufacturing engineers

did a great job performing a very structured design- of- experiments

at our ceramic magnetic recording head supplier. I wrote a praising

review regarding their excellent work in Japan to their supervisor

and sent a copy of my review to our human resources.

is Japanese supplier was a critical part of our product. As a

project manager, it was my responsibility to help them in any way

I could. As a result of this urgent six- week project, our products

138

Project ManageMent case studIes

nal test yields improved immensely and they were steady. Our

Japanese suppliers ceramic magnetic recording head sales doubled.

LESSONS LEARNED FROM THIS PROJECT EVENT

Degradation of crucial production parameters such as

the nal product test yield can be traced all the way to

your subcontractors processes.

You have to do all you can to help your subcontractor to

nd and correct manufacturing problems that are aect-

ing your nal product yields.

Case5.9: Listening to an Engine Assembler

I was a senior scientist on a team of ve engineers and two design-

ers. We designed from the ground up a 70 HP at 5000 RPM

rotary engine for compact cars. e design was completed in one

year and we contracted a British rm to build the engine proto-

types. We were bench testing the rst prototype engine. During

test runs from cold start, the oil pressure was always showing high

and exceeding the preset limit. Initially, we thought that there

was a design ow in some of the oil passages in the engine. We

did some investigative work, but we could not pin down where the

problem was. My teams engineers, including myself, were pulling

our hair out trying to determine the cause of this malfunction.

One of the engine assemblers, named Freddie, thought that

the oil pressure relief valve exit hole that dumps excess pressure

oil directly back into the oil sump was too small in diameter. He

showed me the relief hole and insisted from his experience with

other similar engines that it should be larger in diameter. I listened

to his constructive input and went to the project manager to inform

him about the observation from the engine assembler. I asked the

project manager if we should repeat the oil exit hole sizing calcula-

tions to see if there was an error in them that we missed.

e project manager agreed with me and asked one of our

engineers to repeat the oil pressure relief valve exit hole sizing

calculations. He asked me to be the checker for the new calcula-

tions. e oil ow velocity equation that was used initially in high

oil pressure cases was wrong and during these initial calculations

we predicted higher velocities in small diameter holes. Our new

calculations with the correct oil ow velocity equation predicted

that the required oil pressure relief valve exit hole diameter be

doubled. We changed all the required drawings and released

139

case studIes In resource ManageMent

them for the next set of engines to be built. We also modied the

existing engines. e updated engines ran with great performance

even in cold weather conditions without exceeding the preset oil

pressure limit.

I went back to Freddie and thanked him for his valuable advice

and asked him and his wife to join us for dinner at an exclusive

restaurant in the city. He was very grateful. We had a great time in

celebrating Freddies constructive input to our project.

Listening to the engine assembler saved us precious time

in nding the solution to a simple nagging malfunction in our

engines. ese types of events happen many times during the

life of a project. Listening to your customers input, to your sub-

contractors input, to the regulatory agency input, to input from

people around you from secretaries to assemblers might save your

project. Listening to all input and ltering it down to useful ones

for your project is an art in itself. As a project manager, you have

to be appreciative of all input, good or bad, and you should not

forget to reward the good ones.

LESSONS LEARNED FROM THIS PROJECT EVENT

A nagging problem can be solved easily by listening to

others.

As project managers, we have to be very open- minded

to ideas and suggestions given by others. Our easygoing

and appreciative attitude will encourage everyone around

us to sound their input for the goodness of our project.

Case5.10: Russian Federation Technical Passport Issue

Bureaucracy was a major hurdle in shipping equipment to a project

for a Russian Federation oil platform. As a part of the project, tech-

nical passports were required to ship our equipment to Russia. e

Russian Federation regulatory authorities review and approve the

equipment documents ahead of shipment. ey issue a GOST- R

certicate of conformity for customs clearance. I had to send all the

equipment drawings, specication sheets, quality and conformity

certicates, certicates of origin, and operating manuals in Russian

to the Russian authorities about three months before the shipment.

at would give them enough time for their review and for a ques-

tion and answer period and to release the certicate of conformity.

I estimated that all the documents that had to be submitted

to be around 1,000 pages. I got bids from two agencies that were

140

Project ManageMent case studIes

experts in obtaining these certicates. ese agencies do all the

translation into Russian, submit the documents, do the follow- up

and resolve all the conicts, and get the certicate in time before

shipment of our equipment. ese agencies asked $60,000 to

do the entire job. is expense was not funded in our original

bidding for the project. We had to spend this amount from our

margin. My upper management asked me to look into other ways

of obtaining the Russian Federation certicate. I researched and

found a certied Russian technical translator for $15 per page. If

we got our documents translated and submitted them ourselves,

we would increase our margin by $45,000.

I went to my management and explained to them the alternate

way of getting the certicate of conformity. We all agreed to submit

our documents to the Russian Federation regulatory authorities our-

selves. I got all the documents translated into Russian, which took

two months. I sent all the documents by FedEx three months before

the shipment to the Russian Federation regulatory authorities.

I followed up the approval process by e- mail and by telephone

with my Russian translator next to me every week. We always

received an answer from a secretary that our documents were in

the review cycle and we should get the approval any day. A month

had passed and I started to get edgy. Two months passed and

we got the same response, that the review cycle was almost com-

plete. I could not wait anymore. I had only one month to ship our

equipment according to our contract with our customer. I talked

with my customers project manager about the runaround I was

getting from the regulatory authorities in Russia. He warned me

that their response was typical. He advised me that I should have

gone with an expert agency to get the certicate of conformity.

ese agencies knew how to push the paperwork and get the cer-

ticate of conformity on time.

I immediately contacted one of the agencies I had dealt with

before. I got a new bid from them to obtain the certicate of confor-

mity in a month with all documents already in Russian. is time I

received a $40,000 price tag. I went to my upper management and

laid out the details and the risks to them. We decided not to wait

anymore. We had to go with the expert agency to obtain the certi-

cate of conformity. ese agencies had oces in Moscow and they

hand carried all the documents and followed their progress daily. If

there was a hiccup they took care of it right there. ey promised to

obtain the certicate of conformity within a month and I received

it by overnight FedEx two days before our equipment shipment.

141

case studIes In resource ManageMent

After all this hoopla, I made an extra $5,000 in our margin,

but it was not worth it. I had several sleepless nights and spent a

lot of my time following a Russian Federation regulatory author-

ity process, which I had no control over. I should have put my foot

down with my upper management and should have gone with an

expert agency from the beginning of the process.

I received the certicate of conformity for my original applica-

tion four months later by mail. Bureaucracy in a foreign govern-

ment can hurt your project in many ways. You have to go along

with the experts to solve your problems with the bureaucrats even

if it costs your project an arm and a leg.

LESSONS LEARNED FROM THIS PROJECT EVENT

Let certied people or companies handle government

bureaucracies in foreign countries.

Do not cut corners to reduce your cost when dealing with

foreign governments.

Case5.11: Natural Disaster Insurance

We were contracted to design, build, and install communication

equipment in a gas pipeline in Bangladesh. We prepared and

tested all subassemblies of the equipment in our facilities. en

we packaged them in waterproof crates and shipped them using

land/ ocean/ land routes to their destination. We had a reliable

freight forwarder who insured the goods that were being shipped

against all risks of physical loss or damage for door- to- door trans-

portation. All risks cargo insurance covered damages during

loading and unloading, all transportation, war, strikes, riots, civil

commotion, theft, and nondelivery of any portion of the ship-

ment. Our cargo insurance even covered jettisoning of containers

during the voyage in the ocean that could be encountered due to

adverse conditions.

e total cargo insurance cost for all the equipment that lled

up two 40-foot containers was over $60,000. e shipment was

scheduled to arrive at the port of Chittagong, Bangladesh in ve

weeks. At the beginning of the fth week, I received an e- mail

from our freight forwarder that the shipment had arrived at the

port of Chittagong and our containers were unloaded success-

fully. I got ready to send my engineering team to Bangladesh for

the installation process.

142

Project ManageMent case studIes

One of my engineers informed me that there was a cyclone

forming in the Bay of Bengal and it was heading north toward

Bangladesh. I immediately called our freight forwarder regarding

the status of our two containers at the port. He assured me that he

would talk to his agent in Bangladesh and get the two containers

transported inland away from the cyclone hit areas of the coast.

He also told me that our all risk insurance did not cover natural

disasters. at was very disturbing news to me. Apparently, we

had to buy separate insurance coverage for natural disasters such

as earthquakes, cyclones, ooding, and so on. To save us around

$10,000 our shipping department and our freight forwarder

decided to bypass the natural disaster insurance for my projects

equipment. I was very worried at that point. I called my manager

and the company president and explained to them the pickle we

were in. en I called my customer to warn them about the status

of their equipment shipment with the upcoming massive storm

and our lack of insurance coverage for natural disasters.

I could do nothing, but wait and pray. I was hoping that my

freight forwarders agent in Bangladesh could move our containers

inland before the cyclone hit land. I started to follow the cyclone

news on the Internet. It was a massive and powerful cyclone pack-

ing heavy rains and destructive winds. It was heading toward the

Indian and Bangladesh coastlines. Satellite images showed the

cyclones spinning tails covering a huge area. Weather forecasters

predicted the storm to make landfall the next day near the border

between India and Bangladesh.

I could not sleep that night. I followed the storm very closely.

ere was no news from our freight forwarder regarding our two

containers whereabouts. e next morning I saw on the news

that the cyclone had made landfall closer to the Indian shoreline.

Chittagong and its vicinity got hit by heavy rains and 100-mph

winds. At 8a.m., I received a call from our freight forwarder that

our two containers were still at the Chittagong port. ey could

not move them inland due to the storm. Our two containers were

under 3feet of water. Luckily, our equipment was very well pack-

aged and all weather protected. e cyclone had a large footprint,

but only its tail hit the port of Chittagong. We came very close to

losing all of our equipment.

As a project manager, I should have questioned in detail the

insurance coverage of my shipment. When I heard that we had

all risk insurance, I did not dig into further detail. at was a

mistake. My team, my management, my customer, my freight

143

case studIes In resource ManageMent

forwarder, and myself had a very scary 36 hours. I wished we had

the extra coverage for natural disasters. What we went through

was not at all worth the $10,000 saved.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to cover and ask smart

questions about every segment of our project. We cannot

leave any unturned stone that might come back and bite

us at the end.

Saving a little money in a large project is not worth the

trouble and the agony you have to go through.

Case5.12: Project Partners

Bidding for a project can get quite complicated. You have to

strengthen your companys position in a bidding war by partner-

ing with other companies in order to have a winning chance. In a

project you might partner with another company or companies for

nancial reasons, for technical reasons, for domestic content rea-

sons (in international bids), and for rules and regulations coverage

reasons. Project management can get complicated in a multicom-

pany team environment. You have to have the responsibilities of

each party well dened. You have to have a well- agreed- upon

pecking order for project management authority.

In a volume production project to build an advanced passenger

vehicle, a complex team of international companies agreed to par-

ticipate in a start- up automotive company. I performed a detailed

feasibility study for the volume production project. Design of the

vehicle was completed by the start- up company and the vehicles

manufacturing was in the prototype phase. In volume production,

the vehicles unibody frame construction was going to be man-

ufactured in Italy by a well- known automotive company. e

drivetrain was going to be supplied by a well- respected French

automotive company. e nal assembly and test of the vehicle

were going to be done in a new volume production plant in the

United States by the start- up automotive company. e project

was being nanced by a couple of high- powered venture capital

investors in the United States. It took about a year of negotia-

tions to bring all involved companies together as a team and to

sign nal contracts. e technical project partners and nancial

project partners were all on solid ground. Everyone was upbeat for

a successful project.

144

Project ManageMent case studIes

e project manager of the whole project, a good friend of

mine, formed three separate project teams, one in Italy, one in

France, and one in the United States. Every team had well- dened

project tasks, project schedules, and a team leader who reported to

him. e project manager had to travel a lot between three project

groups to coordinate and be up to date regarding every task. is

project was in the 1980s, and Internet communication was just

starting and international calling systems were not as good. You

had to be on location in order to assess the true status of a project.

e projects manager had to present cost performance analysis of

the project to nancing groups on a weekly basis. Final assem-

bly and test facilities for volume production were near completion

after a year. During that time, 60 prototypes of the advanced pas-

senger vehicle were built and tested thoroughly and successfully.

Everything for the volume production project was going as

planned. e rst vehicle was scheduled to roll out of the volume

production line in January of 1988. However, stock markets around

the world crashed all of a sudden in October of 1987. Financial

backers of the project had to drop out of the project with their losses.

Eorts to raise additional capital to get the project moving were

fruitless in that nancial turmoil. At the end of 1987, operations at

the new start- up automotive company came to a halt. e project

manager did a heck of a job for three years to bring this highly

complicated multinational project to the gates of volume produc-

tion, but his luck ran out as a result of an unforeseen nancial crisis.

In another project, I was leading a project team to design,

build, manufacture, test, and install high- pressure hydraulic cyl-

inders in a very low temperature environment. My company had

to team up with a seal manufacturer in Germany during the bid-

ding phase of the contract. e German company was responsible

for designing, manufacturing, and delivering to us special cyl-

inder seals. e German companys technical know- how was in

designing and manufacturing high- pressure seals operated in very

cold temperatures. e German company brought a good techni-

cal boost to the winning bid combination. e German company

had a well- dened responsibility, a schedule, and a project team.

ey were supposed to deliver the rst articles in six months. e

project was progressing on schedule. At the end of the fourth

month, there was a shue in the German project team without my

approval. e new team members were novices and they started

to delay their seal delivery dates. e special seals were constantly

failing very low- temperature life tests. I started to get worried.

145

case studIes In resource ManageMent

I met with my companys president and explained the alarming

situation to him. We decided to send our quality manager imme-

diately to Germany to evaluate our projects progress on-site. His

project status reports to me were not favorable at all. is private

and small German company was going through an upper man-

agement shake- up. ey had lost several of their experienced

designers. e quality managers recommendation was to drop

the German company and to nd another partner for designing

and manufacturing special seals for our hydraulic cylinders. I dis-

cussed this emergency situation with my companys president. We

decided together to cancel our seal project partnership with the

German company because of their failure to fulll our joint con-

tract commitments. We could go this route only after getting an

okay from my customers project manager. My customers project

manager agreed with my proposal to change our German part-

ner. My purchasing department and I scrambled to nd another

seal company that could design and provide us special seals in an

expedited schedule. Luckily, we found one close to our facilities

in the United States. My customers project manager and I visited

our new seal design and manufacturing partner for qualication.

e qualication visit was very successful. We signed a contract

with our new special seal design and manufacturing partner in

one week. I monitored their progress very closely. I also had one

of my project team engineers reside at the new seal company for

the duration of the whole project. When everything was said and

done, my company was late one month in delivering our hydraulic

cylinders to our customers site. However, I was very lucky to be

able to turn around the special seal crisis.

At the bidding phase of a project, all project partners look

eager and willing to win the bid. Many unforeseen issues might

surface with our project partners during the execution phase of

the project. As project managers, it is our responsibility to remedy

these project partner issues as fast as we can without damaging

the cost and schedule performance of our project.

LESSONS LEARNED FROM THIS PROJECT EVENT

In a multicompany partnership project environment,

there has to be a mutually agreed upon project manager

who is responsible for the whole project.

You have to be proactive and drop some of your project

partners in a timely fashion if they are not performing

up to par.

146

Project ManageMent case studIes

Case5.13: Cost Overrun Due to Steel Price Increase

I was heading a project to design, build, and test 20 high- load

capacity and high- pressure hydraulic cylinders for a customer in

Brazil. Each cylinder was priced at $200k. e total project rev-

enue was $4M. Each cylinders cost was broken down to distrib-

uted design costs, manufacturing costs, and testing, which was

$120k per cylinder. Material costs for each cylinder were $40k.

Packaging and shipment of the cylinders were the customers

responsibility, namely, delivery was ex- factory. So each cylinder

would have a cost of $160k with a total project cost of $3.2M,

which resulted in a project margin of 20%.

e material cost was mainly the special steel cost used in build-

ing the hydraulic cylinders. We could only use steel from the cus-

tomers qualied countries and qualied suppliers in those countries.

My purchasing agent was screening all the qualied steel manufac-

turing suppliers and dealers. Due to a large demand for steel from

China, steel prices skyrocketed during my project, which we did

not account for in our pricing. With high steel prices our material

costs were going to increase by 50% to $60k for each cylinder. is

unexpected cost increase in steel would have lowered our project

margins to 10%. I had a meeting with my team and with my upper

management to brainstorm the skyrocketing price of steel for my

project. One of the vice presidents suggested that I should discuss

this issue with our customers project manager too. Our customer

had large steel construction projects. Maybe purchasing our steel

under our customers umbrella would give us some relief in price.

After our internal meeting, I immediately sent an e- mail to our

customers project manager to set up a teleconference with him

regarding our projects steel costs. During the teleconference, I

told him that we were going to get a big hit to our project margin

with the current steel prices. We discussed several ways to solve

the high steel pricing issue at hand. He promised to look into the

matter in his company to see if they could help us in any way. ey

also purchased a lot of steel themselves for their other projects.

Our customers project manager got back to me in a week with

exciting news. He said that they just qualied a new steel ven-

dor in South Africa. ey were ready to purchase a substantial

amount of steel for themselves for another project. He discussed

our high steel price issue with his material purchasing manager.

His material purchasing manager agreed to piggyback us onto his

order in order for us to get a reasonable discount. His material

purchasing manager was leaving for South Africa in two days to

147

case studIes In resource ManageMent

nalize his steel order. I proposed that I send my purchasing agent

along with him so that we could get steel for my project at a rea-

sonable price by riding on their coattails. Our customers project

manager and their purchasing manager were very understanding

and helpful in accepting my proposal.

My purchasing agent traveled to South Africa with our cus-

tomers purchasing manager. After a couple of days of negotia-

tions, together they negotiated a good deal for us with the new

South African steel supplier. We only had to pay $8k extra for

each cylinders steel. is steel supplier was also able to provide

the steel in a timely manner for my project with the required

material certicates. I was lucky that I was able to piggyback my

projects special steel order with my customers substantial steel

purchase order. is deal was quite a success story for my project

during continually rising steel prices. It saved our projects margin

from going down to 10%. With this new South African steel deal,

our projects margin eroded down to a reasonable value of 16%.

I was elated with the help I received from our customer on this

steel deal. I sent our customers project manager and his purchas-

ing manager two bottles of ne whisky for their excellent support

in helping us to get my projects steel at a very reasonable price. I

also gave my purchasing agent a dinner gift certicate for two at

a restaurant of his choice.

I kept my upper management informed continually about the

status of the South African steel deal. ey were very happy about

the nal steel deal. I asked the president of my company to write

a thank you letter to the president of our customer while praising

the help we got from our customers project manager and from

their purchasing agent in our steel deal. Teamwork like this went a

long way in making a project a success in a win- winsituation.

LESSONS LEARNED FROM THIS PROJECT EVENT

An unexpected rise in material costs during the execution

of a project will bite into your companys prot margin.

It is a good practice to lock down material costs at the

beginning of a project without any delay before surprise

increases hit your project.

Case5.14: Actual Cost of Work Performance

As the project manager I had to keep track of the schedule per-

formance index and cost performance index for every task group.

148

Project ManageMent case studIes

I presented these two important schedule performance and cost

performance indices to upper management every two weeks or at

most every four weeks. Schedule performance indices were eas-

ier to calculate because input to work completion estimates were

determined by me and task groups. However, it was very dicult

to obtain input for cost performance indices.

I had to chase our accounting department every month in

order to be able to collect all costs charged to my projects charge

numbers. e accounting department was always late in getting

all charges collected. ey also made unthinkable mistakes. I saw

many charges from unrelated company personnel to my project.

I saw several equipment costs charged to my project by mistake

or knowingly. At the end of every scal month, dened as four

weeks, four weeks, and ve weeks, I had to get these erroneous

charges cleaned up before I could determine the actual cost of the

work performed by every task group of my project.

I expressed my concerns about delays and errors occurring in

the accounting department to my manager. My manager set up

a meeting with the chief nancial ocer. During the meeting, I

voiced my concerns with examples. I emphasized that my project

was a very dynamic one with a tight budget. I had to know the

charges made to my projects charge numbers, 14 of them, at most

within a week from the end of the scal month. I asked them to

allow me to sit down with the accounting departments personnel

at the end of every scal month to go over all the charges made

to my projects account numbers. e chief nancial ocer agreed

to my requests and promised to improve cost reporting delays and

errors.

One month passed yet the situation with cost accounting did

not improve. Two months passed and it was the same old story. I

had to get my projects cost accounting xed. I, myself, made an

appointment with the chief executive ocer of the company and

laid in front of him the details of our companys cost accounting

delays and errors. He told me that he was aware of the slow pace

of our accounting department in preparing the scal monthly cost

report. I told him that I could not fulll my project management

duties in a timely manner and take the necessary steps to correct

for cost overruns at this tempo. He promised me that he would

discuss the accounting department issues with the chief nancial

ocer immediately and they would make the necessary improve-

ments to enhance the companys cost account speed and error rate.

149

case studIes In resource ManageMent

At the end of the next scal month, the cost report came out in

two days. ere was one error in my projects cost report. I was so

happy. I sent thank you e- mails to our chief nancial ocer and

copied our chief executive ocer and my manager. I was able to

get the actual cost of work performed within two days after every

scal month. I was able to balance my under budget task groups

with over budget task groups and determine what actions to take

to improve my projects cost estimates to completion. More often

than not, my projects overran the budgeted cost of work. en I

had to present the overrun reasons to my upper management and

get their okay to dip into my projects contingency funds or dip

into the companys company margin.

ere was another major issue with the project cost account-

ing, which was the timely submission of travel expense reports.

My team members led their expense reports within a week of

their return to home base. However, some manufacturing depart-

ment engineers and some quality department engineers submitted

their trip expense reports one to six months late. I had to nudge

every one of them and their managers to get their trip expense

reports led with the accounting department in a timely fashion.

Finally, I got tired of nudging them and took the trip expense

report timely ling issue to my upper management. After a couple

of discussions with upper management, it became a requirement

in the company for everyone to submit their trip expense reports

within one week of their arrival to home base.

Monitoring schedule and cost performances of a project very

closely at regular intervals is a must for a project manager. You

have to bring your companys other departments in sync with your

projects dynamic environment. e challenge is to be able to col-

lect all schedule and cost performance data in a timely fashion

from your foreign project partners.

LESSONS LEARNED FROM THIS PROJECT EVENT

Your projects cost performance can be hampered by your

nance departments delays and errors.

A trip expense report for a project should be led and

approved within a week of completion.

Periodically always check every item charged to your project

152

Project ManageMent case studIes

my task was to nd a remedy to this crisis fast without hampering the

progress of my project as described in Case6.5.

Traveling to foreign countries for a job can be very strenuous. It

requires detailed preparation. Passport issues, visa issues, money

issues, security issues, language dierences, hotels, transportation,

and foreign contacts all have to be dealt with in utmost detail and

accuracy ahead of a trip. As project managers, it is our responsibility

to make sure that all the is are dotted and all the ts are crossed before

a foreign trip is made as shown in Case6.6.

Nonperforming and/ or underperforming team members are always

an issue during the life of a project. Keeping them on the team or

getting rid of them has to be weighed very carefully. Risk analysis of

your actions has to be thought out in utmost detail. e eects of an

underperforming team member can be very destructive in a dynamic

team environment. Such a situation is detailed in Case6.7.

One of the important tasks of a project manager is to attend special

ceremonies involving your team members. ese ceremonies can be

birthday parties, weddings, patent presentation banquets, technical

society presentations, and so forth. As a team leader one of your main

functions is to participate in your team members celebration events.

Such an international event is detailed in Case6.8.

A work environment should be like a second family environment

away from home. Every employee should be able to talk and express

his or her issues and concerns to their managers, upper manage-

ment, and/ or to human resources without any reservations or fears.

ese issues and concerns can be personal ones, work- related ones, or

community- related ones. As managers, our responsibility is to help

every employee as much as we can to make them feel that they are

always under our companys family umbrella as described in Case6.9.

In a project environment, during the course of events, several

unexpected sacrices can come from any one of your team members.

Sometimes these sacrices can come from people outside of your

team. As the project manager, you have to recognize and appreciate

these kinds of above and beyond duties. Such an example is detailed

in Case6.10.

I have seen many project teams go through a honeymoon period at

the beginning or at the middle of a project throughout my career. As

project managers, we have to watch for slacking signs from every team

153

case studIes In teaM ManageMent

member and take the necessary action to keep the pressure cooker at

a constant stress level. An unfortunate slacking period is detailed in

Case6.11.

When a good employee who helped you a lot in your project is leav-

ing the company, you have to provide a memorable farewell to him or

her. I managed to give a great farewell party to my senior mechanical

tool designer when expenses were very restricted in my company as

detailed in Case6.12.

As I gained experience in project management, I only made prom-

ises that I could keep to my team members. I researched thoroughly

beforehand, if I could keep my promise. When I gave a time frame

for a promise, I always accomplished it within that time frame as

depicted in Case6.13.

Several unexpected events can occur during the course of a project.

Some project managers get upset and blow their tops, but this type

of behavior does not solve anything. Negative reactions make things

worse. You have to be coolheaded, versatile, and rm to nd other

solutions fast in order to bring the dicult situation at hand under

control as shown in Case6.14.

As project managers, we have to sometimes act as psychologists.

We should not take drastic actions on a whim or with a burst of anger.

We have to consider all repercussions that an immediate action might

cause in our project as shown in Case6.15.

Specialists and/ or scientists can be very moody and demanding in

a team environment. As a project manager, you need their expertise.

You have to treat them with respect. You have to create a exible

boundary with their needs and with your projects requirements. If

you become a hard- liner with such people, your project will suer in

the end as shown in Case6.16.

A projects work atmosphere can be very dierent after a personal

vacation or after holidays. As project managers, we have to settle

down anxiety or lackadaisical behavior after such events as detailed

in Case6.17.

Maternity leave can be very disrupting to a projects progress. As

project managers, we have to work with our human resources depart-

ment in order to make the right decisions and appropriate arrange-

ments to solve the issues at hand as detailed in Case6.18.

154

Project ManageMent case studIes

As project managers, we have to encourage and empower our team

members constantly to make improvement suggestions to their tasks.

Such improvement suggestions can come from unexpected sources.

We have to praise and reward contributing suggestions to our project

as detailed in Case6.19.

Eciently run meetings are the backbone of a project. Meetings

have to be standardized and managed properly so that team members

precious time is not wasted. A team member should not be bored and

he or she should contribute constructively while present during a proj-

ect meeting. Especially in large team groups, as it was in Case6.20,

breaking up a meeting into smaller subgroups can be very eective.

Mishaps happen more often than not while preparing for critical

meetings or deadlines in a project. Overworked and overtired team

members become prone to mistakes and accidents. As project manag-

ers, we have to watch over our team members and over ourselves for

fatigue and for burnout conditions as detailed in Case6.21.

Case6.1: Getting a Senior Wafer Fabrication

Engineers Life Stabilized

e project was to set up a new 6 wafer fabrication for computer

disk drive heads into production. I had an engineer assigned to

every piece of equipment in the new wafer factory. ey were

tasked for sourcing the equipment, qualifying the equipment, and

optimizing that particular equipments process for the computer

disk drive head specications using design of experiments. e

project was fast paced with a duration of six months.

One of the senior engineers in charge of the nickel iron plating

module was starting to slack o and he was falling behind in his

tasks. He was the owner of the nickel iron plating module. He wrote

the specications for it. He sourced the manufacturer. He went

to North Carolina to accept the module. He was now performing

design of experiments to optimize the pulsed power supply, current

density, bath temperature, and agitation of the electrolyte solution

for critical nickel iron parameters.

I went to his oce and started to discuss the delays in his tasks

and asked him if he needed any help to catch up. He said he had

some family issues and he was certain that he would be able to

complete the design of experiments in time and qualify the nickel

iron plating module. A week passed. I sensed that things were

155

case studIes In teaM ManageMent

not progressing smoothly. is plating engineer was under a lot

of stress. I called him to my oce and started to have a heart- to-

heart discussion about his missed commitments. He started to

open up and explain to me his family issues. His wife left him

and they were going through a divorce. During this turmoil,

his 12- year- old son was staying with him. He had to run every

day and take him to school and back from school. He was trying

to sell his house. e poor guy was ready to ip due to extreme

stress. I asked him if I could be of any help. I told him to think

about it. I did not want to lose him at this juncture of the project

and bring in a new engineer from the cold. I asked him if we could

have lunch together that day. He said okay.

Until lunchtime I made a couple of telephone calls to human

resources and I saw my supervisor to nd out if the company

could provide him a company- owned apartment for the next six

months. I explained my senior engineers situation in condence

and how it was aecting my project. I received favorable responses

from all sources. He did not have to pay any rent and the company

apartments were very close to his sons school.

We had a heart- to- heart discussion about his family situation

during our lunch. I told him about the companys apartment oer.

He was very appreciative and accepted it. I asked him if there was

anything else I could help him with in order to stabilize his family

life. He told me that he was looking for a good divorce lawyer. I told

him that I would investigate nding a good divorce lawyer for him

through our legal department. I emphasized to him the importance

of his work for the start-up of the 6 wafer factory. I also empha-

sized to him to come to me if he ran into any other dicult hurdles.

I had to walk a ne line when I dealt with this troubled senior

engineer. I wanted to help him all I could without becoming too

friendly with him and without losing his respect for me. Getting

sucked into non- work- related issues with a team member can be

very tricky for a project manager. I had to go along with the com-

pany rules and regulations. I would not promise him something

that I could not deliver. Above all, my projects health was my

main concern.

I went to our legal department and discussed the divorce law-

yer issue with the companys head legal counselor. He called a

divorce lawyer friend of his in town and arranged a meeting with

my senior engineer. e two met and agreed on terms. e senior

engineer was very grateful to me. On top of everything, he got a

substantially reduced rate from the divorce lawyer.

156

Project ManageMent case studIes

In two days time, the senior engineer moved into the com-

panys apartment. He signed his son up for an afterschool pro-

gram so that he did not have to rush to school in the middle of

the afternoon. His performance at work improved instantly. He

put in some extra hours and nished his tasks only one week late.

As a project manager, I was very gratied that I could help

a troubled member of my team. Other options such as replac-

ing the team member in the critical segment of a project or

assigning another junior engineer to help him could have been

more risky.

Identifying risky areas in a project should be a continual task

for a project manager. After a risky situation is identied, you

should identify various paths to cure the risky situation. You

should choose the path that you as the project manager can have

the most control over. Risk management in a controlled fashion is

very crucial to a projects success.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to be good psychologists

too.

Identifying and dealing with a team members stress

level and risky condition are our number one responsi-

bility as project managers.

Helping a project team member to get on track in his or

her personal life is very gratifying.

Case6.2: A Recalcitrant Engineer on a Project Team

I was asked to develop the next generation of thin lm magnetic

heads with a team of four physicists and electrical engineers in

one year in order to keep ahead of the competition. e magnetic

head design had to be very ecient and increase the areal density

of magnetic recording at least an order of magnitude. I had a very

bright and innovative group on my team. e team was given to

me and I did not have any say in picking the team members.

We started the project on a very positive footing. After a week,

one of the prominent members of the team started spreading neg-

ative rumors about the company and he was not attending some

of our team meetings. He came to work late and left work as he

pleased. He had a Ph.D. in physics from MIT and he behaved like

a disobedient child. His behavior aected my teams morale and

started to hamper the progress of my project.

157

case studIes In teaM ManageMent

I called him to my oce and had a heart- to- heart discussion

with him about his attitude. I told him that he was a very valuable

member of my team and we depended on his magnetic design

calculations and recommendations. He told me he was what he

was and he did not like to work in a team environment. I asked

him not to spread rumors against the company and discourage

the team members and asked him to try to work with the team

members as eciently as he could. I told him I would not mind

him using exible hours at work. He agreed that he would try his

best and left our meeting with good intentions.

Another week passed, but nothing had changed. His behavior

got worse. He started to bring some of the other team members to

his oce and shut the door to have hours of discussions. I learned

that these discussions were not about our project. ey were dis-

cussing the stock market, who was going to make a bid to buy our

company, when our companys president was going to be red, when

was a layo going to happen, and so on. is physicist was a team

breaker and not a team builder. I had to take more serious steps to

bring him in line so that the project could progress smoothly.

I went to his supervisor and discussed this physicists behavior

in condence with him. His supervisor told me that this physicist

was a recalcitrant person and he did not like to be under anyones

authority, he looked down on everyone, and he thought his knowl-

edge was superior to anyone around him. I told his supervisor that

I needed this physicists contributions to my project. I told him

that I was going to control this grown up and obstinate scientist

very closely so that my team could successfully complete the project.

I had a team meeting without the recalcitrant physicist. I asked

my team members not to interact with this physicist. I told them

that I would be the only interface between him and the team. I

went over the reasons for my actions. e rest of my team mem-

bers understood the delicate situation with this physicist. After

the team meeting, I called the disobedient physicist to my oce

and explained to him that team harmony was necessary to succeed

in our project. I told him that we needed his invaluable input to

the project. I asked him to interface only through me regarding

the project and not with the team members. I also asked him to

move his oce next to mine, which luckily was not occupied at

the time. I asked him not to attend the team meetings. I cautioned

him not to have demoralizing discussions with my team members.

I told him that my actions were not to punish him, but to make

the project a successful one. He reluctantly agreed to my requests.

158

Project ManageMent case studIes

en I went to the human resources department and explained

to the head of the human resources department the diculties I

was having with this particular employee on my team. I outlined

all the actions I was taking to remedy the issue. I also emphasized

that I needed this physicists contributions for my project. She

asked me to write a review letter about him and list all the actions

I was taking to remedy the behavior of this physicist. I wrote a

detailed review letter and discussed it with the recalcitrant physi-

cist. I gave a copy to him. I also gave copies of my review letter to

his supervisor and to the human resources department.

is obstinate physicist worked under my very close supervi-

sion for the next six months and he contributed extensively to my

project. He heavily cut his demoralizing activities during these six

months. I made him work in a completely isolated environment.

Unfortunately, at the end of six months, he was let go during a

layo because of his behavior. He predicted the companys layo

timing right on the dot. He was a paragon of magnetism as a

physicist, but he was not a team player at all.

LESSONS LEARNED FROM THIS PROJECT EVENT

You have to take immediate action to deal with people

who are disrupting your project teams harmony and who

are demoralizing your project team members.

Some high- level scientists behave like a child in a team

environment. ese kinds of people need to be micro-

managed with very close supervision.

Case6.3: Error in Motor Mount Moment

of Inertia Calculations

I was heading a vehicle design group to design an all terrain vehi-

cle for a German customer. e design was completed on time

and approved by the customer. My companys manufacturing

group was starting to build 20 vehicles for beta testing. All chas-

sis were built and all the motor mounts were built. ey were in

the process of welding them together. During this juncture of the

project, one of my structural engineers walked into my oce with

a red face and told me that he made a calculation mistake during

the design of the motor mount beams. He forgot to divide the

beams moment of inertia calculation by a constant, namely by

12, and he was very sorry about it. Another structural engineer

who checked his calculations also missed this moment of inertia

159

case studIes In teaM ManageMent

calculation error. is error created unacceptable bending stress

levels in the motor mount beams during dynamic loading.

I immediately called our manufacturing manager and asked

him to put a hold on all chassis and motor mount construction. I

told my structural engineer to keep cool. I told him we all make

mistakes. e important thing was to learn from our mistakes

and not to repeat them again. I called the calculation checker to

my oce. I advised him in a similar fashion. I told both of them

that I would control the damage. I asked them to get together,

focus, and revise the motor mount calculation and come back with

relined drawings in a day. I called a team meeting to explain this

unfortunate error to all team members and to discuss what steps

we should take so that similar errors would not occur again.

e team meeting was very productive. I praised the structural

engineer for coming forward and discovering his error in the early

phase of manufacturing. e focus of the meeting was to nd a

better way to check our calculations so that they would be error-

free. We decided to double our checkpoints for all critical calcula-

tions. One of the checkers was going to be outside the project team,

namely an independent and a well- qualied checker. is new

design process would add a couple of extra days to the release of

calculation documents, but would give us more reliable results. e

manufacturing manager and the manufacturing lead for the proj-

ect were also invited to the team meeting. We discussed time and

cost damages due to the design error. All 20 motor mounts were

going to be scrapped. e total time lost in manufacturing would

be about ve days and it would cost the project an extra of $20k

to build the new motor mounts. Manufacturing processes in other

subassemblies would be able to move forward. ese schedule and

cost impacts were mild and they were recoverable.

en I called a meeting with my manager and the structural

engineers manager. I explained the unfortunate events to the two

managers. We went through my solutions. ey were both satis-

ed with my teams solutions to the error. However, the structural

engineers manager got upset with his engineers. He was a ashy

type of a person. He wanted to discipline both of them. He even

leaned toward ring them. I asked him to cool down a little bit.

I told him that we all make mistakes, but the key was to learn

from these mistakes and not to repeat them again. I asked the

structural engineers manager not to discipline his engineers. I

told him that these two engineers are very promising young ones.

ey needed grooming and needed a positive support from a

160

Project ManageMent case studIes

negative event. ey would contribute immensely to the company

projects in years to come. I told the structural engineers manager

that the structural engineer came forward to me on his own with

a red face. He was very honest and very sorry about the error he

made. We were lucky to catch the error in the early phase of man-

ufacturing. My project was going to get a minor hit, but in the end

the two structural engineers would gain a real- life experience. We

discussed the issue heatedly for an hour. e structural engineers

manager nally agreed with my recommendations and promised

not to do anything counterproductive to discourage them.

Errors are part of real life in engineering projects. ey can

happen in design, in the customers specications, in manufactur-

ing, in quality control, in receiving inspection, at subcontractors,

at certication laboratories, and so on. e key is to catch them

before the project is completed. Hopefully, the error would cause

a minor distraction to the project. If everyone involved with the

project could learn from the mistake made, you could make a big

contribution to your company as a project manager. I have heard

of several major errors made during a project too, such as in a

space project when the payload of an unmanned space probe was

calculated in pounds instead of kilograms.

LESSONS LEARNED FROM THIS PROJECT EVENT

Errors are more likely to occur during the execution of

a project.

As project managers, we have to be coolheaded and make

sure that our team learns from a mistake made in order

not to repeat it again.

As project managers, we have to correct errors in a

timely fashion.

As project managers, we have to gather our project team

in order to explain what the error was and how we are

going to take care of it.

Case6.4: Training in the Japanese Language

My company, a customized computer component designer and

manufacturer, planned to increase our market share in Japan. I

was given the engineering responsibility for guiding our design

and application engineers to go periodically to Japan to visit our

potential customers. We had to present our future products and

convince our potential customers as to how advanced our products

case studIes In teaM ManageMent

were and how advanced and controlled our manufacturing pro-

cesses were.

I went to Japan several times with my design and application

engineers. We all were struggling to get to know the Japanese

culture and their workplace ethics, such as how to greet people

from your customers end, how to exchange business cards, how

to exchange small gifts, how to behave in a meeting, how to make

small talk, how to behave at lunches and dinners, and so on. When

I returned to the United States from my second visit to Japan, I

decided that we should be trained in the Japanese business culture

and language. I requested a meeting with my companys president

regarding the necessary training, if we wanted to succeed in busi-

ness in Japan.

My company president was very receptive to my training idea in

the Japanese business culture and language. He further proposed

that this training should be a requirement for all of our employees

who dealt with Japan. He asked me to arrange it with our human

resources department. Our human resources department found a

perfect trainer from the University of California. He was Japanese

and he was studying for his Ph.D. degree in psychology. He came

to our company every Tuesday for a year at lunchtime and trained

us on the ins and outs of Japanese business culture and business

language. He taught us important Japanese phrases that we could

use during our encounters with our Japanese customers. He gave

us recorded tapes lled with Japanese phrases so that we could

practice the pronunciations at our leisure. Since Japanese is a pho-

netic language, we learned pronunciation of phrases with ease.

Every one of my engineers who dealt with Japan, all of our

sales personnel, purchasing personnel, and even executives who

dealt with Japan took this one- year training course. Brown paper

bag lunches were provided by the company. ere were 26 train-

ees in the class. We had written and oral examinations once a

month. Fifteen of us passed the course with ying colors includ-

ing all of my engineers who dealt with Japan. Ten of us unked

the course and one dropped out because of health reasons.

e course taught us a lot of small talk phrases and greeting

phrases in Japanese. We learned greeting phrases such as pleased

to meet you (hajimemashite), good morning (ohayo gozaimasu),

and thank you very much (domo arigato gozaimasu). We learned

the telephone hello response, which was moshi moshi. At the end

of a long meeting in Japan, it was customary to write down action

items on the board with the names of owners and due dates. After

162

Project ManageMent case studIes

everyone agreed on the action items list, the scriber of meeting

minutes sent the action items list to everyone involved by e- mail.

Once, at the end of a 12-hour meeting, I started the action items list

by writing action items in Japanese Kanji characters on the board.

All of our Japanese colleagues almost dropped out of their chairs.

ey had a good laugh at the end of a long and strenuous meeting.

We learned how to sit in pecking order around a conference

table. As guests, our team always sat on the side of the table that

was away from the conference room entrance door. We learned

when to talk during a meeting. e highest-ranking member of

our team always answered their questions. If that ranking member

needed help from other members of his team, he mentioned that so

and so would be responding to their particular question. Dinners

were less formal, but again high- ranking members of both teams

sat at the ends of the dinner table. A 12-hour meeting from 9a.m.

to 9p.m. and afterward a 3-hour business dinner until midnight

was a normal day in Japan.

e one- year business culture training course for Japan helped

my company to gain ground in their marketplace. After two years,

we saw a 10-fold sales increase for our products in Japan. e

president of my company thanked me for suggesting the Japanese

business culture classes for our people. Also, everyone who took

the course was very appreciative for gaining such an eye- opening

experience into Japanese culture and language.

LESSONS LEARNED FROM THIS PROJECT EVENT

Every member of your team dealing with a foreign coun-

try has to know that foreign countrys history, culture,

and workplace ethics.

Knowing the business language of a foreign country that

you are dealing with goes a long way in negotiations and

in gaining mutual respect among players.

Case6.5: A Project Engineer Left the Company

under Adverse Conditions

When I started a project with a team, I made sure that I had all

the information about each team members vacation plans, wed-

ding and honeymoon plans, and other time- o plans. I put every

team members personal time- o plan into the project schedule

and I made sure that there were no conicts with project tasks and

deliverables.

163

case studIes In teaM ManageMent

In one of my projects, a senior engineer on my team decided to

take a three- month sabbatical leave from the company right in the

middle of the project. He was a crucial member of my team. He

was doing dynamic stress analysis for the product we were design-

ing. He asked me to have a meeting together with his manager.

During the meeting, he explained that he was an avid cyclist. He

was invited to train with a cycling team and to enter an interna-

tional race with this cycling team. He requested a three- month

sabbatical leave starting in two weeks. is was quite a shock to

me. I told them that it was not possible for him to leave my project

at that critical juncture. ere was no one else in the company

who could step in and take over his tasks. He insisted that he

had to take three months o from work, he had already made a

commitment to his cycling team, and no one could stop him. I

was upset with his irresponsible behavior. I told him that his rst

responsibility should have been to the project which he was an

important part of. He should have rst consulted with us before

making a commitment to his cycling team. He should have told

us his sabbatical leave intentions four months ago when the proj-

ect started. He understood that he was not going to get anywhere

with me. So he said to his manager that he wanted to give his

two- week resignation notice and leave the company. He immedi-

ately left his managers oce without saying goodbye.

His manager was very upset too with his engineers childish

and obstinate behavior. He called the human resources depart-

ment in front of me and explained to them the unfortunate situa-

tion. e human resources director immediately went over to the

senior engineers oce to discuss if there was a way out of this

quagmire. She reported to the senior engineers manager and to

me that there was no solution to the senior engineers adamant

request. ey decided to walk him out the door at the end of the

day without any delay. I was able to salvage some of the modeling

and test runs he had done for my project before he left for good.

I had to scramble to nd a replacement for my teams dynamic

stress analyzer. I had a design review coming up in two months

with the customer and my team had to nish all the pertinent

calculations and designs before the phase 1 review meeting. To

nd a replacement engineer with a similar skill set would have

taken at least two to three months. A novice engineer right out

of college would not be able to help me. I needed an experienced

mechanical engineer in stress analysis. Even if we had to steal one

from another company, it would have been awhile to get him or

164

Project ManageMent case studIes

her to be productive on my team. e only solution was to go out

and nd a consulting rm in dynamic stress analysis and bring

them on board for my project.

I went to a couple of prominent stress analysis companies in

the United States and interviewed them for my project. ey were

expensive. I did not have any contingency funds in my budget to

cover these unexpected extra costs. I started to look at the possi-

bilities outside the United States. I found a stress analysis company

in India and one in the United Kingdom. I interviewed them by

teleconferencing. I also checked their references. I made sure that

they were using the same version of the stress analysis software

as we used in house. e stress analysis company in the United

Kingdom had the right expertise to help my project. eir price

was in the middle between the U.S. and Indian companies. I went

to my manager and discussed my search results with him and I

told him that I was going to sign a contract with the UK subcon-

tractor to complete my projects dynamic stress analysis require-

ments. He was pleased that I was able to nd a potential candidate

in a week. He assured me that the company would absorb the

extra cost of the UK subcontractor in the project margin. My pur-

chasing department and I completed the subcontract agreement

with the UK subcontractor in three days. ey started to work on

my team two weeks after the senior engineers departure.

I did all the communication by teleconferencing with the UK

subcontractor. ey came up to speed fast. ey also worked 60 to

70 hours per week without charging me overtime. I was able to get

all the required calculations and designs completed in two months

time before the phase 1 review. I did not inform my customer

about this crisis we had because this crisis was totally an internal

issue and it did not aect the progress of the project. I resolved

this crisis without disturbing my customers project manager.

ese kinds of unexpected situations can arise in any project.

As the project manager, my task was to nd a remedy to this crisis

fast without hampering the progress of my project.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to make sure that at the

beginning of a project, we have all the information

about each team members vacation plans, wedding

and honeymoon plans, and other time- o plans on our

project schedule.

165

case studIes In teaM ManageMent

A team members work plan can change suddenly, which

can aect your projects progress adversely.

Replacing a specialized and experienced engineer is very

dicult at a moments notice.

Case6.6: On- Site Equipment Training

One of the requirements of building and installing a hydraulic

mover on an oil platform project was to train the customers person-

nel on-site. As the project manager of the project, I decided to send

a senior engineer for this training. e training was in the North

East region of Russia and it was for two weeks in April. April was

supposed to be the beginning of spring weather in that region. My

senior engineer prepared an extensive MS PowerPoint presentation

for the training. He got his laptop computer and his thermal under-

wear and left for this cold region of Russia in early April.

He was to connect with our companys liaison in Vladivostok

and then travel together to the oil platform site. My engineer did

not speak a word of Russian, but our companys liaison was going

to help translate his training presentations. e training was sup-

posed to be done with two groups of 10 personnel who did not

speak or understand a word of English. All the meeting dates and

locations in Vladivostok with the company liaison were arranged

and conrmed by Internet correspondence. My engineer arrived

at the airport. During passport control the agent asked him why

he was entering Russia. My engineer honestly said that he would

be training 20 Russian workers on an oil platform. e agent

emphasized that my engineer did not have the proper visa to enter

Russia for training purposes. On top of that, his passport expira-

tion date was within six months of his exit date. His passport

expiration date should have been six months beyond his exit date

from Russia. My engineer started to plead that he was there for

only two weeks to help the Russian workers get trained on crucial

equipment at an oil platform. e passport control agent took my

engineer to a small cubicle with a glass enclosure and called his

supervisor who spoke a little English. My engineer pleaded his

case to the supervisor. ey together tried to call our companys

liaison in town, who was not to be found at work or home. e

supervisor threatened to send him out of the country with the

next international ight, asked him to stay put, and left the cubi-

cle. My engineer waited in the cubicle for three hours and nally

the supervisor showed up again with smiles. He told him that

166

Project ManageMent case studIes

he discussed his situation with authorities in Moscow and they

decided that he could enter Russia for only two weeks as a tour-

ist. Finally, my engineer said, Let me be a tourist for two weeks

in your country. en they shook hands and his passport was

stamped with the tourist entry date.

My engineer took a taxi downtown to our company liaisons

oce. He found a secretary there who did not speak any English.

ey were able to communicate with hand motions and by writ-

ing. Finally, my engineer understood that our companys liaison

was out of the country in South Korea for a two- day trip. Our

companys liaison never informed us about the change in his plans.

My engineer decided to stay in Vladivostok for two days and wait

for the company liaisons return. He checked into a boutique hotel

close to the company liaisons oce and called me to detail all the

hurdles that he crossed when he arrived in Russia. I agreed with

him that he should wait for two days for the companys liaison

before traveling to the training site because of the language barri-

ers. I told him to hang in there and told him that I would inform

our customer about the two- day delay in starting the training.

My engineer almost froze to death at the boutique hotel where

he was staying. Apparently, the hotel personnel turned o the heat

at night from 9p.m. to 7a.m. to save on fuel costs. e poor guy

had to buy extra blankets to keep warm at night. He started to

check out after two days at this freezing hotel, but his credit card

bounced because his credit account was maxed out. He did not have

enough cash on him to pay the hotel. He called the companys liai-

son oce and nally he was able to touch base with the companys

Russian liaison. e companys liaison came to the hotel and paid

my engineers hotel bill. My companys liaison was not even sorry

that he was two days late to his appointment with my engineer.

Together they traveled by bus to a village that was 20miles away

from the oil platform. en they took our customers shuttle boat

to the platform. ey stayed on the platform for 10days because

my engineers visa expired two days after the end of training. He

had to condense his training into two ve- day sessions. He could

not use his laptop computer on the platform because his computer

battery died. He could not charge his computers batteries since

he did not have the right adapter to the oil platform outlets. He

transferred his MS PowerPoint training le to the company liai-

sons laptop computer and used his computer during the training

sessions. It was so cold, 20C, in North East Russia in April that

my engineer had to sleep wearing his sweaters, pants, and alpaca

167

case studIes In teaM ManageMent

socks at night. He was lucky that he did not get sick during those

10 training days. Overall the training went well. He exited Russia

without any issues and made it safely back home.

I had a long meeting with him when he got back. I told him

that it was my fault not to warn him about the validity of his pass-

port duration. It was also my fault that I did not advise him on the

type of visa that he should get for training purposes. He should

have gotten a business visa. We discussed his credit card balance

issue. He accepted that it was his fault not to straighten out his

balance before he left for his trip. I went to my upper management

and laid out the details of my engineers troubles in Russia and

made sure that my company cut ties with our liaison there.

Traveling to foreign countries for a job can be very strenuous. It

requires detailed preparation. Passport issues, visa issues, money

issues, security issues, language dierences, hotels, transporta-

tion, and foreign contacts all have to be dealt with in utmost detail

and accuracy ahead of a trip.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to be extra sure that people

working for us in foreign countries are dependable.

Before we send our team members oshore, we have to

verify the validity of their travel documents.

Case6.7: Getting Rid of a Lackadaisical Team Member

I was heading ve separate groups of engineers in a wafer fabrica-

tion project. Each group had its own manager. One of the engi-

neering groups was responsible for quality control of the incoming

materials and outgoing product. ere were visual inspection corre-

lation issues regarding the outgoing wafers with our South Korean

plant. My quality engineering groups manager and I decided to

send one of the seasoned quality engineers to South Korea to train

the South Korean engineers and inspectors per our inspection cri-

teria. We wanted to eliminate our dierences in visual inspection.

My quality engineering groups manager explained in detail to

our seasoned quality engineer what his responsibilities would be

in South Korea. He had two weeks to train the South Koreans

and then return to his home base. He made his trip and trained

the South Koreans and got back. He gave me and my quality

groups manager a brieng in my oce about his accomplish-

ments in South Korea. To our surprise, he only trained the South

168

Project ManageMent case studIes

Koreans on one inspection parameter, which was the highest cor-

relation discrepancy on the Pareto chart. He did not deal with any

of the other inspection parameters. He made his trip and spent

thousands of dollars to improve our inspection correlation only

in one parameter. He overlooked all other 15 parameters which

were on his checklist. I asked him why he neglected all the other

inspection parameters. He responded in a spiritless manner that

he had time to x only one parameter. I asked him why he did

not call his manager to discuss an extension of his stay so that he

could complete his tasks fully. He said in a lackadaisical way that

he felt that he completed his mission in South Korea. I politely

asked the seasoned quality engineer to leave my oce and com-

plete his trip report.

I closed the door to my oce and started to discuss the per-

formance status of the seasoned quality engineer with my quality

groups manager. e seasoned quality engineer had been with our

company for 15years and his performance went downhill every

year. He was experienced, but he was denitely lazy. My quality

groups manager did not document instances of his poor perfor-

mance. His annual performance reviews were mediocre. I told

my quality groups manager that this seasoned engineer would be

a listless mentor for our young and dynamic engineers. I asked

him if there was a way to revive the spark in work habits of the

seasoned quality engineer. My quality groups manager told me

he discussed the mediocre performance with the seasoned qual-

ity engineer several times during his annual performance reviews

and told him that his performance was not good enough for his

advancement in the company. e seasoned quality engineer told

my manager that he is content with his job level and that he did

not care about advancement. I told my quality groups manager

that we should get rid of him as soon as we could. My quality

groups manager agreed with me.

I immediately called our human resources director and asked him

to come to my oce. e three of us discussed the seasoned quality

engineers poor performance, his spiritless behavior, and his termi-

nation steps. Our human resources director told us that our com-

pany had an at- will employment policy and that we could terminate

a nonperforming employee at any time without waiting for a layo.

He also cautioned us that my quality groups manager should docu-

ment the seasoned quality engineers poor performance and spiritless

behavior during the South Korean trip and discuss the performance

document with the employee. is performance document and his

169

case studIes In teaM ManageMent

annual performance reviews provided legitimacy to his termination

and prevented any lawsuits that his termination was discriminatory.

My quality groups manager wrote a performance document for

the seasoned quality engineer. Our human resources director and

I reviewed the document. After some minor changes, my qual-

ity groups manager and our human resources director, together,

went over the performance document with the seasoned quality

engineer. I heard that even during his performance review, the

seasoned quality engineer was spiritless. He accepted all poor per-

formance claims and signed the performance review document.

In the late afternoon, our human resources director walked the

seasoned quality engineer out the door of our company.

We went through all that hoopla in order to get rid of an

underperforming seasoned engineer. My company had a layo

two weeks later. We could have gotten rid of him easily during

the layo process.

Nonperforming and/ or underperforming team members are

always an issue during the life of a project. Keeping them on the

team or getting rid of them has to be weighed very carefully. Risk

analysis of your actions has to be thought out in utmost detail. e

eects of an underperforming team member can be very destruc-

tive in a dynamic team environment.

LESSONS LEARNED FROM THIS PROJECT EVENT

It is always dicult to spark a re under lazy and under-

performing personnel.

You have to coordinate with your human resources

department and go through the required legal process

step by step if you want to terminate personnel.

It is much easier to clean up underperforming personnel

during an ocial company layo.

Case6.8: A Japanese Wedding

One of the important tasks of a project manager is to attend special

ceremonies involving your team members. ese ceremonies can be

birthday parties, weddings, patent presentation banquets, technical

society presentations, and so on. As a team leader, one of your main

functions is to participate in your team members celebration events.

One of the most memorable events in my project management

career was to attend a Japanese wedding for one of my Japanese

team members. He asked me to attend his wedding ceremony as

170

Project ManageMent case studIes

a guest of honor in Tokyo and he also asked me to give a speech

during the reception. His wedding ceremony date coincided with

my semiannual trip to Japan to check out the progress of my proj-

ect team there. I accepted his kind oer with excitement. is was

my rst experience in a Japanese wedding ceremony and recep-

tion. I was going to be the guest of honor representing our team

and our company and I was going to give a speech.

I had to research how to prepare for this honor. I had to learn

what to wear, what kind of gift to get for the couple, and what

to say during my speech. He also invited four colleagues from

our Japanese team and one colleague from our U.S. team to his

wedding ceremony and reception. I learned that the wedding cer-

emony and reception was going to be a nonreligious one taking

place in a banquet room at a very nice hotel in Tokyo. e recep-

tion party afterward was going to be in the same banquet room

and all my teams members and I were going to be seated at the

same table. I learned that we were required to wear tuxedos with

black ties. I decided to stay at the same hotel where the wedding

ceremony and reception were. I arranged for a tuxedo rental place

through the hotels concierge. e tuxedo rental places tailor came

to the hotel two days before the event and tted me with a nice

tuxedo. I investigated what the new couples needs were so that I

could get a wedding gift for them. ere was no registry process for

wedding gifts like we have in the United States. I learned from his

colleagues that a at-screen TV might be a good gift for their new

home. I went to Tokyos electronic stores district and bought a nice

42 at-screen Sony TV for them and sent it to their new home

with a congratulatory card from me, from our team members, and

from our company. Later, I discussed the wedding gift cost issue

with human resources. I was able to charge the wedding gift cost to

a human resources overhead account instead of my project.

e last thing I had to do was to prepare my speech during the

reception. I was allocated ve minutes for my speech. I was going

to be the last one to give a speech. I learned that the wedding

ceremony and reception followed a strict order of events and time

allocated for each event was xed down to the second. e entire

reception was going to take exactly two hours and ten minutes

with all the speeches, cake cutting, newlyweds rst dance as hus-

band and wife, and so on. I asked one of the engineers from our

team in Japan to help me to include several Japanese phrases into

my speech. My closing statement was also in Japanese. Anata wa

issho ni, otto to tsuma to shite, naganen, onaji makura no ue ni kenko

171

case studIes In teaM ManageMent

to kofuku ni kite taisetsu ni ari. In English it went something like

May you together, as husband and wife, cherish many years to

come in health and happiness on the same pillow. I reviewed my

speech several times and read it to the engineer who helped me

with the Japanese phrases. He said that my Japanese pronuncia-

tion was close to perfect. I was ready for the big event, which

was on a Saturday afternoon.

e wedding ceremony and the reception went like clockwork.

e bride wore a gorgeous kimono and she had heavy makeup,

a wig, and a head covering. e groom wore a standard tuxedo.

I gave my ve- minute speech very uently. At the end of my

speech, I asked everyone to raise their glasses and toast kampai

for the new couple. en the bride went to a changing room to

change from her kimono to a Western-style dress. Every guest

started to relax, eat, and drink. After dinner, the new couple cut

their colossal wedding cake and then they had their rst dance as

a couple to rock and roll music. Toward the end of the reception,

the newly wed couple went around to every table and gave every

attendee a gift for sharing their important event.

I attended similar events in Malaysia, South Korea, and in

Germany. Attending these special events takes a lot of thought

and preparation because you are representing your team and

your company.

LESSONS LEARNED FROM THIS PROJECT EVENT

As project managers, we have to give lots of thought and

attention to our team members special events.

Especially if you are attending a special event in a for-

eign country, you have to learn all the dos and donts for

that event.

Case6.9: An Engineer Wants to Return to Her Old Job

I had an interesting employee rehire case during my career. I had

a quality engineer working on my project team and reporting

to the quality engineering department manager. She was a very

dedicated and a thorough engineer. She was commuting between

her home and work 120miles every workday. We always chatted

about her commute at the beginning of our weekly meetings. We

talked about speed traps, getting trac violation tickets, trac

jams, what are the best hours to drive on the freeway, and so on. I

had a good rapport with her. She did not mind the commute and

172

Project ManageMent case studIes

I thought she enjoyed it. I valued her contributions to my team.

One day I got a call from her manager informing me that she gave

her notice that she was leaving our company in two weeks.

I was surprised at her departure announcement. I went to her

oce and expressed my disillusionment. She told me that she was

sorry to leave my team. She really enjoyed working on my team.

She said that she found a great job very close to her home at a

start-up engineering company. Her new job was a perfect t for

her and she would miss my team and also the daily commuting.

I had to scramble to nd a replacement for her in the company

to join my team. I nally got a novice engineer to replace her. He

needed a lot of monitoring and hand-holding. She and my novice

engineer were able to interface for about a week so that she could

transfer her tasks to him. I also asked her to leave all her engi-

neering books and e- mail les with me regarding my project. Her

manager and I gave her a great farewell luncheon. All of my team

members attended her luncheon.

After her departure from my company, I still kept in touch

with her. We e- mailed each other at least once a month asking

how things were going. About four months passed and I received

a telephone call from her. She told me that her new job was not

what she hoped for. She wanted to quit her job and rejoin my

company and especially my project team. I was very surprised to

hear her dismay at her new job. Apparently, there was no organi-

zational structure at the new start-up company. She had to take

care of everything on her own. Working hours were very long.

She was working on average 12 hours a day. Her boss was enforc-

ing unreasonable deadlines on her. All they did was to rush- rush

to get a prototype out to their customer so that they could guaran-

tee their next phase of funding. She wanted to return to our more

structured and employee- valued environment. I told her that our

company had a no- rehire policy, but I promised her that I was

going to try my best to get her back.

e next day, I set up a meeting with her old manager and the

human resources director. I explained to them in detail the call I

had from her. I expressed my favorable views about rehiring her.

After an hour of discussion, we came to a just solution to be able

to bring her back to our company. She was going to join my team

as a consulting quality engineer. e novice engineer would move

back to the quality department. She would contribute to my team

for the rest of my project, which had another year and a half to go.

After a year and a half, the quality department manager would

173

case studIes In teaM ManageMent

reinstate her as a senior quality engineer into his group. is way

we were not going to break the no- rehire rule of our company.

I called her immediately after our meeting and told her our

solution for rehiring her. She was ecstatic that she was coming

back to work for my company and very grateful for my help. She

accepted our proposal to work as a consultant for a year and a half

and join the quality group full time afterward. I told her that she

would get a formal call in the next day or two from the quality

department manager and the human resources director to nalize

the details of her return.

ree weeks after her pleading phone call to me, she started to

work for me. Her work ethic and contributions to my team were

of the highest standard. She was reinstated into the quality group

after 18months on a full- time basis as promised. I thought the

company gained an excellent employee by taking her back. We

did not break the no- rehire rule of our company, but we had to

bend it a little.

A work environment should be like a second family environ-

ment away from home. Every employee should be able to talk and

express his or her issues and concerns to their managers, upper

management, and/ or to human resources without any reserva-

tions or fears. ese issues and concerns can be personal ones,

work- related ones, or community- related ones. As managers, our

responsibility is to help every employee all we can to make them

feel that they are always under our companys family umbrella.

LESSONS LEARNED FROM THIS PROJECT EVENT

After leaving your job at will from a company, it will be

very unlikely for you to go back to your old job.

Job hopping is an unwritten taboo between competing

high technology companies.

As project managers, we have to help a good person in

our team all that we can when that person makes a per-

sonal mistake.

Case6.10: A Deserving Vacation

I had a long- term project to ramp up volume production for a

communication chip in Malaysia. I had a good team of engineers

in the United States supporting our eorts in Malaysia. I was

sending them back and forth from the United States to Malaysia.

We were training the Malaysian engineers. ey were taking over

174

Project ManageMent case studIes

full responsibility of their assignments after about six months of

training. One of the areas where I was having my doubts was the

wafer testing in the clean room. ere were three young, novice

electrical engineers trying to learn and take over all the testing

functions such as operator training, tester maintenance, tester

upgrading, and tester software development.

I had to send one of my senior test engineers to Malaysia the

beginning of November. I assured him that he would only stay there

for three weeks and he would be back home by anksgiving. He

was a strong family man. He had a wife and a 12- year- old son. We

put together a detailed three- week agenda for him. We discussed

and agreed on all agenda items with the Malaysian engineers.

e senior test engineers progress was going smoothly during

the rst week of his mission in Malaysia. However, when he saw

the reality of the testing environment in Malaysia, he started to

add more items to his to-do list that required extensive training.

e Malaysian engineers were struggling in the software develop-

ment phase of the testers. During our daily telephone discussions,

I asked him if he could stay another three weeks to complete his

extended tasks and skip anksgiving at home. He agreed to my

proposal. I thanked him for his dedication and I told him that I

would strongly emphasize his commitment to our company dur-

ing his annual review.

Another two weeks passed and Christmas was coming, but my

senior test engineers to-do list was growing instead of shrinking.

We again discussed what to do about his stay there. He missed

his family and he wanted to return home. I did not have anyone

else on my team and not even in the whole company with similar

extensive experience to send to Malaysia to relieve him. I had to

ask him to extend his stay until his mission was complete. I made

him a proposal for his extended stay. I told him if he extended his

stay until the end of January and completed his mission, I would

treat his wife and his son to a vacation in a place of his choice in

Southeast Asia. He was very appreciative of my vacation proposal.

He said that he would discuss my all paid vacation proposal with

his wife.

e next day during our telephone call, he informed me that

he would take my vacation proposal and spend the rst week in

February on the island of Langkawi at the northwest coast of pen-

insular Malaysia. Finally, they would get together as a family to

relax on a tropical island after three months of separation. He

and his wife enjoyed the marine life and beaches. His wife was

175

case studIes In teaM ManageMent

anxious to absorb some of the Malaysian culture. ey were also

able to take a week o for his son from his schooling. ey chose

the Langkawi Island as their vacation spot.

My senior test engineer stayed in the Malaysian plant for three

months instead of three weeks as originally planned and he com-

pleted his mission with ying colors. He missed anksgiving,

Christmas, and the New Year holidays at his home. My all

expenses paid one- week vacation proposal for him hit the spot.

at was his familys rst trip to Southeast Asia. ey had a

great time on Langkawi Island. My gesture cost my project about

$4,000, but every penny spent was worth it. He sacriced his

family and his holidays and completed his tasks in Malaysia with

exceptional professionalism.

In a project environment, during the course of events, these

kinds of unexpected sacrices could come from any one of your

team members. Sometimes these sacrices could come from peo-

ple outside of your team. As the project manager, you have to

recognize and appreciate these kinds of above and beyond duties.

A cash bonus, a gift certicate to a restaurant, a couple of tickets

to a sporting event, even a contribution to his or her choice of a

nonprot organization can go a long way.

LESSONS LEARNED FROM THIS PROJECT EVENT

If a team member has to extend his or her stay in a for-

eign country for unforeseen reasons to help your project,

you should recognize and reward his or her sacrices

accordingly.

Being away from family for a long time in a foreign

country can negatively aect your team members overall

performance.

Case6.11: Honeymoon Period

I was assigned to lead an oshore oil rig equipment design, build,

test, and installation project. e project was to last one year from

the start of design to nal installation and acceptance on-site in

the North Sea. I had a team of eight design and manufacturing

engineers. Our customer was in England. I had a two- week vaca-

tion preplanned after the third week into the project. I left the

project team in the hands of a senior engineer and left for my fam-

ily vacation. I had a heart- to- heart discussion with my replace-

ment before I left for him to check on the engineers daily and to

176

Project ManageMent case studIes

take care of their needs so that the schedule would not slip. We

had on the contract a 5% of total cost penalty for each week of late

acceptance on-site. Everyone on my team was very well aware of

our tight schedule and of the late acceptance penalty. No one had

any slack time for his or her assigned tasks.

I came back after two weeks from my vacation and got a brief-

ing from my replacement project manager regarding the status of

all current and completed tasks. I saw that we were behind about

a week to two weeks in several tasks. I went around and discussed

task- delaying reasons and the issues in detail with every engineer

on my team. I saw a relaxed atmosphere in the whole team. ey

all were behaving like they were on a honeymoon. It was sum-

mertime and excessive heat, beaches, surng, sailing, and outdoor

barbecues were giving them all a cozy feeling. My replacement

project manager did not do a good job of monitoring and putting

adequate pressure on the team members. ey all said to me we

would catch up eventually and not to worry. I heard the emer-

gency bells ringing in my head. I went to my oce to evaluate the

whole project task by task and to decide on my course of action.

e next day I called an emergency team meeting. During the

meeting, I went over every task with my team. I showed them on the

schedule that with the present pace we would be at least one week

and at most three weeks late for the acceptance of on-site comple-

tion. I emphasized that the progress we had made was not acceptable

to our customer nor to our company. I asked everyone for his or her

input as to how to catch up and not delay the project by even one day.

ere were some great suggestions from the team. I thought

the whole team woke up from a summer honeymoon dream.

ere were six critical tasks that fell behind. Six engineers that

fell behind oered to work some extra hours to catch up during

the next two weeks. At the same time, other engineers and I were

going to give them an extra hand in several minor tasks. I was

going to meet with every engineer daily for 15 minutes to discuss

the condition of his or her tasks.

e stress levels on the team members were high for the next

four weeks. We nally caught up to the critical task on the sched-

ule, which was the internal design review meeting. At the begin-

ning of the internal design review meeting, I praised all my team

members for giving extra eort in order to catch up to the sched-

ule. I invited them to a team beach barbecue with their families

on Friday afternoon. ey all accepted my invitation. We all had

177

case studIes In teaM ManageMent

a great time at the beach after roller coaster stress levels at work

for the last three months.

During the course of a project, stress levels go up and down for

every team member. A good project manager has to keep these

stress levels as normal as possible without burning out his or her

people. It is normal for the stress levels to go up before a criti-

cal design review meeting, before a regulatory agency inspection,

after an unexpected malfunction of your product, before a nal

product acceptance event, and so on. However, as the project

manager, your important task is to smooth out these stress levels

during the course of a project.

I have seen many project teams go through a honeymoon

period at the beginning or at the middle of a project. You have to

watch for the slacking signs from every team member and take the

necessary action to keep the pressure cooker at a constant stress

level. It is also a good idea for the project manager not to go on a

vacation during the course of a project that has no slack time on

its schedule and that has performance penalties in its contract.

LESSONS LEARNED FROM THIS PROJECT EVENT

A project managers replacement during his or her absence

from a project can have adverse eects on team members.

It is always dicult to shake o a honeymoon periods

relaxed atmosphere in a team environment.

As project managers, we might have to delay our vaca-

tions to after the completion of a project.

Case6.12: Farewell Luncheon

e computer company that I worked for had a chief operating

ocer whose top priority was to generate a favorable balance sheet

for Wall Street every quarter. When we could not meet our ship-

ment forecasts, he used to ship products that were in our inventory

out the door on the last day of the quarter and receive them back

as warranty return the next day. If the sales forecast for a par-

ticular quarter was down, he used to monitor all travel and extra

expenses such as luncheons and in- house birthday parties, and so

on. He tracked every penny that was spent.

During tight expenditure periods, we had to get the chief

nancial ocers approval before going on a trip or before taking

someone out to lunch or dinner at company expense. Airplane

travel was to be only in economy class. We had strict per diem

178

Project ManageMent case studIes

expense limits depending upon the place we were traveling to.

We could not take our customers or colleagues to lunch or din-

ner without prior approval. Controlling expenses and austerity

policies were good for prot and loss management, but the chief

operating ocer should have given company managers reasonable

leeway in managing their budgets.

I had a senior mechanical tool designer on my project team. He

was moving to his home state to be close to his aging parents after

15years of service to our company. He participated in several of

my projects during his last 10years with his highly professional

work ethics. My team and I wanted to give him an unforgettable

farewell party. However, we were right in the middle of a nan-

cial crunch. I had to get every expense preapproved. My team

and I decided to throw his farewell party ourselves without going

through the expense preapproval process.

I met with each of my team members and asked for their sug-

gestions. First, we decided to give a morning break chocolate cake

party around his cubicle. My secretary volunteered to bake the

cake. We were going to invite all top management people includ-

ing the chief operating ocer to the morning break party. One of

the team members suggested that we get a commemorative plaque

for all his contributions to our team. We agreed to chip in $10

each for a silver plaque.

Afterward we planned to take him out to a farewell luncheon at

his favorite Mexican restaurant and to give him several presents. I

assigned a team member to get the presents before the luncheon.

I knew that my tool designer was a skier and a golfer. We decided

to get him a pair of ski goggles and half a dozen LED lighted golf

balls. e cost for each team member was $16.

e morning break chocolate cake party was well attended.

I gave a little speech praising my tool designer and wished him

well in his new life. I asked our chief operating ocer to present

him the silver plaque. e chief operating ocer said some inspir-

ing words and did his presentation. It was a great 20-minute get-

together and the delicious chocolate cake was all gone. I thanked

my secretary on the side for her great cooking skills. I also men-

tioned to our chief operating ocer that we were paying all fare-

well party expenses from our pockets. He was very tickled to

hear that.

en my team and I took him out to lunch and had outstand-

ing Mexican food in my tool designers honor. Everyone around

the table gave spirit- lifting speeches about him. I gave him his

179

case studIes In teaM ManageMent

presents and thanked him again for his outstanding contribu-

tions to my projects. He was ecstatic about his presents. He gave

a gracious farewell speech too thanking each individual on my

team and me for coaching, mentoring, and providing assistance

all throughout his career at our company. Lunch cost for each

team member was $7. Overall we had a great farewell party for

my tool designer. e cost of the farewell party for each team

member was $33.

e company overall saved a $330 expense. We managed to

give a great farewell party to my senior mechanical tool designer

without going through the pre- approval process for expenses. All

our eorts were for a good colleague and we accomplished every-

thing without any help from the company.

LESSONS LEARNED FROM THIS PROJECT EVENT

Sometimes you have to be creative and go around strict

company rules and policies without breaking any laws.

As project managers, we have to always show our appre-

ciation for good eorts put into our team by a fellow

team member who is leaving the company under favor-

able conditions.

Case6.13: Promises to Team Members

As a project manager, my ultimate target was to gain the respect

of my team members nationally and internationally. e best way

to gain respect was to keep all my promises to team members in a

timely fashion. I learned this approach the hard way. Earlier in

my project management career I made promises that I could not

keep. ese unkept promises created conicts and disharmony in

my project teams. A simple promise to upgrade one of my team

members workstation was not fullled on time due to my com-

panys budgeting conicts. My design engineer was livid about

my not keeping my end of the bargain in a timely fashion. I had

to authorize an upgrade to his workstation instead of waiting for

the IT department to act and charged the upgrade to my project.

More conicting promises arose from things that were outside

of my control as a project manager. Examples of these uncontrol-

lable promises were salary increases, bonuses, changing depart-

ments, and extra vacation times.

I had a design engineer from our Japanese division working

for me in California. I brought him to the United States for two

180

Project ManageMent case studIes

years of extra training and for him to help me in projects dealing

with our Japanese customers. He brought his family to the United

States too. During his stay in the United States, he still reported

to his supervisor in our Japanese division. He was at engineer 2

level. Engineer 2 level was dened according to our Japanese divi-

sion standards, which was dierent from the U.S. engineer 2 level

ones. He was always complaining about his salary level to me.

Our level 2 engineers were making 20% more than what he was

making. He was a good and hard working engineer and his con-

tributions were as valuable as his U.S. counterparts. During one

of our weekly meetings, I promised him that I would discuss his

salary situation with his supervisor and request an increase in his

salary. I called his supervisor and negotiated hard with him about

increasing his salary by at least 10%. His supervisor would not

budge. His supervisor told me that this young Japanese engineer

had two more years to go at engineer 2 level. After two years

depending on his performance, he could be promoted to engineer

3 level and get a handsome bump in his salary, which would be

comparable to U.S. engineer 2 level. My hands were tied. I could

not do anything else to keep my promise. I made a promise that I

should not have. I should have called his supervisor and discussed

his salary increase before promising him anything. I called the

young Japanese engineer to my oce and explained to him my

discussions with his supervisor. I told him that I would give him

a very high recommendation for the work he was doing in the

United States for me. He could be promoted to engineer 3 level in

two years and then could achieve the salary level he was aiming

for. He understood his salary situation. He was working for me

in the United States under our Japanese divisions rules. He con-

tinued his good and hard work and he got his promotion on his

return to Japan after two years. He called me and thanked me for

my very favorable recommendation.

I had another unfullled promise early in my career. I had a

team of six engineers to design and create software for feasibility

studies of industrial investments. We tested and released the soft-

ware on time and within our budget. During our project closure

meeting, I promised my team members good year- end bonuses

for their extraordinary eorts. Our feasibility software was being

used for every new industrial project planned by our corpora-

tion. My six engineers reported to three dierent managers in

our corporation. I talked to every one of them about the success

of my team. I emphasized that our corporation was gaining a lot

181

case studIes In teaM ManageMent

by optimizing investments made to new industrial divisions by

using our feasibility software. All managers agreed to recommend

handsome year- end bonuses for my teams engineers. In January,

all year- end bonuses were announced, but none of my teams

engineers got a penny. I was very disturbed and I could not face

my teams engineers. I went to see their managers to understand

what happened. ey all gave me the same story. Due to corporate

prot crunch, year- end bonuses were given to very few people.

My engineers missed the bonus pot. I had to explain to every one

of my teams engineers what happened despite my eorts. I was

wrong in raising the hopes of my teams engineers for something

that I had no control of.

In another empty promise case, one of the engineers on my team

was not happy at all with her supervisor. She wanted to change her

department and report to another supervisor whom she thought

very highly of. I promised her that I would talk to both supervisors

and would help her to switch departments. I discussed her wish

with both supervisors and with our human resources director with

no success. e department that she wanted to move to had to

generate a new opening at her level and her capabilities. en she

had to ocially apply for this new job opening. I did not have the

authority to accomplish her desired move in any way. Her options

were to quit the company or to learn to deal with her supervi-

sor. She chose the second option. She had to endure another three

years before her supervisor was assigned to another position.

In one of my design projects, we had a very tight schedule.

Our salespeople underbid my project. My project hours were

reduced by 25%. My four engineers were putting in 12-hour days

and working Saturdays and Sundays to keep up with our proj-

ect schedule. My team was close to burnout and they were not

enjoying their jobs. ey were joking with me by saying that they

wished they were hourly employees. ey would be making at

least double their salaries if they were hourly employees. I had to

keep them energized and happy. I worked the long hours along-

side them. I promised them an extra week of vacation time after

the project was completed. I talked to their supervisor in detail.

He did not agree with my generous vacation oer. He said that

his engineers were salaried personnel and they were judged by

the quality and the quantity of their accomplishments and not

by the hours that they put in. I was dumbfounded. I did not agree

with his assessment of salaried personnel at all. I took it on myself

to correct these unfair working conditions. I gave my engineers a

182

Project ManageMent case studIes

day o during the week if they spent a weekend day at the oce.

I showed these days o as working days on my project. is way I

eased their stress levels. In the end, I overran my budget by 9%,

but it was all worth it. We were only late by a week to complete

a yearlong project. I was apologetic to my team members that I

could not give them an extra week of vacation time. ey were

all appreciative that I leveled their stress levels by a day o during

the week.

As I gained experience in project management, I only made

promises that I could keep to my team members. I researched

thoroughly beforehand whether I could keep my promise. When

I gave a time frame for a promise, I always accomplished it within

that time frame.

LESSONS LEARNED FROM THIS PROJECT EVENT

Promises not fullled in a timely fashion to team mem-

bers will create disharmony and underperformance dur-

ing the execution of your project.

Do not make a promise to a team member that is beyond

your control.

Always discuss your idea for reward with the supervi-

sor of your team member and obtain his or her consent

before announcing it.

Case6.14: A Critical Team Member Getting

Married and Going on a Honeymoon

In the middle of an oshore oil platform equipment design and

construction project, one of my critical software design engineers

decided to get married and go on a honeymoon. He came to my

oce one day right in the middle of our projects very high activ-

ity period and surprised me by saying that he was going to get

married in a month in Mexico and then go on a honeymoon to

Australia for three weeks. He was going to be o the project close

to four weeks. ese surprising events were not planned in my

project scheduling at all. He was responsible for designing and

generating the software for the control system of the equipment.

He was right in the middle of his tasks. I told him that this was

quite a change of events in the middle of our project. His absence

period coincided with the initial testing of the equipment using

his control system. I had no one capable of taking over his tasks. I

had to think and nd ways to manage his tasks during his absence.

183

case studIes In teaM ManageMent

I could not get mad at him or ask him to delay his plans. He was

one of my ace engineers. I congratulated him on his decision to

get married, but I also told him that he should have planned for

his marriage at least six months ago. I told him that I was going to

prepare a plan to take care of his responsibilities in his absence. I

told him to meet with me again the next day on the subject.

He had four more weeks of work before he left for Mexico.

His eciency was going to drop, as he got closer to his wedding

day because of intense activities for his wedding ceremony. e rst

thing I had to get him to do was to bring the control system soft-

ware to a preliminary and operable phase before he left. He had to

provide me with a preliminary version of the software. He had

to leave me with his computers password and software le loca-

tions. I was not going to ask him to release his control software

through document control in its preliminary version. He was

going to train me on the usage of his software during his last two

days in the oce. I did not want to get any other team members

distracted spending time on his software. en I was going to

ask him to give us a call every morning at 9a.m. Australian east-

ern daylight time (3p.m. Pacic daylight time) so that we could

discuss all problems and hiccups that we had encountered while

operating the equipment control system software. I did not want

to call him and disturb him on his honeymoon every time I had

an issue with his software.

I had an hour meeting with him the next day. I laid out my

proposed solutions for his absence. He agreed with me that he was

going to be able to complete a preliminary version of his software

before he left for Mexico. He was not going to be able to complete

user instructions for his software by the time he left. He agreed to

train me on the usage of his software for two days before he left.

He also agreed to call me on Skype Tuesday through Saturday

mornings ve times a week at the agreed time. He was very appre-

ciative of my understanding of his situation. He told me that one

of my projects team members was going to be a groomsman at

his wedding.

I checked his progress daily during the next four weeks. He

completed as promised a preliminary version of his software before

he left for his big day in Mexico. He trained me for two days on

all the inputs, outputs, and possible trouble areas of his software.

He called me from Australia on the agreed upon call schedule.

Some of the calls lasted ve minutes, but several of them lasted

over an hour. We tried several ways to solve software operating

184

Project ManageMent case studIes

issues while he was live on Skype. With the daily calls, we got

along okay in his absence. He completed and released his con-

trol software and its user instructions two months after his return

from Australia. My team members and I contributed handsomely

to get a great present for our newlywed colleague.

Several unexpected events like this one occur during the course

of a project. Some project managers get upset and blow their tops

o, but this type of behavior does not solve anything. Negative

reactions make things worse. You have to be coolheaded, versa-

tile, and rm to nd other solutions fast in order to bring the dif-

cult situation under control.

LESSONS LEARNED FROM THIS PROJECT EVENT

Many surprising and unscheduled events can occur dur-

ing the execution of your project.

As project managers, we have to be coolheaded, versatile,

and able to orchestrate a viable solution to keep our proj-

ect moving ahead unharmed.

Case6.15: A Project Manager Goes on a Sabbatical Leave

I was a senior scientist in a team of several engineers and designers

that were assigned to design and build prototypes of a new rotary

combustion engine in 18months. Our team leader was a dedi-

cated automotive engineer and an excellent team leader. Right at

the height of the project, he had to take a three- month sabbatical

leave to fulll his compulsory military service. He asked me if

I could lead the team during his absence. I accepted the chal-

lenge without any hesitation. I knew all the team players well.

All tasks were progressing smoothly. I did not see any problems

on the horizon. We agreed that he was going to call me twice a

week in the evenings to get a brieng about the project. He gave

me authorization to sign o on all time cards and all expenses for

the project. We had a team meeting and he explained his situation

to the team. He introduced me as the interim project manager

for the project for the next three months. e next day he left

to fulll his military service obligation.

I started to manage the team without any incidents. e rst

week passed without a glitch. e project was on track on all

cylinders. My management style was dierent from our project

manager. He liked to micromanage every team member to the

extreme. On the other hand, I gave a calculated space to team

185

case studIes In teaM ManageMent

members working under me. I gave a task to a team member and

asked for results in a given time frame depending upon the team

members experience and dedication to his or her work.

During the second week, one of the design engineers started to

slack o. His behavior was reminiscent of a mouse playing because

the cat was gone. His work eciency dropped drastically. His outside

interests increased. He started to take long lunch hours. He called in

sick on Mondays. At rst I cautioned him verbally. Nothing in his

behavior changed. He thought he could get away with it since I was

the interim project manager. I discussed his behavior with the proj-

ect manager during our bi- weekly brieng. He asked me to write a

warning letter and review the letter with the design engineer in the

presence of a human resources representative. I reviewed the written

warning with the design engineer and led it with human resources.

I started to micromanage him and tried to help him get on track and

catch up with his tasks. I did not want to take drastic measures and

re him before our project manager returned from his sabbatical

leave. Everyone else on the team was performing well. I was patient

and limped along with the design engineer for three months.

Our project engineer came back and relieved me from my team

management responsibilities. He was also very upset with the proj-

ect engineer for not completing his tasks as scheduled. Our project

manager gave him a written warning too. He was ready to re the

project engineer. I asked the project manager to give me another

week to straighten out the project engineer. I told him that the

design engineer was very knowledgeable in material science and it

would not be easy to replace him in the middle of the project. He

agreed with me. I took the project engineer out to lunch to have

a heart- to- heart discussion about his work behavior and perfor-

mance. I told him that he had to pull himself together without

any delay and had to improve his work performance or else he had

to nd another job. I emphasized to him that management was

ready to re him if he did not improve his work behavior and per-

formance fast. He started to share his personal problems with me.

He had a new girlfriend who was apparently very demanding. He

was prioritizing his new girlfriend before his work responsibilities.

Our two- hour long lunch discussion did the trick. Finally, the

gravity of his deteriorating situation at work dawned on him. He

started to work harder. He put in many extra hours to catch up

with his commitments. Our project manager thanked me for sav-

ing the design engineer from being red. at disruption would

have put a dent in the progress of our project

186

Project ManageMent case studIes

As project managers, we have to sometimes act as psycholo-

gists. We should not take drastic actions on a whim or in a burst

of anger. We have to consider all repercussions that an immediate

action might cause in our project. A colleague of mine used to

always remind me to measure twice or better three times before

you make a critical cut.

LESSONS LEARNED FROM THIS PROJECT EVENT

Diculties can arise between you and your team mem-

bers when you take over a project in the middle of its

execution.

As project managers, we have to consider all options

before we make a critical decision.

Case6.16: Technical Publishing during a Project

I always encouraged my project team members to publish their

leading-edge ndings in reputable journals as long as their publi-

cations did not disclose any intellectual property of our company

and of our customers. I also encouraged them to subscribe and to

read all technical journals in their elds so that they could stay up

to date in their elds of expertise. I asked every team member to

share his or her news about technological advances in our weekly

team meetings. As engineers we were always in a technology race.

As soon as we stopped learning and closed our eyes to the outside

world, we would fall behind in our eld and we would evaporate.

Our publications enhanced our resumes to a higher level and gave

us an insurmountable edge over our competition in promotions

and in job searches.

In my project management career, I had to provide my team

members a fair balance between time spent on writing papers and

on doing actual project work. I had a Ph.D. physicist working for

me on an advanced magnetic head design project. His knowledge

of advanced magnetics was excellent. He spent almost 50% of his

working time writing papers for dierent journals. He was also

refereeing submitted papers on several journals during working

hours. He came to work exactly at 8a.m. and left exactly at 5p.m.,

not a minute later. He copublished most of his papers with other

contributors from my project team. If he did not copublish, he

acknowledged all the contributors in his papers. He was a well-

respected scientist in his eld. I valued his achievements but I had

187

case studIes In teaM ManageMent

to get more out of him on my projects side and reduce his com-

mitments to publishing during working hours.

I went to his oce and had a heart- to- heart discussion about

his excess commitment to publication during working hours. I

told him that it was okay with me if he spent 10% to 15% of his

working hours on publication- related issues. I reminded him that

his project tasks in advanced magnetic head design were falling

behind. He told me that he was always in a race with other scien-

tists to publish a new idea. He wanted to be the rst one to publish

a new idea in the scientic world. He also had to get approval

from our patent lawyers before submitting his papers. He believed

that it was always desirable to have our companys name rst in

leading journals.

I agreed with all his comments and left his oce without a res-

olution regarding his time spent on writing and refereeing papers.

I had to think hard not to antagonize him and get a fair resolution

to our problem. I did not want to go to his boss and complain

about the situation at hand. I had to deal with him myself and

nd a fair solution. I thought about a middle-ground solution for

a couple of days. en I called him to my oce in order to propose

and negotiate my solution. I told him that he could spend all the

time he wanted on publishing and refereeing papers as long as

he put in an honest 32 hours of work on my project every week.

I gave him freedom in 20% of his weekly working hours to do

whatever he wanted to do in publishing. If he wanted to spend

more time in publishing, he had to do it after 5p.m. at work or

at home. He could not argue with my proposal. He told me that

I was trying to put brakes on his publishing eorts. I emphasized

that my projects tasks were more important than his publishing

eorts. I reminded him that our company could only survive, if

we were the leader in our products, not in publishing. Finally, he

came around and reluctantly accepted my proposal. I told him that

in dire situations such as a deadline, he could spend more work

time for publishing as long as he notied me. is ne loophole

gave him more condence in our relationship. Finally, he started

to spend 32 hours per week on my projects tasks.

Specialists and/ or scientists can be very moody and demand-

ing in a team environment. As a project manager, you need their

expertise. You have to treat them with respect. You have to cre-

ate a exible boundary with their needs and with your projects

requirements. If you become a hard- liner with such people, your

project will suer in the end.

188

Project ManageMent case studIes

LESSONS LEARNED FROM THIS PROJECT EVENT

Getting a team member to focus on your projects tasks

can be challenging when that team member has a lot of

other interests besides your project.

Your exibility in solving a dicult case regarding a

team member will benet your project in the long run.

Case6.17: Team Atmosphere after Vacations and Holidays

As global project managers we have to know every team members

vacation plans in advance. We have to know all national holi-

days of the countries we are dealing with. We have to know all

religious holidays that each one of our team members and coun-

tries are observing. Religious holiday observance days might get

very confusing, if you are dealing with multi- ethnic countries like

India and Malaysia. It is always a must to include all these events

into your project schedule at the initial stage of your planning.

You might come across many surprises that can aect your proj-

ects critical tasks and deliverables.

In one of my project teams, I had a novice engineer who could

not get into a work mood easily after he came back from holidays.

He was still dreaming about turkey dinners, apple pies and ice

cream, a Christmas gift he got, and New Years celebrations. He

was going around discussing his experiences during the holidays

in detail with child- like excitement with his colleagues. I had to

micromanage him daily after the holidays so that he could get

back to his work and start focusing on his tasks. After a couple

of holidays, he started to act more professionally and discussed

his holiday experiences with his teammates only during breaks.

is novice engineer took his two- week vacation after a year

of employment and went to Tahiti with his girlfriend. After he

got back he acted like a lost soul under lots of stress. He could not

switch easily from a relaxed atmosphere to the rhythm of orga-

nized work. His e- mails and his phone messages accumulated

quite a bit during his two weeks of absence. He did not know

which task to tackle rst. He came to my oce and asked for my

help. I told him to rst review all his e- mails and phone messages

and jot down important ones and ones that needed action and

response from him. en I asked him to come back to my oce

with his list the same day. He came back and we together reviewed

his action items list and prioritized every item on it. We also put

completion dates for each action item. is kind of personalized

help showed my novice engineer how to deal with numerous action

189

case studIes In teaM ManageMent

items on his to- do list after a relaxing vacation. He appreciated my

guidance and thanked me a lot for easing his stress level. He went

on to become a very organized and productive engineer in two

years. After two years, I recommended him to be promoted to an

engineer 2 level. He received his promotion. He was very grateful

to me and he always wanted to work on my projects.

In an opposite case, an engineer from our Malaysian facil-

ity was working on my project in California. I brought him to

California for a six- month period to help me in several tasks in my

volume production ramp- up project and to be trained in certain

inspection methods. One day he came to my oce and asked if I

could send him back to Malaysia for a week to see his family dur-

ing a religious holiday that was coming up in 10days. His request

came to me by surprise at a very high activity phase of our project.

I told him that it would put a big dent in the progress of our project

if he were gone for a week. I could not outright reject his request. I

had to do all I could to nd a way to send him home for a week to

spend his important religious holiday with his family. I told him

that I would try to bring in another engineer to ll in for him for

a week. I also told him that I could not pay for his trip expenses

from my projects budget. I promised him a response in a day.

I discussed my Malaysian engineers holiday request and my

projects dire need for backup engineering manpower for a week

with our quality engineering manager and got one of his engineers

to help me. I immediately gave the good news to my Malaysian

engineer that he could leave our team for a week. Somehow he

found a cheap round trip ticket in a short time and went home for

his religious holiday. After he got back, he worked very hard and

long hours on my project team to pay me back his gratitude.

Unexpected vacation and holiday requests from team members

can occur during the course of a global project. Vacations and

holidays tend to bring instability to the progress and atmosphere

of a project. As project managers, we have to deal with them in a

timely fashion and try to smooth out their ripple eects.

LESSONS LEARNED FROM THIS PROJECT EVENT

It takes awhile and your continual guidance to get some

of your team members into an eective working mood

after holidays and vacations.

Unexpected vacation or holiday requests can come from

your team members. You have to deal with these requests

in a positive manner.

190

Project ManageMent case studIes

Case6.18: Project Team Members Maternity Leave

Maternity leave can hit your project team any time. You have to

restructure your team and get new personnel reinforcements in a

timely fashion in order not to aect the progress of your project.

In a new wafer factory setup project, I had a very talented female

engineer on my team. She was very experienced in experimental

design and in industrial statistics. She was designing all qualica-

tion experiments for new equipment along with equipment engi-

neers who were cognizant of wafer processes and then analyzing

resulting data with them. She came to my oce one day and told

me that she was four months pregnant. She had already talked

with our human resources group. She was very excited about her

rst child. She was planning to take o a week before her due

date, which was predicted by her doctor, and she was going to

take a total of 12weeks for maternity leave. She was going to have

her full salary and her full health benets during her maternity

leave. She was also going to have full job protection. She wanted

to come back and continue to work on my team after her mater-

nity leave was over. She also would not be able to y after her

sixth month of pregnancy, which was going to be in two months.

I congratulated her and wished her a healthy pregnancy. I asked

her to think about how to replace her temporarily for 12weeks. I

asked her to get together with me on the subject in a week.

I considered my options too during the week. I analyzed all her

upcoming tasks. Her maternity leave was occurring right in the

thick of things in my project. I had to nd a reliable replacement

for her fast so that the two of them could spend a month together

before she went on her leave. She came to my oce the following

week to discuss her temporary replacement. We could not agree

on an internal replacement. No one in our company had the broad

and in- depth experimental design skills that she possessed. We

decided to go outside to a consulting rm. is consulting rm

had given her lots of training in the past. We called the consult-

ing rm and set up a face- to- face meeting. We agreed on a senior

consultant to come and help us during her maternity leave. is

senior consultant was at one time her training instructor. He was

very expensive, but he was the right person for the job. He agreed

to start a month before her maternity leave for a phase- in period

for her tasks. I asked my purchasing department to put together

a contract with the consulting rm. We had to cover his travel,

191

case studIes In teaM ManageMent

lodging, and meal expenses too. e senior consultants expenses

were going to put a huge dent into my projects cost performance.

I went to my upper management and negotiated to charge to my

project only the amount equal to my engineers salary. e rest of

the consultants expenses were to be absorbed into the company

overhead. at was the just way of splitting the consultants cost

to my project.

e consultant started to work on my team along with her a

month before her maternity leave. e phase- in and phase- out

process was smooth. She gave birth to a healthy boy on the day

predicted by her doctor. My team and I sent her hospital con-

gratulatory owers. I talked with her on the phone and discussed

her and the babys health. Everyone was doing great.

Two months passed after her birth, I got a phone call from

our human resources group informing me that she wanted to take

o another six weeks after her maternity leave was over for baby

bonding. She was going to have 50% of her salary, her full health

benets, and her full job protection during this baby bonding

period. is was quite a shock to me. She did not even call me

to discuss her decision to extend her maternity leave. My human

resources director told me that she had the right for this baby

bonding leave under California law.

I discussed the six- week baby bonding extension with the senior

consultant. He said he could not extend his contract because he

already had other commitments. He had three more weeks left on

his contract with us. During these six weeks, all her tasks were

on the critical path of my project. I had to scramble again to nd

a replacement for her for another six weeks. I decided to groom a

willing engineer internally for my team. Internal grooming was

also benecial for my company in the long run. I discussed the

issue with all engineering departments heads. Two names came

up as possible candidates. I interviewed both engineers. I decided

to give a novice and ambitious mechanical engineer a try. He

spent three weeks next to the senior consultant. I called my female

engineer at home to discuss the bind I was in. She oered to help

my new engineer on the phone from home. We limped through

six weeks of her baby bonding period. Finally, my female engineer

returned to her tasks after 18weeks. During this chaotic period

in my project, my company gained another bright engineer who

went on to become an expert in experimental design and in indus-

trial statistics.

192

Project ManageMent case studIes

LESSONS LEARNED FROM THIS PROJECT EVENT

When a maternity leave request comes to you, always

bring your human resources department into the picture

to learn all federal, state, and company rules, regulations,

and options.

You have to be ready for surprises during a maternity

leave so that your project does not suer.

Case6.19: Shelf Life of Photoresists in Wafer Fabrication

In wafer fabrication of magnetic heads the photoresist played a

very important role. As the photoresist aged, its sensitivity to light

exposure and its light absorption characteristics changed. is

variability in turn aected our products steep wall proles. Our

product lost wall edge acuity. erefore, all of a sudden lots of

wafer scraps started to occur. is phenomenon occurred inter-

mittently in our wafer fabrication when I was heading the engi-

neering group. I had several meetings with my photolithography

engineers. We could not determine the cause of the degrading

edge acuity phenomenon. We did lots of design of experiments,

but we could not pin the yield drop to the age of the photoresist

used in the factory.

One of my quality engineers in wafer fabrication suggested

my team perform an experiment with the age of photoresist

versus steep wall edge acuity. Everyone on the team agreed to

these experiments. I assigned the quality engineer who suggested

the experiment along with a photolithography engineer to per-

form the required tests in two weeks. ey ran experiments with

one-, two-, three-, four-, ve-, and six- month- old photoresists.

ey found out that steep wall edge acuity in our products started

to degrade when the photoresist was older than three months.

ey also ran conrmation experiments to verify these results.

I immediately issued a memorandum to all shifts in wafer

fabrication not to use any photoresists that were older than three

months. We had another problem with the photoresist contain-

ers. e manufacturing date of the photoresist was indicated on

a sticker by the manufacturer, but this sticker very often fell o

the container. So we sometimes had no idea when the photo resist

was manufactured. I called the photoresist manufacturer with

our receiving inspection and purchasing managers. We asked

them to put permanent laser markings on every photoresist con-

tainer identifying the lot number and the manufacturing date.

193

case studIes In teaM ManageMent

e photoresist manufacturer agreed to our container markings

request. Two weeks after our telephone discussion, we started

receiving photoresist containers that were permanently marked

with the lot number and the manufacturing date.

e photoresist usage expiration date had to be on every con-

tainer. I discussed this issue with our stockroom manager. We

decided to laser scribe usage expiration dates on the body of the

container in large fonts. We kept the photoresist in special stor-

age rooms with temperature, 5C to 10C, and relative humidity,

30% to 50%, control. Upon my request, all stockroom personnel

were instructed by their manager not to issue to production any

photoresist containers that were over the usage expiration date.

ey were also instructed to dispose of any containers that were

over the usage expiration date.

With all the steps taken to control the useful life of the photo-

resist, our products steep wall edge acuity became very stable.

We did not have any intermittent out- of- specication wall pro-

les. Our wafer scraps due to out- of- specication wall proles

decreased tremendously.

We spent months to nd the cause for our steep wall pro-

le defects. We performed numerous full factorial design- of-

experiments with two or three factors and each factor having two

or three levels. None of these complicated, time- consuming, and

expensive experiments provided us with any reliable solution.

e photoresist useful life eects on steep wall prole were

not even suggested by one of my photolithography engineers. e

suggestion came from one of my quality engineers. She was not at

all involved with our photolithography processes. She was a qual-

ity engineer in our plate and etch group. During our weekly engi-

neering team meeting, I praised her for suggesting the solution to

one of our mind- boggling problems. I also gave her a handsome

bonus during our annual review. I patiently learned to listen and

evaluate all suggestions that were proposed during our engineer-

ing team meetings. Being a good listener provided my team mem-

bers with upbeat empowerment and helped us nd solutions to

dicult issues in our wafer fabrication.

LESSONS LEARNED FROM THIS PROJECT EVENT

A good solution to a nagging engineering issue can come

from unexpected sources.

As project managers, listening and evaluating everyones

input to a problem increases our chances of success.

194

Project ManageMent case studIes

Case6.20: Excessive Meetings

I was leading a project with a U.S. and overseas team in Malaysia

to set up a manufacturing plant there. My U.S. team consisted of

12 engineers split equally into design, manufacturing, test, and

quality subteams. I had 12 Malaysian engineers based in Penang

as counterparts of my U.S. team. We had weekly teleconferences

to bring everyone on the team up to date regarding the tasks that

everyone was working on. It took us two hours every Monday

afternoon (Tuesday morning in Malaysia) to go over all the tasks.

It gave every engineer about ve minutes on average to present the

status of his or her task responsibilities.

We were spending 48 man- hours a week on this teleconfer-

ence meeting. Everyone was waiting for his or her turn. Some

engineers were twiddling their thumbs during the presentations

that they had no interest in. Some engineers were busy with their

laptops. Some Malaysian engineers were not at the meeting when

their turn came up. ere was a lot of wasted time during these

teleconference meetings. It was an inecient way to manage a

meeting. I decided to take some action to correct the situation.

I talked with my dierent subteams in the United States and in

Malaysia about improving the weekly teleconference meeting. We

brainstormed several ideas to improve the eciency of our weekly

status meeting. e best idea came from an engineer in Malaysia.

She proposed that we break up the meeting into four half- hour

segments, namely design, manufacturing, test, and quality seg-

ments. During the design segment, only the design engineers

would attend the meeting. During the manufacturing segment,

only the manufacturing engineers would attend the meeting.

During the test segment, only the test engineers would attend the

meeting. During the quality segment, only the quality engineers

would attend the meeting. If there were any issues crossing the

subteam groups, I would record them as action items in the meet-

ing minutes and a particular issue would be handled by e- mail

or by telephone by its action item owner. If any one of the team

members were interested in a certain task in a dierent subteam,

he or she could review the released meeting minutes from docu-

ment control.

I issued the new weekly teleconference meeting process. From

4 p.m. to 4:30p.m. (U.S. Pacic time zone), it was the design task

groups turn, from 4:30 p.m. to 5p.m., it was the manufacturing

task groups turn, from 5 p.m. to 5:30p.m., it was the test groups

195

case studIes In teaM ManageMent

turn, and from 5:30 p.m. to 6p.m. it was the quality groups turn.

I also rotated the groups turns every two months so that one task

group did not get stuck with the late afternoon meeting time in

the United States or the early morning meeting time in Malaysia.

I also had a monthly half- hour general project status teleconfer-

ence meeting for all team members, domestic and international.

is new communication setup worked very well all through-

out the project for two years and we saved about 75% man- hours

that were being wasted during the weekly status meetings. On top

of that, engineers were not bored during the meeting. ey came

into the meeting room, gave their presentation, and left the meet-

ing room in half an hour. Sometimes there were shifts in presen-

tation timing. If a subteams presentation ran over half an hour,

I informed the other subteams about the delay and they showed

up at the new modied presentation time in the conference room.

My counterpart in Malaysia did the same thing.

Meetings are the backbone of a project. ey have to be stan-

dardized and managed properly so that a precious team members

time is not wasted; the team member is not bored, and he or she

contributes constructively during his or her presence in the meet-

ing. Especially in large team groups, as it was in this case, break-

ing up a meeting into smaller subgroups can be very eective.

LESSONS LEARNED FROM THIS PROJECT EVENT

Project meetings can accumulate lots of wasted team

members time.

Plan ecient project meetings and make sure that your

team members around the world are not twiddling their

thumbs and they do not look bored during a meeting.

Case6.21: First Article Mishap

I was heading the project of designing, manufacturing, and test-

ing a new generation of battery- powered electric buses. Forty- foot

long electric buses provided four and a half hours of stop- and- go

level terrain travel on a single charge fully loaded with 80 pas-

sengers. e electric buses were for a mall shuttle operation. My

team was getting ready for the rst article acceptance meeting

that was scheduled to start on a Monday and was supposed to

last for three days. On Friday morning before the start of the rst

article acceptance meeting, my manufacturing manager brought

196

Project ManageMent case studIes

the rst article bus to the charge station in our plant to charge

its batteries. e charging operation took about eight hours. We

were running around like our heads were cut o to complete last

minute nishing touches and tasks for the Monday meeting. We

were all tired and were looking forward to a restful weekend

before the big Monday presentation. All my team members and

I had been working 70-hour weeks for the last month to prepare

the rst article for this crucial acceptance meeting.

At 4p.m. on Friday, I unplugged the battery charger eagerly

and started to drive the bus to its presentation spot. ere was a

short steel post in front of the charge station hidden behind the

bus. While backing the bus out of the charge station, I ran the rear

side of the bus into the steel post. One of the side rear windows

broke and there was minor bodily damage too. It was my mistake

to rush to drive the bus to its presentation spot. I knew where the

steel post was and I thought I was clearing it during my maneuver.

I was so mad at myself for rushing and causing this damage to the

bus right before the rst article acceptance meeting.

I immediately called a meeting with our manufacturing

manager and our body shop personnel. e meeting was held

at the damaged rear of the rst article bus. I told my team that

I was devastated by my mistake and I asked them if the dam-

age was xable by Monday. We all assessed the damage and

agreed that the damage was xable before Mondays meeting.

We decided that three body shop technicians would be needed

to x the damage during the weekend. I asked my team who

would volunteer for the weekend overtime repair task. ree out

of six technicians volunteered immediately. I told them that I

would be at the plant too along with them during the week-

end and bring breakfast and lunch for them. My gesture was

received very favorably. We were able to replace the broken win-

dow easily with another one. e body damage took most of the

repair time. e body damage was repaired by straightening the

surface sheet metal and then painting over it during Saturday

and Sunday.

e rst article electric bus was ready for the acceptance meet-

ing at 9a.m. Monday morning. e fresh paint at the rear of the

bus was not even dry. I was afraid to drive the bus to the presen-

tation site. I let my manufacturing manager do the honors. For

three days, the rst article acceptance meeting went well. Our

new generation of battery electric bus got excellent grades from

197

case studIes In teaM ManageMent

our customers representatives. ey accepted our battery electric

bus with minor modications.

I told our customers representatives of what happened on

Friday. ey were amazed that we were able to work all weekend

to get the bus xed and ready in top shape. Our customer was very

appreciative of our performance. After the last meeting, they took

my whole team of 20 people out to dinner.

ese kinds of mishaps happen more often than not while pre-

paring for critical meetings or deadlines in a project. Overworked

and overtired team members become prone to mistakes and acci-

dents. As a project manager, I had to watch myself and my team

members for fatigue and for burnout conditions. We had to slow

down and take a break from running a 100miles an hour. One

solution would have been to delay Mondays rst article meeting

for a couple of days.

LESSONS LEARNED FROM THIS PROJECT EVENT

You have to control your pace and fatigue level and your

team members pace and fatigue level when you are pre-

paring for a crucial event for your project.

It might be wiser to postpone a crucial project event than

to burn out yourself and your team members preparing

for it.

  • Uploaded By : Pooja Dhaka
  • Posted on : November 21st, 2024
  • Downloads : 0
  • Views : 150

Download Solution Now

Can't find what you're looking for?

Whatsapp Tap to ChatGet instant assistance

Choose a Plan

Premium

80 USD
  • All in Gold, plus:
  • 30-minute live one-to-one session with an expert
    • Understanding Marking Rubric
    • Understanding task requirements
    • Structuring & Formatting
    • Referencing & Citing
Most
Popular

Gold

30 50 USD
  • Get the Full Used Solution
    (Solution is already submitted and 100% plagiarised.
    Can only be used for reference purposes)
Save 33%

Silver

20 USD
  • Journals
  • Peer-Reviewed Articles
  • Books
  • Various other Data Sources – ProQuest, Informit, Scopus, Academic Search Complete, EBSCO, Exerpta Medica Database, and more