diff_months: 11

DIPLOMA OF PROJECT MANAGEMENT BSBPMG522

Flat 50% Off Order New Solution
Added on: 2024-11-26 19:30:20
Order Code:
Question Task Id: 486782

DIPLOMA OF PROJECT MANAGEMENT

contents

Change Request Template. 3

Components of Project Governance Checklist. 5

Contract Inclusions Checklist. 9

Contract Management Plan Checklist. 10

Contract Review Checklist. 11

GROW Discussion Template. 12

Issues Log Template. 13

Knowledge Management Plan. 14

Lessons Learned Checklist. 15

Meeting Minutes Template. 19

Milestone Report Template. 20

Project Schedule Template. 21

Project Budget Template. 22

Project Charter Template. 23

Project Communications Plan. 24

Project Management Capability Reflection Template. 25

Project Documentation Checklist 27

Project Governance Plan. 28

Project Review and Closure Report Template. 29

Project Risk Register Template. 31

Project Scope Document Template. 32

Project Scope Management Plan. 33

Quality Assurance Log Template. 34

Quality Control Log Template. 35

Responsibility Allocation Matrix Template. 36

Scope Considerations Template. 37

SMART Objectives Template. 38

Stakeholder Analysis Template. 39

Stakeholder Classification Matrix. 40

Supplier Evaluation Criteria Template. 41

Writing Project Documentation Checklist 42

Additional Web-based Template Examples. 43

Change Request Template

Document Control


Date


Version


Status


Action


Responsibility







Change request


Request no.:


Project:


Project no.:


Proposed by:


Date received:


Description:


Reasons:


Benefits (quantify):


Impact:



Time estimate



Cost estimate



Quality



Contractors



Suppliers



Attachments (reference documents, impact details):


Date Required by:


Date Requested by:


Date Completed by:


Comments:



Reviewed by:


Position: Date:



Approved by:


Position: Date:



Accepted and implemented by:


Position:



Date:


Records of action to be completed:




Project objectives changed



Client agreement varied



Project quality plan amended



Project plan changed



Documentation revised


Stakeholders to be advised:



Components of Project Governance Checklist


Portfolio direction


This component seeks to ensure that all projects are identified within the one portfolio. This portfolio should be evaluated and directed, mindful of the organisations aims and constraints.



Yes


No


Is the organisations project portfolio aligned with its key business objectives, including those of profitability, customer service, reputation, sustainability and growth?




Are the organisations financial controls, financial planning and expenditure review processes applied to both individual projects and the portfolio as a whole?




Is the project portfolio prioritised, refreshed, maintained and pruned in such a way that the mix of projects continues to support strategy and take account of external factors?




Does the organisation discriminate correctly between activities that should be managed as projects and other activities that should be managed as non-project operations?




Does the organisation assess and address the risks associated with the project portfolio, including the risk of corporate failure?




Is the project portfolio consistent with the organisations capacity?




Does the organisations engagement with project suppliers encourage a sustainable portfolio by ensuring their early involvement and by a shared understanding of the risks and rewards?




Does the organisations engagement with its customers encourage a sustainable portfolio?




Does the organisations engagement with the sources of finance for its projects encourage a sustainable portfolio?




Has the organisation assured itself that the impact of implementing its project portfolio is acceptable to its ongoing operations?



Reflect on your own contribution to these components:



Project sponsorship


This component seeks to ensure that project sponsorship is the effective link between the organisations senior executive body and the management of the project. The sponsoring role has decision-making, directing and representational accountabilities.



Yes


No


Do all major projects have competent sponsors at all times?




Do sponsors devote enough time to the project?




Do project sponsors hold regular meetings with project managers, and are they sufficiently aware of the project status?




Do project sponsors provide clear and timely directions and decisions?




Do project sponsors ensure that project managers have access to sufficient resources with the right skills to deliver projects?




Are projects closed at the appropriate time?




Is independent advice used for appraisal of projects?




Are sponsors accountable for and do they own and maintain the business case?




Are sponsors accountable for the realisation of benefits?




Do sponsors adequately represent the project throughout the organisation?




Are the interests of key project stakeholders, including suppliers, regulators and providers of finance, aligned with project success?



Reflect on your own contribution to these components:



Project management effectiveness and efficiency


This component seeks to ensure that the teams responsible for projects are capable of achieving the objectives that are defined at project approval points. The teams capability is driven by skill and experience of project leaders, resources available and the tools and process deployed. Delegation should also allow for decisions consistent with the organisations system.




Yes


No


Do all projects have clear critical success criteria and are they used to inform decision- making?




Is the board assured that the organisations project management processes and project management tools are appropriate for the projects that it sponsors?




Is the board assured that the people responsible for project delivery, especially the project managers, are clearly mandated, sufficiently competent, and have the capacity to achieve satisfactory project outcomes?




Are project managers encouraged to develop opportunities for improving project outcomes?




Is key governance of project management roles and responsibilities clear and in place?




Are service departments and suppliers able and willing to provide key resources tailored to the varying needs of different projects and to provide an efficient and responsive service?




Are appropriate issue, change and risk management practices implemented in line with adopted policies?




Is authority delegated to the right levels, balancing efficiency and control?




Are project contingencies estimated and controlled in accordance with delegated powers?



Reflect on your own contribution to these components:



Disclosure and reporting


This component seeks to ensure that the content of project reports will provide timely, relevant and reliable information that supports the organisations decision- making processes, without fostering a culture of micro-management. It is important for the organisation to distinguish between key drivers of success and key indicators of success. An effective reporting process will therefore include measures of both.



Yes


No


Do all projects have clear critical success criteria and are they used to inform decision- making?




Does the board receive timely, relevant and reliable information of project progress?




Does the board have sufficient information on significant project-related risks and their management?




Are there threshold criteria that are used to escalate significant issues, risks and opportunities through the organisation to the board?




Does the organisation use measures for both key success drivers and key success indicators?




Is the organisation able to distinguish between project forecasts based on targets, commitments and expected outcomes?




Does the board seek independent verification of reported project and portfolio information as appropriate?




Does the business culture encourage open and honest reporting?




Where responsibility for disclosure and reporting is delegated or duplicated, does the board ensure that the quality of information that it receives is not compromised?




Is a policy supportive of whistleblowers effective in the management of projects?




Do project processes reduce reporting requirements to the minimum necessary?



Reflect on your own contribution to these components:


Contract Inclusions Checklist


Contract inclusions checklist



Full party detailsif company, ACN/ABN and registered business address



Definition of basic terms



Date of acceptance



The deliverables, such as equipment, services, service levels, people (often an annexure to the contract, such as a schedule or statement of work)



Price to be paid, with a schedule of when and how progress payments are to be made



Any other fees or charges



Term of the contract



Performance levels and other warranties



Reporting and monitoring requirements



Quality and audit requirements



Intellectual property assignment, ownership, and transference details



Subcontracting acceptance or rejection, as appropriate



Risk indemnification and management



Variation and change control processes



Exclusions and limitations



Force majeure provisions (an act of god, such as a major storm, earthquake)



Regulatory, legislative and organisational requirements, such as workplace health and safety standards, public sector standards, Australian Standards, and matters relating to probity, financial management, approvals, compliance and due diligence



Disputation and resolution process



Start-up or transition arrangements



Termination provisions, including liabilities and claims



Terms and conditions to remain enforceable at the end of the contract period (such as warranty and defect periods)


Contract Management Plan Checklist


Contract Management Plan



Roles and responsibilities of key parties



Key or critical phases of the contract



A summary of milestones (key performance indicators) and deliverables



Communications strategy or stakeholder management plan



Lines of communication with contractors, for example, meeting schedules and reporting requirements



Risk response strategy



Confidentiality provisions (where appropriate)



Audit procedure



Contract review strategy (to review management of the contract, contractor performance, user satisfaction and audit results)



Variations and amendments



Dispute resolution



Payment and invoice processing



Expected standards of behaviour, e.g. corporate social responsibility and ethical behaviour



Scheduling requirements



Resourcing requirements



Key skill requirements



Control and monitoring provisions


Contract Review Checklist


Contract Management Plan



Roles and responsibilities of key parties



Key or critical phases of the contract



A summary of milestones (key performance indicators) and deliverables



Communications strategy or stakeholder management plan



Lines of communication with contractors, for example, meeting schedules and reporting requirements



Risk response strategy



Confidentiality provisions (where appropriate)



Audit procedure



Contract review strategy (to review management of the contract, contractor performance, user satisfaction and audit results)



Variations and amendments



Dispute resolution



Payment and invoice processing



Expected standards of behaviour, e.g. corporate social responsibility and ethical behaviour



Scheduling requirements



Resourcing requirements



Key skill requirements



Control and monitoring provisions


GROW Discussion Template


Goal


Set the goal for the session


What do you want to get out of todays session?


What will we focus on today?


Is this a SMART goal?



Reality


Use questioning skills to raise awareness


What is working for you now?


What is happening now?




Options


Help shift perspective towards actions and solutions


What are you doing already thats working?


Magic question differences between now and ideal outcome




Wrap up


Gain commitment to action steps


What are the next steps to take?




Actions Steps



Issues Log Template

Document Control


Date


Version


Status


Action


Responsibility







Issue #


Date


Source


Description


Priority


Status







































































































Knowledge Management Plan

The Knowledge Management Plan is created during the projects Planning Process Phase and is considered a component of the Project Management Plan (PMP). The purpose of the Knowledge Management Plan is to document the collection, processing, storage and distribution of information as it relates to the project.

A comprehensive Knowledge Management Plan template is available in your downloadable Project Management Templates

Lessons Learned Checklist



Lesson Learned





Yes





No





N/A


Impact


Low High


1


2


3


4


5


Project Planning


1.


Business Objectives were specific, measurable, attainable, results-focused and time-limited










2.


Product concept was appropriate to Business Objectives










3.


Project Plan and Schedule were well-documented, with appropriate structure and detail










4.


Project Schedule encompassed all aspects of the project










5.


Tasks were defined adequately










6.


Stakeholders (e.g., Sponsor, Customer) had appropriate input into the project planning process










7.


Requirements were gathered to sufficient detail










8.


Requirements were documented clearly










9.


Specifications were clear and well-documented










10.


Test Plan was adequate, understandable, and well- documented










11.


External dependencies were identified, agreements signed










12.


Project budget was well defined










13.


End of Phase Criteria were clear for all project phases










14.


Project Plan had buy-in from the stakeholders










15.


Stakeholders had easy access to Project Plan and Schedule










Project Execution and Delivery


16.


Project stuck to its original goals










17.


Changes in direction that did occur were of manageable frequency and magnitude










18.


Project baselines (Scope, Time, Cost, Quality) were well- managed (e.g., changed through a formal Change Control Process)










19.


Design changes were well-controlled










20.


Basic project management processes (e.g., Risk Management, Issue Management) were adequate










21.


Project tracked progress against baselines and reported accurate status










22.


Procurement (e.g., RFP, Contract with vendor) went smoothly










23.


Contracted vendor provided acceptable deliverables of appropriate quality, on time, and within budget










24.


Stakeholders were satisfied with the information they received










25.


The project had adequate Quality Control










26.


Requirements specifications Test Plan were well- managed (e.g., Requirements Management System was used)










27.


Risks were manageable











Lesson Learned





Yes





No





N/A


Impact


Low High


1


2


3


4


5


Human Factors


28.


Project Manager reported to the appropriate part of the organisation










29.


Project Manager was effective










30.


Project Manager was not a contracted resource










31.


Project Team was properly organised and staffed










32.


Project Manager and staff received adequate training










33.


Project Teams talent and experience were adequate










34.


Project team worked effectively on project goals










35.


Project team worked effectively with outside entities










36.


There was good communication within the Project Team










37.


Management gave this project adequate attention and time










38.


Resources were not over-committed










39.


Resources were consistently committed to project aims










40.


Functional areas cooperated well










41.


Conflicting departmental goals did not cause problems










42.


Authority and accountability were well defined and public










Overall


43.


Initial cost and schedule estimates were accurate










44.


Product was delivered within amended schedule










45.


Product was delivered within amended budget










46.


Overall Change Control was effective










47.


External dependencies were understood and well-managed










48.


Technology chosen was appropriate










49.


The project was a technological success










50.


Customers needs/requirements were met










51.


Customer was satisfied with the product










52.


Project Objectives were met










53.


Business Objectives were met









Meeting Minutes Template


Date


Time


Venue


Attended by:








Project Name



Meeting objective




Action item review


Actions from previous meeting


status


Assigned to

















Schedule review


Status of project schedule. Risks identified which affect the schedule. High level list of work completed and plan for next two weeks.


Risk management


Provide a status update for each identified project risk.



New action items


New actions


Date due


Assigned to
















Milestone Report Template


Milestone


Date


Status


Responsibility


Issues/Comments



























Wrap up


Gain commitment to action steps


What are the next steps to take?








Actions Steps







Project Schedule Template

Document Control


Date


Version


Status


Action


Responsibility







Project:


Period (Day, Week, Month)


1


2


3


4


5


6


7


8


9


10


11


12


13


14


15


16


17


18


19


20


Stage / Activity


Tasks





































































































































































































Project Budget Template

Document Control




















Date


Version


Status


Action


Responsibility

























































Expenditure


Item


Cost


Notes











Income


Item


Cost


Notes










Project Charter Template

Document Control




















Date


Version


Status


Action


Responsibility







Project Name



Purpose / Context



Description



Objectives



Deliverables



Summary milestones



Indicative budget



Project Manager



Approved by


Project Communications Plan

Document Control


Date


Version


Status


Action


Responsibility






Stakeholder


Specific Interests/ Needs


Requirements


Frequency


Medium




















































































































Project Management Capability Reflection Template

Record your strengths and needs for the following areas of Project Management:


Knowledge area


Strengths


Needs


Integration





Scope






Time





Cost





Quality





Human resources





Communications





Stakeholders





Risk





Procurement




Identify two ways you can utilise your strengths in your current or an upcoming project.




In consultation with your manager, decide on three ways to address your development opportunities.




Project Documentation Checklist


Project documentation checklist



Official correspondence, including email correspondence



Key or critical phases of the contract



Stakeholder contact details



Project brief/proposal/approval



Change or variance requests/decisions made



Issues/risk log and mitigation strategies



Status reports



Procurement documents



Instructions, direction, advice issued, and file notes



Handover documents



Project diary (where applicable)



Contracts with any external organisations



If using software program to manage your project, a copy of the initial plan and the final plan once the project is finished.


Project Governance Plan

A Project Governance Plan develops the high-level governance arrangements documented in the approved Project Charter and the discussions held with the Project Sponsor and key stakeholders to discuss governance expectations and roles.

A comprehensive Project Governance Plan template is available in your downloadable Project Management Templates

Project Review and Closure Report Template


Project Review and Closure Report


Background



Briefly describe the background to the project.



Reason for closing the project



State the reason why this project is being closed this is usually because the outputs have been delivered but it may be closed for other reasons, e.g. a change in organisational priorities, loss of funding or deadline date reached.



Highlights and innovations



Describe any highlights of the project and any innovations used or developed by the project.


Project Performance



Summarise the actual performance of the project against the planned performance. Identify any variations and the reasons for the variance described.



Performance against objectives



Describe the actual performance of the project in relation to the achievement of the planned project objectives.


Performance against outcomes



Describe the actual performance of the project in relation to the achievement of targeted outcomes. Were all planned targeted outcomes achieved, to what degree?



Performance against schedule



Describe the actual performance of the project against the Project Schedule.


Performance against budget



Describe the actual performance of the project against the Project Budget.



Lessons learned



What lessons did you learn? Describe how you collected the lessons learned and what they are.


What worked well?



What processes helped you with the project? Were the risk management, quality and project documents useful? What would you do again?



What could be improved?


How would you change the processes for your next project? What would you not do again?



Closure Activities


Issues management




Risk management




Financial management




Records management




Post project responsibilities




Recommendations




Sign off



/ /



Project Manager




/ /



Project Sponsor



/ /



Project Customer


Wrap up


Gain commitment to action steps


What are the next steps to take?




Actions Steps





Project Risk Register Template

Document Control


Date


Version


Status


Action


Responsibility






td width="165">

Responsibility assigned to:


#


Describe Risk


Analysis


Treatment





Likelihood


(1-5)


Consequence


(1-5)


Rank


L x C


































































Project Scope Document Template

Document Control


Date


Version



Status


Action


Responsibility







Note: Where a Project Charter document has been prepared, summarise relevant sections below


Project Name



Background / Context



Project Sponsor



Project Client



Stakeholders



Product specification



Start Date



End Date



Key Deliverables



Key Milestones



Inclusions



Exclusions



Assumptions



Constraints



Key Risks



Project Manager



Project Team


Project Scope Management Plan

The Scope Management Plan is created during the projects Planning Process Phase and is considered a component of the Project Management Plan (PMP). The purpose of the Scope Management Plan is to document the defined scope management approach and processes, as well as the roles and responsibilities for Stakeholders participating in those processes.

The Scope Management Plan serves as a written reference guide. It describes how the project team will define and develop the project scope, create the Work Breakdown Structure (WBS), validate the scope, verify completion of project deliverables, control the scope baseline, and handle scope changes.

A comprehensive Project Scope Management Plan template is available in your downloadable Project Management Templates

Quality Assurance Log Template

Document Control


Date


Version


Status


Action


Responsibility







Exception ID Number


Review Date


Process Reviewed


Findings


Resolution


Resolution Date





































Quality Control Log Template

Document Control


Date


Version


Status


Action


Responsibility







Exception ID Number


Review Date


Deliverable


Reviewed


Findings


Resolution































Responsibility Allocation Matrix Template


Activity


Responsible


Accountable


Consult


Inform





































Wrap up


Gain commitment to action steps


What are the next steps to take?








Actions Steps







Scope Considerations Template


Briefly describe your project



Scope Inclusions


Scope Exclusions





















Assumptions




Constraints



SMART Objectives Template

Document Control


Date


Version


Status


Action


Responsibility







Project Objective Insert Name


Specific



Measurable




Realistic




Time-based



Write your objective


Stakeholder Analysis Template

Document Control


Date


Version


Status


Action


Responsibility







Key Stakeholder


Nature of impact consequences for Stakeholder /group


Importance and Involvement Rank


Individual or group affected by project


How will they influence the project?


At what stage?


How can the project take advantage of the Stakeholder?


(Skills)


What can the project


do for the


Stakeholder?


(Outcomes)


Level of influence:


Important


Influential


Mandatory


Beneficiaries


Impactees


Level of involvement:


Seek participation


Consult


Inform


Maintain awareness





































Supplier Evaluation Criteria Template

Document Control


Date


Version


Status


Action


Responsibility






Receiving reports are essential to verify that goods and services received were in a manner acceptable to the conditions and requirements of the contract prior to payment.

The following should be checked promptly:


Receiving goods


Rendered services


Documentation includes


Verify the items


Goods are in acceptable condition (free of defects)


Correct quantity agreed upon


Delivered in accordance with the contract terms


Effect on warranties and returns by delays



The services have been delivered in accordance with the terms of the purchase order/contract.



Date received


Quantity and description of items received


Vendor name


Purchase order, if applicable


Signatures verifying the items were received in good condition and that payment is authorised.


Devise a criterion to evaluate your suppliers performance.


Task/Supplier


Criteria


Weighting




















Total


100

Writing Project Documentation Checklist


Writing project documentation



Language clearly states who is responsible for what



Document correctly represents all data



Language that could possible mislead readers has not been used



Provides correct emphasis based on the data



Treats the views of others fairly and professionally



Clearly cites all sources used to write the report



Each alternative is presented in a clear and unbiased manner



All recommendations and conclusions are supported by facts presented in the report



All judgements, recommendations or comments are within the scope of the project or the organisations policies



Acknowledged and received permission to use copyrighted information used in the report



All material is pertinent to this project



Document has been checked for comments that might be misconstrued or cause conflict for the organisation



Gender-neutral wording used



Legal, regulatory and policy implications are clearly stated



Used organisational style guide (or if public sector the the Style Manual for authors, editors and printers)



Intellectual property rights implications dealt with


Additional Web-based Template Examples

You may find the following web-based templates useful as you work through your assessment modules.



  • Scope management plan- http://www.projectmanagementdocs.com/project-planning-templates/scope-management-plan.html#axzz54Ck2Z1i3

  • Work breakdown structure- http://www.projectmanagementdocs.com/project-planning-templates/work-breakdown-structure-wbs.html#axzz57WESidsX

  • Project Management Plan- http://www.projectmanagementdocs.com/project-planning-templates/project-management-plan.html#axzz54Ck2Z1i3

  • Project Charter http://www.projectmanagementdocs.com/project-initiation-templates/project-charter.html#axzz54Ck2Z1i3

  • Lessons learned report- http://www.projectmanagementdocs.com/project-closing-templates/lessons-learned.html#axzz54Ck2Z1i3

  • HR Management Plan- http://www.projectmanagementdocs.com/project-planning-templates/human-resource-plan.html#axzz54Ck2Z1i3

  • Skills analysis- http://euitt.com/wp-content/uploads/2012/03/Skills-Matrix-Template.xls (Includes a role matrix and gap analysis)

  • Communication Management Plan- http://www.projectmanagementdocs.com/project-planning-templates/communications-management-plan.html#axzz54Ck2Z1i3

  • Cost Management Plan- http://www.projectmanagementdocs.com/project-planning-templates/cost-management-plan.html#axzz54Ck2Z1i3

  • Quality Management Plan- http://www.projectmanagementdocs.com/project-planning-templates/quality-management-plan.html#axzz54Ck2Z1i3

  • Procurement Management Plan- http://www.projectmanagementdocs.com/project-planning-templates/procurement-management-plan.html#axzz54Ck2Z1i3

  • Risk Management Plan- http://www.projectmanagementdocs.com/project-planning-templates/risk-management-plan.html#axzz54Ck2Z1i3

  • Uploaded By : Akshita
  • Posted on : November 26th, 2024
  • Downloads : 0
  • Views : 225

Order New Solution

Can't find what you're looking for?

Whatsapp Tap to ChatGet instant assistance

Choose a Plan

Premium

80 USD
  • All in Gold, plus:
  • 30-minute live one-to-one session with an expert
    • Understanding Marking Rubric
    • Understanding task requirements
    • Structuring & Formatting
    • Referencing & Citing
Most
Popular

Gold

30 50 USD
  • Get the Full Used Solution
    (Solution is already submitted and 100% plagiarised.
    Can only be used for reference purposes)
Save 33%

Silver

20 USD
  • Journals
  • Peer-Reviewed Articles
  • Books
  • Various other Data Sources – ProQuest, Informit, Scopus, Academic Search Complete, EBSCO, Exerpta Medica Database, and more