ICT508InformationTechnologyProjectManagement Project Scenario Description
BACKGROUND
You are a Project Manager working forMaternity Stream International Pty Ltd(MSI).MSI is a small to medium enterprise based out of Perth in Western Australia (WA), but we have some staff located in Rockingham and Mandurah as well. Up to this point, MSI is focused on health service delivery solutions to WA Health.
AsidentifiedbyCapasso(2024),thereisagrowingtrendinincreasedICTusefortheprovisionofmaternity services.WAiswellplacedfromanetworkandinfrastructureperspectivetoleverage thistrendinsupport ofincreasedpopulationgrowthfromtheminingsector.Also,thepopulationinregionalWAhasincreased and hence varying and diverse health needs. It is the hope of WA country health service that remote communities, Aboriginal and culturally and Linguistically Diverse (CALD) people access various health servicesthatmeet uniqueandculturalneeds.Asmanystakeholdersexplorepossiblesolutions,MSIwants toconsiderasolutionthatenablesvirtualhealthcareforallpeopletoaccessurgentcare,accessspecialised care, and access key maternal services from home, hence reducing the need to travel.
Increasingly,theadoptionofHealthcareSoftwareasaService(HealthcareSaaS)isseeninmanyhealthcare entities as an option for providing services over the Internet. The implementation of a SaaS solution for maternity care can provide expectant mothers an alternative avenue to connect with their treating team. Health organisations use cloud-based software solutions to enhance accessibility to healthcare services across regions. Intended use cases for this solution include:
- Telehealth: enable remote/virtual consultations and remote patient monitoring, expanding access to care and improving patient convenience
- Appointment Scheduling: help healthcare practices manage appointments and other administrative tasks
- Billing management and other claims
- Data analytics: helps healthcare organisations analyse patient data to identify trends, improve care strategies, and optimise operations.
- Health information management and exchange: help labs manage samples, track results, and ensure quality control.
Withthissolution,MSImustensurethatSaaSprovidershaverobustdataprotectionmeasuresinplace.The organisation must ensure that SaaS solutions comply with strict regulations to protect patient privacy.
Given the level of interest in the product, additional stakeholders are forming to establish a more scalable business for expansion into other Australian markets.
The proposal put to the MSI Board involves theimplementation of a Healthcare SaaS1platform MaternityStreamSystem(MSS)tosupportinformationexchangeinthedeliveryoffourcriticalmaternity services, including pathology, imaging, pharmacy, and telehealth. The preliminary intent is to roll out a one-yearPilotProjectthatwillestablishthe MaternityStream System(MSS)foundation andthen expand onthisthroughthefollowingprojectphases.However,forthemoment,thefocuswillonlybeonthePilotProject.
TheMSIChiefInformationOfficer(CIO)(MrBenDover)isthedelegatedProjectSponsor,andhewillbe reportingdirectlytotheMSIChiefExecutiveOfficer(CEO)(MrsDonnaJenner).Youhavebeenselected astheProject Manager.Thismeansthat youareresponsibletotheCIOforimplementingandoverseeing thePilotProjectfrominitiationtoclosure.Ifthepilotprojectissuccessful,theintentisforyoutoassume the role of project manager for the following phases.
As a first step, you will need to develop key project initiation and planning materials for theBoard's approval (Stage Gate Approval for the Business Case See project timeline provided).These materials must deliver clarity regarding the business case and outline how the project can be implemented successfully(if approved) some of the materials to develop include a project charter and project management plan see details in Assignment 1 Information Sheet.
THEPROJECT
Theobjectivesoftheproject
The aimofthis project is tocreateastable, secure, effective, scalableand user-friendlymaternityservices solutionthatenhancestheprovisionoffourservicestoexpectant
mothers the target services include pathology, imaging, pharmacy and telehealth (remote patient consultations). MSS is a SaaS-based clinical information system2aimed to serve clients in Perth, RockinghamandMandurah.Thesystemwillallowalliedhealthstaff toaccessresources,attendvirtualmeetings,serviceregionalpatients, and engage inpatient-reportedoutcomemeasures deployed overthe Internet.
TosupportMSIsystems,youwillneedtoimplementarangeofother elements.Apreliminarytechnicalarchitecturehasbeendeveloped
for this system.This architecture and some descriptions of key system elements are available throughthe LMSundertheAssessment Informationheading.Youwill needto ensurethat you understand the project deliverable, MSS architecture, and proposed project timeline.
Considerations and regulatory requirements include patient data privacy, security protocols, and identity and access management.
Key issues to be addressedToimplementthisproject,thefollowingimportantissueswillneedtobeaddressed:
- A "Healthcare SaaS" refers to a cloud-based software application specifically designed for the healthcare industry, allowing healthcareproviderstoaccessandmanagepatientdata,clinicaltools,andadministrativefunctionsthroughaninternetconnectioninsteadofrelyingonlocal servers, typically accessed through a subscription model; essentially, it's a software service tailored to healthcare needs hosted on thecloud.
- Aclinical information system (CIS)is a computer-based system used in healthcare settings to collect, store, manage, and readily accesspatient data like medical history, lab results, imaging studies, medications, and clinical notes, allowing healthcare professionals to makeinformeddecisionsatthepointofcareandstreamlineworkflowsbysupportingtaskslikechartingandmedicationadministration;essentially,it's a digital platform that centralises patient information for optimal clinical decision-making.
- The Board is still not convinced that this will be a feasibleThe materials that you provide in this Assignment will, therefore, have to be detailed and convincing, or you may find yourself out of a job.
- You, as the PM, will need to engage one or more experienced contractors who can coordinate/implement this solution under our control. This identification and selection of contractors will be a high priority for your efforts. When conducting this selection process, it is recommended that you implement aweightedanalysisapproachasapartofaRequestforTender (RFT) preparation process.This weighted analysis approach will be discussed later as this is criticalintheselectionofasuitableSaaSproviderandother Third-Partyproviderstoworkonthis
- MSIisnotadedicatedtechnologyConsequently,settingup integratedsystems is beyond the capabilities of MSI.For this reason, outsourcing will be important.Tip: a weighted analysis will need to be conducted to choose the most suitable SaaS provider
- You may also want to think about aspects such as leasing infrastructure and other equipment, if needed, to help minimise up-front costs.
- At the end of the project, we will need to ensure that MSIcan maintain and manage the maternity servicesplatformitcreatedwithoutthe ongoingsupportoftheprojectThiswillbeachieved via a project to support the (P2S) handover process. NB: This is where the SME will provide a handover to the in-house IT support team. This may mean that we need to bring skills and IntellectualProperty(IP)intothecompanyorsetupreliablerelationshipswithotherorganisations, who can do this for us.
KeyMilestones
You will need to achieve the following key milestones to meet the Boards defined requirements.Please note that these only reflect some of the pertinent high-level objectives.You will need to work out other key milestones involved in this approach.The subordinate milestones that you select must allow the following to be achieved.
Date |
Event/Milestone |
03Feb2025 |
PreparationsCommence.Youwillbegindevelopinginformalteamrelationships(e.g. start talking to possible contractors and internal stakeholders) and complete the development of the materials required by the Board (your assignment).These discussionscanberepresentedbyaskingthelecturerquestions(e.g.,duringthe workshops). |
31March2025 |
SubmissiontotheBoard.SubmittherequiredprojectmaterialstotheBoard,sothey can decide whether to proceed with the project. |
25April2025 |
BoardApproval(StageGateApprovalfortheBusinessCase).Theprojectcharterand other documents submitted to the board are approved. |
28April2025 |
Planned formal project Start Date.This milestone will trigger the formal allocation ofprojectfundsfromthisdate,anditwillonlybeinitiatediftheBoardapprovesyour submission.Untilthisisauthorised,otherstaffandproviderscannotbeengaged formallyonapaidbasis. |
23June2025 |
Engage Providers.By this date, you need to contractually engage one or more technical contractors to conduct the development work.This activity will require an RFT process.The key steps in this process are outlined in the following cell. Additionally, you will need toengage a SaaS provider and Third-Party Developers for extendedcustomisation.WealsoneedLevel2/3support(tobeprovidedbytheSaaS providersupportteamandexperts)andServiceDeskfacilities(anRFTmaynotbe necessaryforthese). |
11August2025 |
FinaliseNetworkLogicalDesign(inWS6)andFinaliseSoftwareDevelopment(WS8).Thenetworklogicaldesignmustbecompleted,andthesoftwaredevelopmentinthe development environment) |
10November 2025 |
Stage Gate Approval for the Project to go into the execution phase.The MSI staff andengagedproviderswillneedtocompletethe solutiondesignsanddevelopments priortothisdate;afterthis,theprojectwillentertheexecutionphaseseethisstage gateontheprojecttimeline. |
20March2026 |
Go-LiveApproval.Thisisthedatethatallservicesgo-live.TheBoardhaveidentified this as a hard-wall milestone (e.g. it cannot be moved), because it is designed to coincide with MSIs anniversary of the PhD candidates graduation who created this ideaduringtheirresearch.Beforethisdate,therewillbeafullone-monthawareness campaign for local healthcare providers and referrers. To avoid any possible embarrassment after opening, the entire system must be fully operational and stable by this date. ThesameSaaSplatformandserviceswillbethesame Fromaninfrastructureperspective,allthreesitesareidentical Currently, pathology machinery is housed in Perth, but patients can collect their specimens at all three sites. Pathologysystemsareavailableatallsitestoidentifyresults |
29May2026 |
FormalPilotProjectClosure.ThePilotProjectwillbeclosed(SeeTopic11),andfinal reportsandotherdeliverablesmustbeprovidedbythisdate.IfthePilotissuccessful, theprojectis intendedtocontinue,butthePilotProjectClosureprocessmuststillbe done by this date. |
YourTeam
Apart from you as the Project Manager, the Board has indicated that you will have access to the following people, so they can give the advice needed to prepare the project documentation (that needstobedeliveredtotheBoard).Thesepeople/organisationswillthenbeengagedasnecessary to support the project.
Person |
Rolesandadditionalinformation |
Board |
The Boards only role will be to determine whether the project will go ahead.If they approve the project, the allocated funds will be controlled by the Project Sponsor to facilitate the achievement of the project objectives.As much as they will not be highly active participants, you willneed to keep theBoard informed on progress at astrategiclevel(typically through the ProjectSponsor).However,pleaserememberthattheywouldnotnormallyhaveanydirectday- to-day management involvement. Within the board, a local government seed funding project officer, Murdoch University commercialisation team, hospital representatives and female representatives from the maternity womens network will be present. |
Dr Donna Jenner,PhD (Founder) |
Donna is responsible to the Board and is also the primary Executive Member of the Board.In particular, she is responsible for the operational management of MSI.The CEO will have some strategic oversight requirements for the Project, and you will need to provide some reports to her through theProject Sponsor.However, shewould not normally get involved in the day-to- day management of the project. |
Ben Dover (CIO&Project Sponsor) |
BenistheChiefInformationOfficer(CIO)fortheorganisationandisthereforeprimarily focused onbroaderaspectsthanthisproject.TheCIOisthereforeresponsibletotheCEOforallaspects of ICT utilised by MSI. As the Project Sponsor, he will be responsible for the strategic coordination of this project and its budget. You are directly responsible to him for the managementandcontroloftheproject,andyouwould,therefore,needtoproactivelykeephim uptodateonprogress.Additionally,youwouldneedtoengagehiminkeyoperationaldecisions. However, he would not typically get involved in direct operational management (unless he thinks there is a problem, and you are not doing your job you do not want this to happen). Therefore, you will generally keep him aware of the project through formal and informal communication (as discussed in Topic 8), and you will do the bulk of the management and coordination that is necessary. |
BillSykes (LegalSupport) |
He is a legal and contractual expert.In particular, Bill can support contract development and negotiationswithsuppliersandcontractors.Additionally,hecanhelpwiththedevelopmentof the license agreements (e.g., End User License Agreements (EULA)) that will be necessary for client engagement. |
DonMorrison (SecurityExpert) |
Don is our expert on security issues and the associated legal requirements(e.g., implementing thesolutionsinaccordancewiththePrivacyAct).Heisanoutsideconsultantbutwillbeavailable as an internal stakeholder to guide security activities once the project commences. |
Perera Kinley (Data migration expert) |
Kinley is our data migration expert with experience in data migration in SaaS implementation. LikeDon,heisanoutsideconsultantwhowashiredandwillbeavailablefromwhentheproject commencestillitsclosure. |
AshMclelland (TestLead) |
Ash willberesponsiblefor ensuring thequality and successfuldeployment oftheSaaSsolution bycoordinatingalltestingactivities suchasbeinginvolvedintestplanning,testenvironment setup,testcasedesign,riskassessment,facilitatingUATandothers. |
Third-Party Developers |
From the preliminary RFT investigation, you have identified three companies that may be able tomeetat leastpart oftheneedsfor thisproject.TheseareStreamTech, DCPlus,and DemSet. You will need to discuss the issues with these companies, so you can develop ideas, possible solutions and selection criteria.This information will then shape the RFT, as discussed above. Please note that the timeline for this contractual engagement is very short, so you will need to start working on this very soon.Please also take into account the following notes: In this case,you willonly need to do afinancialanalysis and WeightedAnalysis part of the RFT development. |
These organisations are separate from MSI, and they will not work for you or assist directly in your design work unless they are engaged as a contractor.Consequently, youwillneedtoworkwiththemasopenlyaspossible,butyouwillnothaveanycontrol over them until a formal contract is in place. |
|
Suppliers |
You will need to engage appropriate suppliers/service providers for the hardware and other equipment. Additionally, you will need to find an appropriate Service Desk that will be able to provide support for the organisational clients when the system goes live.Please note that you will not provide Service Desk support to all users, as this would be too expensive. |
OtherStaff |
Ifyou need any additional staff/expertiseto completethe project successfully, you willhaveto createproposals fortheProjectSponsor.Intherealworld,youwouldneedtoexplainthecost, time,qualityandscopeimplications.Forthisassignment,youwillnotneedtodothis.Forthis assignment,youcanassumethatyouhavealreadyidentifiedthatyouwillneedstafftosupport theProject Office, which you will have to establish on the Project Start Date.Some of the additional staff that you will need to engage will be required to support administration, payments, Quality Assurance, training, and procurement. |
PreliminaryCost/RevenueInformation
A preliminary analysis has indicated that the following costs and revenues are likely to accrue from the implementation of thePilot Project.These are Rough Order of Magnitude (ROM) figures only, but they should provide a useful starting position for the analysis.
Description |
Year0 |
Year1 |
Year2 |
Year3 |
ROMCosts/Expenditures |
$705,000 |
$590,000 |
$420,000 |
$360,000 |
ROMBenefits/Revenues |
$256,000 |
$815,000 |
$1,120,000 |
$1,331,000 |
Assumptions
The following base assumptions need to be taken into account when analysing the preceding ROM cost/revenue figures and the associated project aspects:
- These figures do not take into account the discount effects related to inflation and the cost of
- The inflation rate is expected to remain at about 3% per annum for the next four
- This project will be funded through debt(a loan from the Bank).There will be no establishment costs(asthiswillbeanextensionofexistingfundingagreements),andthebankhasofferedafixed loan rate of 4.8% per annum.
- Year0commencesattheProjectStartThefollowingyearsareconsecutive.
- The ROM expenditures take into account the software licencing fees for the SaaS platform, costs associated with consulting on configuration, system integration, and data migration provided by the SaaS vendor and third-party providers.
- Software licensing is expected to take 45% of the budget, implementation serviceswill take 30%, User training and support 15%, and data migration and cleansing 10%
- Revenues in Year 0 relate to project feasibility study, project planning, stakeholder consultations and engagement of clients after User Acceptance Tests (UAT).
Youcannow proceedtoreadtheSystemTechnicalArchitectureandProject Implementation Timeline.