MS Project - Breakdown Structure - ROI Assignment
- Country :
Australia
-
If the client decides not to include a feature in a project, what should you do with the related tasks in MS Project?
-
The lectures recommend you reserve the first level of the work breakdown structure for what type of scope?
-
How much work is in a fixed work task lasting 6 days with 2 people working at 300%?
-
What is the predicted ROI for a sprint with a sprint backlog value of $6,000 and a sprint cost of $8,000? Give your answer as a percentage.
-
You have just completed 3 projects as detailed in the table below. Calibrate the SIMPLIFIED-COCOMO model provided in the unit materials and predict the duration of a project with 34,000 lines of code.