Stakeholder Analysis Assignment
- Country :
Netherlands
QUESTION 1
Richard is currently assessing his project stakeholders influences, interests, expectations, risk tolerance and engagement levels. This relates to which of the following tools and techniques?
A. Stakeholder register
B. Stakeholder analysis
C. Autocratic decision making
D. Expert judgement
QUESTION 2
Stakeholder identification is a continuous process. Which of the following statements about stakeholders is incorrect?
A. Positive stakeholders benefit from the outcome of a project
B. A project manager needs to focus on the positive stakeholders since their needs are best served by the project
C. Overlooking negative stakeholders can result in an increased likelihood of failure
D. Stakeholders can have conflicting or differing objectives
QUESTION 3
Alex is managing a hotel refurbishment project. He has identified his projects key stakeholders. Alex now wants to expand this list of stakeholders and convert it to a comprehensive list of project stakeholders. What should Alex do?
A. Do not spend more time on identifying the non-key stakeholders
B. Seek expert judgment from the identified key stakeholders
C. Request the project sponsor to provide the details of the remaining stakeholders
D. Carry out a stakeholder analysis with the identified key stakeholders
QUESTION 4
Jane has recently finalized her project management plan and has also got it approved. She is managing a complex manufacturing process improvement project. The project stakeholders continuous support and commitment is an absolute must for the success of the project. Which of the following are the most crucial stakeholder management processes at this stage?
A. Plan Stakeholder Engagement and Manage Stakeholder Engagement
B. Identify Stakeholders and Plan Stakeholder Engagement
C. Manage Stakeholder Engagement and Monitor Stakeholder Engagement
D. Plan Stakeholder Engagement and Monitor Stakeholder Engagement