Student Version
right-1080462003810342265Portfolio
Student Version
020000Portfolio
Student Version
07265670ICTTEN622
Produce ICT network architecture designs
00ICTTEN622
Produce ICT network architecture designs
CONTENTS
TOC o "1-3" h z t "RTO Works Heading 1,1" Section 1: Preparation and design PAGEREF _Toc131108507 h 4Section 2: Network design finalisation PAGEREF _Toc131108508 h 10
Student name: Assessor: Date:
Section 1: Preparation and designICT Network Architecture Design 1
Complete this section for ICT network architecture design 1. If you are completing this in Peach Institute, information about the network and work details will be as per the information discussed at the meeting with your assessor. If you are completing this for your own business, this will be as per the networks you are accessing.
Work details
Outline the details of the work as relevant to the networks to be designed. As a minimum this must include:
scope of the work to completed including overall objectives
the business specifications
timelines within which the work must be completed
budget allocated
procedures to be followed, including security arrangements
issues/problems/opportunities that the client has flagged
current and future traffic demands. Legislation, codes, regulations and standards
Provide an example of each that you must adhere to whilst completing your work managing network traffic. Explain how each example you provide applies to your work. Site access
Draft an email that could be sent to a client to organise site access. Proposed ICT network architecture design
Document your proposed network design using a network diagram tool.
Make sure you also document the hardware and software that will be needed.
Attach the diagram of your design diagram to your Portfolio. Network architecture design report
Provide a report on the following:
Impact of the network design on the business requirements
Forecasted traffic and how the network design will be able to cater for this
Performance parameters which will be used to assess the network and the likely performance based on the design. Performance parameters must reflect standard industry benchmarks.
Costs of hardware and software proposed
Overall recommendations for preferred solutions including hardware and software.
61859414351000 Attach: Network diagram Design 1
ICT Network Architecture Design 2
Complete this section for ICT network architecture design 2. If you are completing this in Peach Institute, information about the network and work details will be as per the information discussed at the meeting with your assessor. If you are completing this for your own business, this will be as per the networks you are accessing.
Work details
Outline the details of the work as relevant to the networks to be designed. As a minimum this must include:
scope of the work to completed including overall objectives
the business specifications
timelines within which the work must be completed
budget allocated
procedures to be followed, including security arrangements
issues/problems/opportunities that the client has flagged
current and future traffic demands. Legislation, codes, regulations and standards
Provide an example of each that you must adhere to whilst completing your work managing network traffic. Explain how each example you provide applies to your work. Site access
Draft an email that could be sent to a client to organise site access. Proposed ICT network architecture design
Document your proposed network design using a network diagram tool.
Make sure you also document the hardware and software that will be needed.
Attach the diagram of your design diagram to your Portfolio. Network architecture design report
Provide a report on the following:
Impact of the network design on the business requirements
Forecasted traffic and how the network design will be able to cater for this
Performance parameters which will be used to assess the network and the likely performance based on the design. Performance parameters must reflect standard industry benchmarks.
Costs of hardware and software proposed
Overall recommendations for preferred solutions including hardware and software. 61859414351000 Attach: Network diagram Design 2
Section 2: Network design finalisationICT Network Architecture Design 1
Final design feedback
Outline the final feedback you received from your assessor and how you will incorporate this into your final design.
Provide your final design and attach it to your Portfolio. Training and support
Outline the training and support requirements that will be needed to implement the new design. Hardware and software suppliers
Based on the hardware and software solutions you identified in Section 1 of your Portfolio, contact two possible suppliers. Contact can be completed through a review of the suppliers website and identifying the specifications and costs for the equipment that will be required as part of the network you have designed.
Provide screenshots of the information you research. Final design
Include a request for approval for your design here. 61859414351000 Attach: Final design 1
Screenshots for supplier information
ICT Network Architecture Design 2
Final design feedback
Outline the final feedback you received from your assessor and how you will incorporate this into your final design.
Provide your final design and attach it to your Portfolio. Training and support
Outline the training and support requirements that will be needed to implement the new design. Hardware and software suppliers
Based on the hardware and software solutions you identified in Section 1 of your Portfolio, contact two possible suppliers. Contact can be completed through a review of the suppliers website and identifying the specifications and costs for the equipment that will be required as part of the network you have designed.
Provide screenshots of the information you research. Final design
Include a request for approval for your design here. 61859414351000 Attach: Final design 2
Screenshots for supplier information
-989965-1079321003810342265Portfolio
Student Version
020000Portfolio
Student Version
07265670ICTPMG613
Manage ICT project planning
00ICTPMG613
Manage ICT project planning
CONTENTS
TOC o "1-3" h z t "RTO Works Heading 1,1" Section 1: Project Management Plan PAGEREF _Toc128486082 h 4Section 2: Project schedule PAGEREF _Toc128486083 h 6Section 3: Project budget PAGEREF _Toc128486084 h 10
Student name: Assessor: Date: Business this assessment is based on: Project descriptions:
Section 1: Project Management Plan
PROJECT 1: Include name of the Project
Project management models
Discuss the most suitable project management model/systems development approach for this project.
Consider the following in your response:
Why is this methodology suitable rather than others?
What tailoring is appropriate in regards to the project methodology you have chosen? Project Management Plan
Write a Project Management Plan using the template in the Simulation Pack.
List the name of your document here and attach your Project Management Plan to this section of your portfolio. If you are completing this for a project in your workplace, you must also use the template in the Simulation Pack for your Project Management Plan. 5937258191500Attach: Project Management Plan
PROJECT 2: Include name of the Project
Project management models
Discuss the most suitable project management model/systems development approach for this project.
Consider the following in your response:
Why is this methodology suitable rather than others?
What tailoring is appropriate in regards to the project methodology you have chosen? Project Management Plan
Write a Project Management Plan using the template in the Simulation Pack.
List the name of your document here and attach your Project Management Plan to this section of your portfolio. If you are completing this for a project in your workplace, you must also use the template in the Simulation Pack for your Project Management Plan. 5937258191500Attach: Project Management Plan
Section 2: Project schedule
Complete this section for each project. If you are completing this for the case study organisation, use the Simulation Pack information. If you are completing this for your own workplace projects, you will need to include the information based on this.
PROJECT 1: Include name of the Project
Work Breakdown Structure
Include the title of your Work Breakdown Structure here and attach it to your Portfolio. Project effort and duration
Use your WBS to go through the project activities required and identify the following:
Optimistic estimation of each activity (best case scenario).
Pessimistic estimation of each activity (worst case scenario).
Most likely time (best guess).
Also use the PERT formula to develop and document the task estimation here.
Hint: Remember you will need to have watched the video in your learning materials about estimating tasks and dependence. Gantt Chart
Create a Gantt Chart based on your work. This will be the Project Schedule.
List the name of your document here and attach it to your Portfolio. Schedule control
Document here how you will ensure that the schedule you have developed is kept to i.e. schedule controls.
6445255651500Attach: Work Breakdown Structure
Gantt Chart
PROJECT 2: Include name of the Project
Work Breakdown Structure
Include the title of your Work Breakdown Structure here and attach it to your Portfolio. Project effort and duration
Use your WBS to go through the project activities required and identify the following:
Optimistic estimation of each activity (best case scenario).
Pessimistic estimation of each activity (worst case scenario).
Most likely time (best guess).
Also use the PERT formula to develop and document the task estimation here. Gantt Chart
Create a Gantt Chart based on your work. This will be the Project Schedule.
List the name of your document here and attach it to your Portfolio. Schedule control
Document here how you will ensure that the schedule you have developed is kept to i.e. schedule controls.
6445255651500Attach: Work Breakdown Structure
Gantt Chart
Section 3: Project budgetComplete this section for each project. If you are completing this for the case study organisation, use the Simulation Pack information. If you are completing this for your own workplace projects, you will need to include the information based on this.
PROJECT 1: Include name of the Project
Areas of project spend
List all the resources that are required for the project and that will incur costs.
Remember to include physical resources, as well as human resources.
Project costs estimation
For each of the items you have listed above, include the dollar amount.
Further, outline when the budget for the project will be received so as to be clear on cash flow.
Budget control
Document here how you will ensure that the budget you have developed is kept to i.e. budget controls.
List at least three actions that you will take to ensure budget control.
PROJECT 2: Include name of the Project
Areas of project spend
List all the resources that are required for the project and that will incur costs.
Remember to include physical resources, as well as human resources. Project costs estimation
For each of the items you have listed above, include the dollar amount.
Further, outline when the budget for the project will be received so as to be clear on cash flow.
Budget control
Document here how you will ensure that the budget you have developed is kept to i.e. budget controls.
List at least three actions that you will take to ensure budget control.