Project Management Analysis of HELIX Automotives 35Challenge Initiative PMGT602

Flat 50% Off Order New Solution
Added on: 2024-11-26 06:00:15
Order Code:
Question Task Id: 487832

The HELIX Automotive Co. Ltd is facing a period of significant change due to Covid 19 pandemic situation, driven by poor profitability, excess finished stock, overcapacity and less demand from customers. This is due to the process of selling cars from the existing stocks which may not be able to fulfil customer requirements based on their preferences. Shifting their business models away from mass production toward mass customization and build-to-order is the best option towards vehicle manufacturer to overcome these issues. Conversion of the business model from the ready stock to build to order would increase existence system efficiency in terms of order execution and information flow integration. Therefore, in order to compete with the current trend of build-to-order vehicles manufacturing, HELIX Automotive Co. Ltd implemented a 35Challenge project to develop framework based on customer specification in which a vehicle can be built and transport to customer in minimal lead times within 15 days order-to-delivery (OTD) time as the ultimate goal for the project.


However, 35Challenge project was not successfully implemented due to project management team unable to:



  1. i) develop a proper project scope,

  2. ii) balance between scope and time to achieved project goal,


iii) identify appropriate resources,



  1. iv) clearly state contingency plan if there is risk occur.


Due to this limitation faced, 35Challenge project was unable to meet customer requirements, because vehicles built to individual specification could not be delivered within required time a 20% of the development not based on customer specification. The project management team faced obstacles in the project due to a poorly written project charter due to improper work authorization as the responsibilities and roles not clearly stated in project charter.


The CEO is concerned that the 35Challenge project is a crucial project to meet the automotive market competency in meeting the build-to-order trend and the CEO has decided to recover the 35Challenge project.



  1. In order for the organization to ensure timely completion of the 35Challenge project, they performed some main planning tasks including Sequencing activities to review the activity list and project scope statement. Describe any two (2) sequencing activities involved in the project and explain four (4) reasons for Creating Dependencies by providing an example which related to the project. (20 marks)


Sample Answer:



  • Which process group/phase is this? Which knowledge area(s) is this related to? project planning, project schedule management

  • The question looking for Process? Or input, tools and techniques, or output? tools and techniques of Sequence Activities

  • PDM, determining activity Dependency, creating network diagram, project management informative system, identify leads and lags

  • Prioritise activities F-S

  • Maximise resources resources can be arranged according floats

  • Develop full project schedule- to develop schedule baseline

  • Identify full project duration



  1. The management of this organization believed that People are our most important asset. Discuss the importance of Project Resource Management associated with the project, and describe TWO (2) main outputs produced as a part of project resource management planning. Identify and explain ONE (1) component in team management plan that can be used to map work described in Work Breakdown Structures (WBS) to the people responsible for performing the work. (20 marks)


Sample Answer:



  • Which process group/phase is this? Which knowledge area(s) is this related to? project planning, project resource management

  • The question looking for Process? Or input, tools and techniques, or output? project resource management plan process, outpus.

  • Outputs: Project Resource Management Plan (explain what is it and what should be included in the document), Team Charter (explain what is it and what should be included in the document)

  • Team management plan component: Resource breakdown structure (RBS) (explain what is it and what should be included in the document)



  1. The case study clearly stated that the project does not successfully completed due to the several factor. As a project analyst, you are assigned by the project manager to prepare a complete risk register as a guidance for project team to run the execution. Four (4) risks should be identified and briefly describe to ensure project team understand risk register developed. (20 marks)


Sample Answer:



  • Which process group/phase is this? Which knowledge area(s) is this related to? project planning, project risk management

  • The question looking for Process? Or input, tools and techniques, or output? identify risk, risk register as the output.

  • Risk Register

































Risk statement



Type of risk



probability



Impact on/level



Risk Score/priority



Risk Owner



Risk Response strategy/Action



1. Customer request to change design last minute causing delay to delivery



Negative risk



high



Schedule/high



Top priority



Sales manager



Risk avoidance


- Imposing hard deadline for change request



2. Unavailability of parts needed for customization causing some scope cant be completed



Negative risk



low



Scope/mid



medium



Procurement manager



Risk mitigation


- Identify more than one suppliers for parts


  • Uploaded By : Akshita
  • Posted on : November 26th, 2024
  • Downloads : 0
  • Views : 135

Order New Solution

Can't find what you're looking for?

Whatsapp Tap to ChatGet instant assistance

Choose a Plan

Premium

80 USD
  • All in Gold, plus:
  • 30-minute live one-to-one session with an expert
    • Understanding Marking Rubric
    • Understanding task requirements
    • Structuring & Formatting
    • Referencing & Citing
Most
Popular

Gold

30 50 USD
  • Get the Full Used Solution
    (Solution is already submitted and 100% plagiarised.
    Can only be used for reference purposes)
Save 33%

Silver

20 USD
  • Journals
  • Peer-Reviewed Articles
  • Books
  • Various other Data Sources – ProQuest, Informit, Scopus, Academic Search Complete, EBSCO, Exerpta Medica Database, and more